CN205867924U - Circulation drip washing exhaust -gas treatment tower among pyrometallurgical copper smelting - Google Patents

Circulation drip washing exhaust -gas treatment tower among pyrometallurgical copper smelting Download PDF

Info

Publication number
CN205867924U
CN205867924U CN201620493159.6U CN201620493159U CN205867924U CN 205867924 U CN205867924 U CN 205867924U CN 201620493159 U CN201620493159 U CN 201620493159U CN 205867924 U CN205867924 U CN 205867924U
Authority
CN
China
Prior art keywords
eluting column
drip washing
washing tower
shower
tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620493159.6U
Other languages
Chinese (zh)
Inventor
徐特
徐一特
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangxi Jiangnan New Material Technology Co.,Ltd.
Original Assignee
YINGTAN JIANGNAN COPPER Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YINGTAN JIANGNAN COPPER Co Ltd filed Critical YINGTAN JIANGNAN COPPER Co Ltd
Priority to CN201620493159.6U priority Critical patent/CN205867924U/en
Application granted granted Critical
Publication of CN205867924U publication Critical patent/CN205867924U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Treating Waste Gases (AREA)

Abstract

The utility model discloses a circulation drip washing exhaust -gas treatment tower among pyrometallurgical copper smelting to the left drip washing tower and the right drip washing tower that arrange to set up, and the material is the glass steel, a left side, drip washing tower in the right side all highly is 12 meters, the washing liquid is equipped with to lower part in the left side drip washing tower, the gas -supply pipe inserts in the washing liquid to one side, from up having set gradually a plurality of packing layers down in the left side drip washing tower, the top of packing layer all is provided with the shower, the end is provided with the shower nozzle, the lower part at right drip washing tower is connected to spiral cooling tube's the other end, the lower extreme of right side drip washing tower is provided with the drain pipe, in order to be provided with packing layer and shower with the same mode of left drip washing tower in the right side drip washing tower, the top of right side drip washing tower is provided with the outlet duct, below at the outlet duct is provided with the defroster, this defroster with the inner wall fixed connection of right side drip washing tower. The beneficial effect of the utility model adopted a plurality of steps to clear up waste gas, the clearance process prolongs relatively for the clearance more thoroughly of waste gas, efficiency is higher.

