Gas pressure regulating box Download PDF

Info

Publication number
CN205877717U
CN205877717U CN201620827647.6U CN201620827647U CN205877717U CN 205877717 U CN205877717 U CN 205877717U CN 201620827647 U CN201620827647 U CN 201620827647U CN 205877717 U CN205877717 U CN 205877717U
Authority
CN
China
Prior art keywords
pressure
pipe
gas
ball valve
regulating box
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620827647.6U
Other languages
Chinese (zh)
Inventor
张宏远
叶承志
刘学茂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Heyuan New Austrian Gas Co Ltd
Original Assignee
Heyuan New Austrian Gas Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Heyuan New Austrian Gas Co Ltd filed Critical Heyuan New Austrian Gas Co Ltd
Priority to CN201620827647.6U priority Critical patent/CN205877717U/en
Application granted granted Critical
Publication of CN205877717U publication Critical patent/CN205877717U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sampling And Sample Adjustment (AREA)

Abstract

The utility model discloses a gas pressure regulating box belongs to gas pressure regulating equipment technical field, and it includes the box, be equipped with intake pipe and outlet duct in the box, the parallel connection has two pressure regulating pipelines between intake pipe and the outlet duct, and voltage regulator tube curb gas direction of delivery has connected gradually first ball valve, filter, second ball valve and voltage regulator through the gas pipe, and the gas pipe in two pressure regulating pipelines between filter and the second ball valve is connected through the branch pipe, and the outlet duct is connected with the exhaust stack, and the exhaust stack is equipped with in the one end of being close to the outlet duct and diffuses the valve, and the other end of exhaust stack lies in the box outside. The utility model discloses an enlarge on -line maintenance's application range through the structure that improves the pressure regulating box, prevent that the gas from freezing, in time deal with the gas and leak the proruption situation.

