CN205786928U - It is connected the cover plate assay device of air chamber with GIS for oil-gas type transformator - Google Patents

It is connected the cover plate assay device of air chamber with GIS for oil-gas type transformator Download PDF

Info

Publication number
CN205786928U
CN205786928U CN201620699030.0U CN201620699030U CN205786928U CN 205786928 U CN205786928 U CN 205786928U CN 201620699030 U CN201620699030 U CN 201620699030U CN 205786928 U CN205786928 U CN 205786928U
Authority
CN
China
Prior art keywords
gas
oil
cover plate
transformer
gas chamber
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620699030.0U
Other languages
Chinese (zh)
Inventor
陈润晶
张春华
周雨田
苏海南
陆斌
周彬
李丽君
刘鹏
张大伟
杨隆棣
孟佳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dandong Electric Power Supply Co of State Grid Liaoning Electric Power Co Ltd
State Grid Corp of China SGCC
Original Assignee
Dandong Electric Power Supply Co of State Grid Liaoning Electric Power Co Ltd
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dandong Electric Power Supply Co of State Grid Liaoning Electric Power Co Ltd, State Grid Corp of China SGCC filed Critical Dandong Electric Power Supply Co of State Grid Liaoning Electric Power Co Ltd
Priority to CN201620699030.0U priority Critical patent/CN205786928U/en
Application granted granted Critical
Publication of CN205786928U publication Critical patent/CN205786928U/en
Anticipated expiration legal-status Critical
Active legal-status Critical Current

Links

Landscapes

  • Testing Relating To Insulation (AREA)

Abstract

本实用新型提供一种用于油气式变压器与GIS连接气室的盖板试验装置,包括固定连接在连接气室上的绝缘板和连接气室内部固定在绝缘板上的波纹管,所述的绝缘板上设有定位销,用于固定动试验导电杆,所述的波纹管与动试验导电杆固定相连,动试验导电杆穿过绝缘板和波纹管与凹型触头相连,绝缘板上设有一接地接线柱,接地接线柱设置在密封罩内。由于连接气室盖板试验装置可在原来盖板孔的基础上完成,实现了改装易行、操作简单、安全可靠的目标,有效地提高了工作效率和供电可靠性,同时最大限度的保障了人身安全。

The utility model provides a cover plate test device for connecting an oil-gas transformer and a GIS gas chamber, which includes an insulating plate fixedly connected to the connecting gas chamber and a bellows fixed on the insulating plate inside the connecting gas chamber. Positioning pins are arranged on the insulating plate to fix the conductive rod for the dynamic test. The bellows are fixedly connected with the conductive rod for the dynamic test. The conductive rod for the dynamic test passes through the insulating plate and the bellows and is connected with the concave contact. There is a grounding terminal, and the grounding terminal is arranged in the sealing cover. Since the test device for connecting the air chamber cover plate can be completed on the basis of the original cover plate hole, the goal of easy modification, simple operation, safety and reliability is achieved, the work efficiency and power supply reliability are effectively improved, and at the same time, the maximum protection Personal safety.

Description

用于油气式变压器与GIS连接气室的盖板试验装置Cover plate test device for connecting gas chamber of oil-gas transformer and GIS

技术领域technical field

本实用新型涉及一种用于油气式变压器与GIS(Gas Insulated Substation气体绝缘全封闭组合电器)连接气室的盖板试验装置,属于变压器高压试验领域。The utility model relates to a cover plate test device used for connecting an oil-gas transformer and a gas chamber of a GIS (Gas Insulated Substation gas-insulated fully enclosed combined electrical appliance), which belongs to the field of high-voltage tests of transformers.

背景技术Background technique

在电力系统中,一种油气式变压器(变压器组复合式组合电器,用T-GIS表示)已经逐渐普及应用,由于这种油气式变压器与传统电力变压器高压出线方式及结构不同,依据国家GB50150—2006《电气装置安装工程电气设备交接试验标准》及行业标准Q/GDW1168—2013《输变电设备状态检修试验规程》在进行油气式变压器电气试验时不能采用传统法进行测试,因为油气式变压器高压三相套管直接通过与之连接的GIS(Gas InsulatedSubstation气体绝缘全封闭组合电器)及电缆输出。In the power system, a kind of oil-gas transformer (transformer group composite combined electrical appliance, represented by T-GIS) has been gradually popularized and applied. Since this oil-gas transformer is different from the traditional power transformer in the way and structure of high-voltage outlets, according to the national GB50150- 2006 "Electrical Equipment Installation Engineering Handover Test Standard for Electrical Equipment" and industry standard Q/GDW1168-2013 "Condition Maintenance Test Regulations for Power Transmission and Transformation Equipment" cannot use the traditional method for electrical testing of oil-gas transformers, because oil-gas transformers are high-voltage The three-phase bushing is directly output through the GIS (Gas Insulated Substation gas insulated fully enclosed combined electrical appliance) connected to it and the cable.