Description

A kind of cycling elution exhaust gas treating tower in copper smelting by pyrometallurgy
Technical field
This utility model belongs to copper metallurgy technical field of waste gas treatment, particularly relates to the cycling elution in a kind of copper smelting by pyrometallurgy and gives up Gas disposal tower.
Background technology
Copper smelting by pyrometallurgy includes the operations such as roasting, melting, blowing, refine, with copper sulfide concentrate as primary raw material.Roasting Divide partial oxidizing roasting and dead roasting (" dead roast "), all or part of sulfur in removing concentrate, remove part arsenic, antimony simultaneously Etc. volatile impurity.Melting is mainly matte smelting, it is therefore an objective to make the part ferrum in copper concentrate or roasted ore aoxidize, and with The slag making such as stone-like pulse, flux removes, the matte that output cupric is higher.Refine divides pyro-refining and electrorefining.Blister copper essence divides pyrogenic process Refine and electrorefining.Pyro-refining is to utilize some impurity that the affinity of oxygen is more than copper, and its oxide is insoluble in copper The character such as liquid, are removed by oxidative slagging or volatilization.A large amount of flue gas can be produced baking, during melting and pyro-refining, Often containing sulfur dioxide lamp harmful gas in flue gas, for environmental protection and energy-conservation, and fume treatment also serves as our living according to principles for self-cultivation Produce operation.
Impact type leaching absorption tower is the core apparatus of wet process of FGD, common mainly iron spray column, inside does Preservative treatment.In practical application, usually there is desulfuration efficiency low and the problem of job insecurity occurs and maintenance inconvenience, to useless In gas, the noble metal response rate is low, causes greatly waste, in the case of the requirement of current energy-saving and emission-reduction and standard improve constantly, A lot of desulphurization systems can not meet the needs of enterprise, the more efficient and reliable technology of market demand.
Utility model content
In view of this, the cycling elution exhaust gas treating tower in a kind of copper smelting by pyrometallurgy of necessary offer, reach waste gas Cleaning is thorough, cleaning efficiency high effect.
For the defect overcoming prior art to exist, this utility model provides techniques below scheme:
A kind of cycling elution exhaust gas treating tower in copper smelting by pyrometallurgy, including the left eluting column being arranged side by side and right eluting column, And material is fiberglass, described left and right eluting column is made up of 3 joint cylinders, connects by ring flange is fixing, institute between each joint cylinder Stating left and right eluting column all height is 12 meters, and 0.2 times of a diameter of height, tower body wall thickness is 2 centimetres, the bottom in left eluting column Equipped with cleanout fluid, being provided with a gas buffer tank, this gas buffer tank is provided with appendix by described left eluting column, this is defeated Trachea oblique cutting enters in described cleanout fluid, is disposed with multiple packing layer, each packing layer in described left eluting column from the bottom up Top be provided with shower, the end of its this shower is provided with shower nozzle, and this shower nozzle is a upper end open lower end closed Vertical tube, and be provided with multiple spray hole on the sidewall of this vertical tube and bottom, the other end of described shower extends to described Liquid case outside left eluting column, this liquid case is connected with the bottom of described left eluting column by pump, and the upper end of left eluting column connects glass The spiral cooling tube that glass steel is made, the pitch of this spiral cooling tube is 70 centimetres, and the other end of this spiral cooling tube is connected to institute Stating the bottom of right eluting column, the lower end of right eluting column is provided with drain pipe, in right eluting column in the way of identical with left eluting column Being provided with packing layer and shower, the top of described right eluting column is provided with escape pipe, is provided with except mist in the lower section of escape pipe Device, this demister is fixing with the inwall of described right eluting column to be connected.
Preferably, described baffle-box being additionally provided with muffler, the other end of this muffler is connected with described left eluting column, and On-position is positioned at the top of described cleanout fluid liquid level.
Preferably, the angle that described appendix and horizontal plane are formed is 20 °.
Compared with prior art, the beneficial effects of the utility model have employed multiple step and clear up waste gas, clearly Reason process extends relatively so that the cleaning of waste gas is more thorough, in hgher efficiency.
Accompanying drawing explanation
Fig. 1 is the structural representation of the cycling elution exhaust gas treating tower in a kind of copper smelting by pyrometallurgy of this utility model.
Specific examples below will further illustrate this utility model in conjunction with above-mentioned accompanying drawing.
Detailed description of the invention
Below with reference to accompanying drawing, the utility model is described in further detail.
Seeing Fig. 1, the cycling elution exhaust gas treating tower in a kind of copper smelting by pyrometallurgy, including left eluting column 1 He being arranged side by side Right eluting column 2, described left and right eluting column is made up of 3 joint cylinders, connects by ring flange 8 is fixing between each joint cylinder, and material For fiberglass, described left and right eluting column all height are 12 meters, and 0.2 times of a diameter of height, tower body wall thickness is 2 centimetres, left drip washing Bottom in tower 1 is equipped with cleanout fluid 1a, and described left eluting column 1 is other is provided with a gas buffer tank 4, on this gas buffer tank 4 Being provided with appendix 4a, this appendix 4a oblique cutting enters in described cleanout fluid 1a, sets gradually from the bottom up in described left eluting column 1 Having multiple packing layer 6, the top of each packing layer 6 to be provided with shower 3b, the end of its this shower 3b is provided with shower nozzle, 3a this shower nozzle 3a is the vertical tube of a upper end open lower end closed, and is provided with multiple hydrojet on the sidewall of this vertical tube and bottom Hole, the other end of described shower 3b extends to the liquid case 3 outside described left eluting column 1, and this liquid case 3 is by pump 9 and described left pouring Washing the bottom connection of tower 1, the upper end of left eluting column 1 connects the spiral cooling tube 4 having fiberglass to make, this spiral cooling tube 4 Pitch is 70 centimetres, and the other end of this spiral cooling tube 4 is connected to the bottom of described right eluting column 2, and the lower end of right eluting column sets It is equipped with drain pipe 9, in right eluting column 2, in the way of identical with left eluting column 1, is provided with packing layer 6 and shower 3b, the described right side The top of eluting column 2 is provided with escape pipe 5, and the lower section of escape pipe 5 is provided with demister 7, this demister 7 and described right drip washing The inwall of tower 2 is fixing to be connected.
Preferably, described baffle-box 4 is additionally provided with muffler 4b, the other end of this muffler 4b and described left eluting column 1 Connect, and on-position is positioned at the top of described cleanout fluid 1a liquid level.
Preferably, the angle that described appendix 4a and horizontal plane are formed is 20 °.
Waste gas is first passed in baffle-box 4, is being passed in cleanout fluid 1a via the appendix 4a tilted in baffle-box 4 Carry out cleaning for the first time.Waste gas after cleaning for the first time is passed through spray by shower 3b after continuing up to come into packing layer 6 Head 3a ejection cleanout fluid 1a carry out second time clean.Waste gas after second time is cleaned cools down through spiral cooling tube 4 After arrive right eluting column 2 again in carry out third time and clean, complete the waste gas after third time is cleaned after demister 7 processes, then lead to The escape pipe 5 crossing right eluting column 2 top is discharged.Cleanout fluid in right eluting column 2 is discharged by drain pipe 9, makees unified collection Process, there is environmental protection, cost-effective advantage.
Described shower nozzle 3a uses a vertical tube to make, and the sidewall of vertical tube and bottom are provided with multiple spray hole, so, spray Fluid apertures leads to surrounding, towards a biggest scope.Cleanout fluid is outwards sprayed by this spray hole at night, and it is wider that it sprays, Effect is more.On the other hand, the shower nozzle 3a simple in construction of riser type, convenient for production, save manufacturing cost.
Liquid case 3 is connected with the lower end of left eluting column 1 by pump 9, and the cleanout fluid 1a in left eluting column 1 can be extracted into top In liquid case 3, for Sprayer Circulation.
The effect of muffler 4b and baffle-box 4 is to be possible to prevent the cleanout fluid 1 bottom left eluting column 1 to pour in down a chimney.
The explanation of above example is only intended to help to understand method of the present utility model and core concept thereof.Should refer to Go out, for those skilled in the art, on the premise of without departing from this utility model principle, it is also possible to this Utility model carries out some improvement and modification, and these improve and modification also falls into this utility model scope of the claims In.
Described above to the disclosed embodiments, makes professional and technical personnel in the field be capable of or uses this practicality new Type.Multiple amendment to these embodiments will be apparent from for those skilled in the art, is determined herein The General Principle of justice can realize in the case of without departing from spirit or scope of the present utility model in other embodiments.Cause This, this utility model is not intended to be limited to the embodiments shown herein, and is to fit to and principles disclosed herein The widest scope consistent with features of novelty.