Description

Fuel gas pressure-regulating box
Technical field
This utility model relates to Gas Regulator technical field, and specifically, it relates to fuel gas pressure-regulating box.
Background technology
Fuel gas pressure-regulating box is ingredient important in combustion gas transmission system, and its Main Function is regulation and stablizes combustion gas system System pressure, it is ensured that combustion gas transmission safety and stablization.At present, fuel gas pressure-regulating box is divided into single channel, two-way and multichannel, and user is according to demand Carry out selectivity installation.The once accident such as combustion gas generation leakage in gaseous-pressure generation exception or pressure regulating box in fuel gas pressure-regulating box Time, skilled industrial worker needs in time combustion gas transmission system to be debugged, keeped in repair.
Chinese utility model patent Granted publication is CN 205101868U, and authorized announcement date is on March 23rd, 2016, should Utility model disclose a kind of can the single channel fuel gas pressure-regulating box of on-bne repair, it includes casing, is fuel gas inlet below casing, even Connect and after the inlet tube of fuel gas inlet penetrates casing, be sequentially connected with the composition inlet pressure gauge of pressure regulation pipeline, filter, pressure regulator, put Raw edge, in-line relief valve and delivery gauge, the outlet conduit of pressure regulation pipeline passes casing and is connected with gas outlet, at inlet tube Install between road and outlet conduit one with pressure regulation pipeline the bypass that connects, this bypass farther includes affixed with inlet duct Imported valve and the affixed outlet valve of outlet conduit, be connected between imported valve with outlet valve and have suction flange, standby Filter, standby pressure regulator and outlet(discharge) flange.This fuel gas pressure-regulating box is also connected with bypass, and skilled industrial worker can pass not interrupting combustion gas Maintenance work is carried out in the case of defeated.But, this pressure regulating box comes with some shortcomings: 1) when pressure regulation pipeline and bypass in filter or When pressure regulator exists fault, skilled industrial worker has to interrupt combustion gas transmission and keeps in repair, and the scope of on-line maintenance is restricted;2) In fuel gas pressure-regulating box, combustion gas cannot carry out selectivity heating according to ambient temperature, and combustion gas is likely to occur to be freezed;3) in pressure regulating box When combustion gas occurs leakage, technical staff cannot tackle emergency situations in time.
Therefore, it is necessary to design a kind of novel gas pressure regulating box, this fuel gas pressure-regulating box can expand making of on-line maintenance By scope, prevent combustion gas from freezing, in time reply gas leakage emergency situations.
Utility model content
This utility model aims to provide a kind of fuel gas pressure-regulating box, limitation existing during to solve pressure regulating box on-line maintenance Property, combustion gas can occur freezeout and skilled industrial worker cannot tackle gas leakage situation etc. in pressure regulating box in time under low temperature state Problem, expands the range of on-line maintenance, prevents combustion gas from freezing by improving the structure of pressure regulating box, and reply combustion gas in time is let out Leakage emergency situations.
Fuel gas pressure-regulating box, including casing, is provided with air inlet pipe and escape pipe, between air inlet pipe and escape pipe also in described casing Be connected with two pressure regulation pipelines, surge pipe curb fuel gas transmission direction by Gas Pipe be connected with in turn the first ball valve, filter, Two ball valves and pressure regulator, in described two pressure regulation pipelines, the Gas Pipe between filter and the second ball valve is connected by arm, Escape pipe connects exhaust stack, and exhaust stack is provided with diffusion valve in the one end near escape pipe, and the other end of exhaust stack is positioned at casing Outside.
Preferably, described air inlet pipe along combustion gas transmission direction be sequentially provided with heater and boost gauge assembly, described in put Dissipate valve and be provided with outlet pressure table assembly, boost gauge assembly and outlet pressure table along the escape pipe on rear side of combustion gas transmission direction Assembly all includes that needle valve and Pressure gauge, described heater, boost gauge assembly and outlet pressure table assembly are all electrically connected with Instrument for intelligently sampling, instrument for intelligently sampling is provided with oil gas sensor and temperature sensor, and instrument for intelligently sampling side is provided with reception electricity Line.
Preferably, described exhaust stack connects exhaustor, and exhaustor is provided with the 3rd ball valve, the 3rd ball valve electrical connection intelligence Energy Acquisition Instrument, described casing side is provided with nitrogen tube, nitrogen tube is provided with condenser pump.
The utility model has the advantage of: this fuel gas pressure-regulating box can expand the use model of on-line maintenance by improving its structure Enclose, prevent combustion gas from freezing, in time reply gas leakage emergency situations.
Accompanying drawing explanation
In order to be illustrated more clearly that this utility model embodiment or technical scheme of the prior art, below will be to embodiment Or the accompanying drawing used in description of the prior art does and introduces simply, it should be apparent that, the accompanying drawing in describing below is only this Some embodiments of utility model, for those of ordinary skill in the art, on the premise of not paying creative work, also Other accompanying drawing can be obtained according to these accompanying drawings.
Fig. 1 is the structural representation of fuel gas pressure-regulating box.
In figure, casing 1, air inlet pipe 11, escape pipe 12, the first ball valve 2, filter 21, the second ball valve 22, pressure regulator 23, Arm 24, exhaust stack 3, diffusion valve 31, heater 4, Pressure gauge 5, needle valve 51, instrument for intelligently sampling 6, oil gas sensor 61, temperature Degree sensor 62, receives electric wire 63, exhaustor 7, the 3rd ball valve 71, nitrogen tube 8, condenser pump 81, Gas Pipe 9.
Detailed description of the invention
Being restricted to solve pressure regulating box on-line maintenance scope, combustion gas can occur freezeout and skill under low temperature state Art workman cannot tackle in pressure regulating box the problems such as gas leakage situation in time, expands online dimension by improving the structure of pressure regulating box The range repaiied, prevents combustion gas from freezing, in time reply gas leakage emergency situations, and this utility model provides fuel gas pressure-regulating box.
Below in conjunction with the accompanying drawing in this utility model, the technical solution of the utility model is clearly and completely retouched State, it is clear that described is only a part of embodiment of the present utility model rather than whole embodiments.Based on this practicality Embodiment in novel, it is every other that those of ordinary skill in the art are obtained on the premise of not paying creative work Embodiment, broadly falls into the scope of this utility model protection.
Embodiment 1: fuel gas pressure-regulating box, including casing 1, is provided with air inlet pipe 11 and escape pipe 12, air inlet pipe in described casing Between 11 and escape pipe 12 and be connected with two pressure regulation pipelines, surge pipe curb fuel gas transmission direction is sequentially connected with by Gas Pipe 9 There are the first ball valve 2, filter the 21, second ball valve 22 and pressure regulator 23, filter 21 and the second ball valve 22 in two pressure regulation pipelines Between Gas Pipe 9 be connected by arm 24, escape pipe 12 connects exhaust stack 3, and exhaust stack 3 is near the one of escape pipe 12 End is provided with diffusion valve 31, and it is outside that the other end of exhaust stack 3 is positioned at casing 1.
Described air inlet pipe 11 is sequentially provided with heater 4 and boost gauge assembly, diffusion valve 31 edge along combustion gas transmission direction Escape pipe 12 on rear side of combustion gas transmission direction is provided with outlet pressure table assembly, boost gauge assembly and outlet pressure table assembly All include that needle valve 51 and Pressure gauge 5, heater 4, boost gauge assembly and outlet pressure table assembly are all electrically connected with intelligence Acquisition Instrument 6, instrument for intelligently sampling 6 is provided with oil gas sensor 61 and temperature sensor 62, and instrument for intelligently sampling 6 side is provided with reception Electric wire 63, exhaust stack 31 connects exhaustor 7, and exhaustor 7 is provided with the 3rd ball valve 71, and the 3rd ball valve 71 electrically connects intelligence and adopts Collection instrument 6, casing 1 side is provided with nitrogen tube 8, nitrogen tube 8 is provided with condenser pump 81.
Operation principle of the present utility model is: when Article 1 pressure regulation pipeline breaks down, and closes Article 1 pressure regulation pipeline On the first Ball valve and the second ball valve, Article 2 pressure regulation pipeline can transmit combustion gas, skilled industrial worker can on-line maintenance fault adjust Pressure pipe road;When the pressure regulator on the filter on Article 1 pressure regulation pipeline and Article 2 pressure regulation pipeline breaks down, technical staff People can close the first ball valve and second ball valve of Article 2 pressure regulation pipeline of Article 1 pressure regulation pipeline, and combustion gas is through Article 2 pipeline First ball valve and filter, arm, transmits to escape pipe after the second ball valve of Article 1 pressure regulation pipeline and pressure regulator.
Information is received electric wire by Pressure gauge, oil gas sensor, temperature sensor and is sent to control by instrument for intelligently sampling Center, control centre is uninterruptedly monitored.Oil and gas leakage in oil gas sensor is not detected by pressure regulating box, temperature sensor is examined Measure pressure regulating box temperature too low time, instrument for intelligently sampling can start heater, heats the combustion gas in air inlet pipe;Work as oil gas When sensor detects oil and gas leakage in pressure regulating box, instrument for intelligently sampling opens the 3rd ball valve, skilled industrial worker's heart order in the controlling Cold nitrogen it is passed through in pressure regulating box.
The utility model has the advantage of: this utility model by filter and the second ball valve in two pressure regulation pipelines it Between connecting branch, the range of on-line maintenance can be expanded;Instrument for intelligently sampling controls heater to combustion by temperature sensor Gas heats, and is possible to prevent combustion gas to freeze;The 3rd ball valve that instrument for intelligently sampling controls exhaustor by oil gas sensor is opened, Nitrogen tube carries cold nitrogen in pressure regulating box simultaneously, can tackle gas leakage emergency situations in time.
This above content is to combine concrete preferred implementation further detailed description of the utility model, no Can assert that of the present utility model being embodied as is confined to these explanations.Common skill for this utility model art For art personnel, without departing from the concept of the premise utility, it is also possible to make some simple deduction or replace, all should It is considered as belonging to protection domain of the present utility model.

Claims (3)

1. fuel gas pressure-regulating box, including casing, it is characterised in that be provided with air inlet pipe and escape pipe, described air inlet pipe in described casing With between escape pipe and be connected with two pressure regulation pipelines, described surge pipe curb fuel gas transmission direction is connected with in turn by Gas Pipe First ball valve, filter, the second ball valve and pressure regulator, combustion gas between filter and the second ball valve in described two pressure regulation pipelines Pipe is connected by arm, and described escape pipe connects exhaust stack, and described exhaust stack is provided with in the one end near escape pipe and diffuses Valve, the other end of exhaust stack is positioned at outside described casing.
Fuel gas pressure-regulating box the most according to claim 1, it is characterised in that described air inlet pipe sets successively along combustion gas transmission direction Having heaters and boost gauge assembly, described diffusion valve is provided with outlet pressure table along the escape pipe on rear side of combustion gas transmission direction Assembly, described boost gauge assembly and outlet pressure table assembly all include needle valve and Pressure gauge, described heater, air inlet pressure Power table assembly and outlet pressure table assembly are all electrically connected with instrument for intelligently sampling, and described instrument for intelligently sampling is provided with oil gas sensor And temperature sensor, instrument for intelligently sampling side is provided with reception electric wire.
Fuel gas pressure-regulating box the most according to claim 2, it is characterised in that described exhaust stack connects exhaustor, described row Being provided with the 3rd ball valve on trachea, described 3rd ball valve electrically connects described instrument for intelligently sampling, and described casing side is provided with nitrogen tube, In described nitrogen tube, condenser pump is installed.
CN201620827647.6U 2016-08-03 2016-08-03 Gas pressure regulating box Expired - Fee Related CN205877717U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620827647.6U CN205877717U (en) 2016-08-03 2016-08-03 Gas pressure regulating box