Claims (2)

1. the cycling elution exhaust gas treating tower in a copper smelting by pyrometallurgy, it is characterised in that: include the left eluting column that is arranged side by side and Right eluting column, described left and right eluting column is made up of 3 joint cylinders, connects by ring flange is fixing, and material is between each joint cylinder Fiberglass, described left and right eluting column all height are 12 meters, and 0.2 times of a diameter of height, tower body wall thickness is 2 centimetres, left eluting column Interior bottom, equipped with cleanout fluid, is provided with a gas buffer tank, this gas buffer tank is provided with defeated by described left eluting column Trachea, this appendix oblique cutting enters in described cleanout fluid, is disposed with multiple packing layer from the bottom up, often in described left eluting column The top of individual packing layer is provided with shower, and the end of its this shower is provided with shower nozzle, and this shower nozzle is a upper end open Being provided with multiple spray hole on the vertical tube of lower end closed, and the sidewall of this vertical tube and bottom, the other end of described shower prolongs Reaching the liquid case outside described left eluting column, this liquid case is connected with the bottom of described left eluting column by pump, the upper end of left eluting column Connecting the spiral cooling tube having fiberglass to make, the pitch of this spiral cooling tube is 70 centimetres, the other end of this spiral cooling tube Being connected to the bottom of described right eluting column, the lower end of right eluting column is provided with drain pipe, in right eluting column with left eluting column phase Same mode is provided with packing layer and shower, and the top of described right eluting column is provided with escape pipe, sets in the lower section of escape pipe Being equipped with demister, this demister is fixing with the inwall of described right eluting column to be connected;It is additionally provided with muffler, this time on described baffle-box The other end of trachea is connected with described left eluting column, and on-position is positioned at the top of described cleanout fluid liquid level.
Cycling elution exhaust gas treating tower in copper smelting by pyrometallurgy the most according to claim 1, it is characterised in that described appendix The angle formed with horizontal plane is 20 °.
CN201620493159.6U 2016-05-27 2016-05-27 Circulation drip washing exhaust -gas treatment tower among pyrometallurgical copper smelting Active CN205867924U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620493159.6U CN205867924U (en) 2016-05-27 2016-05-27 Circulation drip washing exhaust -gas treatment tower among pyrometallurgical copper smelting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620493159.6U CN205867924U (en) 2016-05-27 2016-05-27 Circulation drip washing exhaust -gas treatment tower among pyrometallurgical copper smelting