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620827647.6U CN205877717U (en) 2016-08-03 2016-08-03 Gas pressure regulating box

Publications (1)

Publication Number Publication Date
CN205877717U true CN205877717U (en) 2017-01-11

Family

ID=57701816

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620827647.6U Expired - Fee Related CN205877717U (en) 2016-08-03 2016-08-03 Gas pressure regulating box

Country Status (1)

Country Link
CN (1) CN205877717U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107940228A (en) * 2017-12-25 2018-04-20 广州发展集团股份有限公司 A kind of surge tank and surge tank system
CN110440136A (en) * 2019-09-16 2019-11-12 重庆乔松信息技术有限公司 A kind of fuel gas pressure-regulating box automatic constant-temperature control system
CN113483273A (en) * 2021-06-25 2021-10-08 河北永良燃气设备有限公司 Gas pressure regulating box
CN114216060A (en) * 2021-11-16 2022-03-22 浙江苍南仪表集团东星能源科技有限公司 Square buried pressure regulating box body and preparation method
CN115823499A (en) * 2023-02-07 2023-03-21 山东奥德燃气设备制造有限公司 Pressure regulating box with protection early warning function
CN117190070A (en) * 2023-11-08 2023-12-08 新疆新易通石油科技有限公司 Urban door station gas pressure regulating device

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107940228A (en) * 2017-12-25 2018-04-20 广州发展集团股份有限公司 A kind of surge tank and surge tank system
CN110440136A (en) * 2019-09-16 2019-11-12 重庆乔松信息技术有限公司 A kind of fuel gas pressure-regulating box automatic constant-temperature control system
CN113483273A (en) * 2021-06-25 2021-10-08 河北永良燃气设备有限公司 Gas pressure regulating box
CN114216060A (en) * 2021-11-16 2022-03-22 浙江苍南仪表集团东星能源科技有限公司 Square buried pressure regulating box body and preparation method
CN114216060B (en) * 2021-11-16 2022-08-05 浙江苍南仪表集团东星能源科技有限公司 Square buried pressure regulating box body and preparation method
CN115823499A (en) * 2023-02-07 2023-03-21 山东奥德燃气设备制造有限公司 Pressure regulating box with protection early warning function
CN115823499B (en) * 2023-02-07 2023-04-28 山东奥德燃气设备制造有限公司 Pressure regulating box with protection early warning function
CN117190070A (en) * 2023-11-08 2023-12-08 新疆新易通石油科技有限公司 Urban door station gas pressure regulating device
CN117190070B (en) * 2023-11-08 2024-02-06 新疆新易通石油科技有限公司 Urban door station gas pressure regulating device

Similar Documents

Publication Publication Date Title
CN205877717U (en) Gas pressure regulating box
CN205782016U (en) Gas Pressure Regulating Equipment
CN109442817B (en) Water power balance system of plant chilled water supply network
CN105755202A (en) Oxygen pipeline system and anti-blasting device of extra-large converter oxygen lance valve station
CN210601051U (en) High-flow pressure regulating box
CN210483827U (en) Energy-saving air inlet structure based on low-pressure steam turbine unit
CN209355362U (en) A kind of superpressure duplicate protection system for heat supply heat distribution pipe network
CN203811371U (en) Natural gas line bleeding valve on-line testing device
CN102654242A (en) Natural gas pressure regulating device
CN203162237U (en) Gas pressure regulation valve
CN205481733U (en) Heating device for natural gas voltage regulator is exclusively used in
CN205172542U (en) Take safety arrangement's high temperature high pressure nitrogen gas heating sled
CN217635102U (en) Safe pressure regulating measurement cabinet suitable for industrial enterprise
CN219655853U (en) Bottle group air supply system for intelligent micro-pipe network ecological chain
CN214745000U (en) Natural gas pressure regulator draws pressure equipment to put
CN205261223U (en) Device is diffused to dual fail -safe safety
CN208845265U (en) Hybrid power engine turbocharger
CN204629942U (en) A kind of hydraulic equilibrium distributor
CN105650472A (en) Gas supply system for food processing plant
CN217635107U (en) Gas pressure energy stable power generation system
CN212867733U (en) Supply line
CN103383045B (en) Pilot-operated type pressure regulating valve heating system with overvoltage protection
CN212338918U (en) Natural gas pressure regulating station system with protection device
CN208458529U (en) Heating furnace blower grid-connected system
CN220434710U (en) Natural gas wellhead heating and pressure regulating system

Legal Events

Date Code Title Description
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170111

Termination date: 20190803