Publications (1)

Publication Number Publication Date
CN205867924U true CN205867924U (en) 2017-01-11

Family

ID=57689552

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620493159.6U Active CN205867924U (en) 2016-05-27 2016-05-27 Circulation drip washing exhaust -gas treatment tower among pyrometallurgical copper smelting

Country Status (1)

Country Link
CN (1) CN205867924U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107149868A (en) * 2017-06-15 2017-09-12 易门铜业有限公司 A kind of copper metallurgy process middle ring collection flue gas processing device and method
CN117101387A (en) * 2023-09-27 2023-11-24 安徽虹泰新材料股份有限公司 Polyamide resin production waste gas treatment equipment and treatment process

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107149868A (en) * 2017-06-15 2017-09-12 易门铜业有限公司 A kind of copper metallurgy process middle ring collection flue gas processing device and method
CN117101387A (en) * 2023-09-27 2023-11-24 安徽虹泰新材料股份有限公司 Polyamide resin production waste gas treatment equipment and treatment process
CN117101387B (en) * 2023-09-27 2024-03-19 安徽虹泰新材料股份有限公司 Polyamide resin production waste gas treatment equipment and treatment process

Similar Documents

Publication Publication Date Title
CN207769439U (en) A kind of UTILIZATION OF VESIDUAL HEAT IN and flue gas purification system for aluminium smelting furnace
CN104857799B (en) Sulfur and dust removal device
CN108421342A (en) Spraying cooling eliminates the device of white cigarette in a kind of desulfuration absorbing tower
CN205867924U (en) Circulation drip washing exhaust -gas treatment tower among pyrometallurgical copper smelting
CN205269314U (en) Hydrochloric acid regenerating unit vent gas treatment system in
CN208115398U (en) A kind of single loop spray tower apparatus with desulphurization denitration function
CN205867927U (en) A waste gas absorption tower for pyrometallurgical copper smelting
CN205796921U (en) A kind of impact type waste gas absorption tower of copper smelting by pyrometallurgy
CN205867925U (en) A drip washing formula glass steel waste gas absorption tower for pyrometallurgical copper smelting
CN205867926U (en) Binary waste gas drip washing tower among pyrometallurgical copper smelting
CN206064103U (en) A kind of cycling elution waste gas absorption tower for copper smelting by pyrometallurgy
CN207755804U (en) A kind of desulfurizing tower
CN207085657U (en) A kind of desulfurizing tower
CN106422585A (en) Welding fume dust remover for PG board soldering tin for plastic package motor
CN207042127U (en) A kind of Tower for purifying waste gas
CN205662562U (en) Extraction element is used in plumbous production of gold that can pollution abatement
CN206184234U (en) A novel drip washing tower for pyrometallurgical copper smelting
CN207641275U (en) A kind of desulfurizing tower that fume treatment effect is good
CN206823505U (en) A kind of efficient desulfurizing tower for smoke gas treatment
CN107149868A (en) A kind of copper metallurgy process middle ring collection flue gas processing device and method
CN209968050U (en) High-efficient zinc cigarette dust removal absorption tower
CN207996503U (en) A kind of copper smelting by pyrometallurgy smoke absorption self-cleaning device
CN208465602U (en) A kind of new multistage formula flue gas desulfurization spray tower
CN207429968U (en) A kind of multi-functional environmental protection enamelled wire processing emission-control equipment
CN205537144U (en) Industrial waste gas treatment system

Legal Events

Date Code Title Description
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: No. 6 Jiangnan Road, National High-salary District, Yingtan City, Jiangxi Province

Patentee after: Jiangxi Jiangnan New Materials Technology Co., Ltd.

Address before: No. 6 Jiangnan Road, National High-salary District, Yingtan City, Jiangxi Province

Patentee before: YINGTAN JIANGNAN COPPER CO., LTD.

CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 335000 Yingtan Industrial Park, Yuehu District, Yingtan, Jiangxi

Patentee after: Jiangxi Jiangnan New Material Technology Co.,Ltd.

Address before: No. 6 Jiangnan Road, National High-salary District, Yingtan City, Jiangxi Province

Patentee before: JIANGXI JIANGNAN NEW MATERIAL TECHNOLOGY Co.,Ltd.