所谓传统法,就是进行电力变压器高压电气试验前,必须将被试变压器停电,然后将所有高、低引出线(通过套管、GIS或电缆)上的端子头断开,该方法对常规电力变压器可行,而对于油气式变压器(T-GIS)则不行。如果想对运行中的油气式变压器进行试验,必须排除油气式变压器与GIS(Gas Insulated Substation气体绝缘全封闭组合电器)之间连接气室中的SF6气体,拆除连接气室上的盖板,在拆除油气套管与GIS(Gas InsulatedSubstation气体绝缘全封闭组合电器)之间的连接头方可进行。新设备交接进行各种试验的时间还很充裕,但对运行中的变压器进行高压电气试验,时间就显得太短(一般电力系统停电时间不超过12小时),如果排除连接气室中的气体,等油气式变压器进行的高压试验项目全部完毕,恢复接线,再将连接气室中充满气体静放24小时(GB50150—2006电气装置安装工程电气设备交接试验标准第20.0.5条SF6气体在充入电气设备24h后方可进行试验)进行气体试验,合格后方可运行,这种方法时间长、效率低,并且影响供电可靠性。The so-called traditional method is that before the high-voltage electrical test of the power transformer, the tested transformer must be powered off, and then all the terminals on the high and low lead-out lines (via bushings, GIS or cables) should be disconnected. Feasible, but not for oil-gas transformers (T-GIS). If you want to test the oil-gas transformer in operation, you must remove the SF6 gas in the connecting gas chamber between the oil-gas transformer and GIS (Gas Insulated Substation Gas Insulated Totally Enclosed Combined Electrical Appliance), remove the cover plate on the connecting gas chamber, and The connection between the oil and gas bushing and GIS (Gas Insulated Substation Gas Insulated Fully Enclosed Combined Electrical Appliance) can be removed. There is plenty of time for various tests for the handover of new equipment, but the time for high-voltage electrical tests on transformers in operation is too short (generally, the power system outage time does not exceed 12 hours). If the gas in the connecting gas chamber is removed, After all the high-voltage test items of the oil-gas type transformer are completed, restore the wiring, and then let the gas in the connecting air chamber be filled for 24 hours (Article 20.0.5 of the Electrical Equipment Handover Test Standard for Electrical Installation Engineering Electrical equipment can be tested after 24 hours), and the gas test can only be carried out after passing the test. This method takes a long time, has low efficiency, and affects the reliability of power supply.

为了保证供电可靠性,缩短停电后连接气室排出SF6气体、充SF6气和油气式变压器本体试验的时间,实用新型一种油气式变压器与GIS(Gas Insulated Substation气体绝缘全封闭组合电器)连接的连接气室盖板试验装置,就可以轻易解决上述难题。In order to ensure the reliability of power supply and shorten the time for connecting the gas chamber to discharge SF6 gas, charge SF6 gas and test the oil-gas transformer body after a power failure, a utility model for connecting the oil-gas transformer with GIS (Gas Insulated Substation Gas Insulated Fully Enclosed Combined Electrical Appliance) Connecting the air chamber cover test device can easily solve the above problems.

名词解释:Glossary:

油气式变压器:所谓油气式变压器,也称为变压器组复合式组合电器(用T-GIS表示),是指变压器高压引出线不通过电容式套管引出,而是直接与GIS(Gas InsulatedSubstation气体绝缘全封闭组合电器)连接,并通过GIS(Gas Insulated Substation气体绝缘全封闭组合电器)内电缆通向输电杆塔上。Oil-gas type transformer: The so-called oil-gas type transformer, also known as transformer group composite combined electrical appliance (expressed as T-GIS), means that the high-voltage lead-out wire of the transformer is not led out through the capacitive bushing, but is directly insulated with GIS (Gas Insulated Substation gas) Fully enclosed combined electrical equipment) connected, and through the GIS (Gas Insulated Substation gas insulated fully enclosed combined electrical equipment) inner cable to the transmission tower.

连接气室:所谓连接气室,即油气式变压器与GIS(Gas Insulated Substation气体绝缘全封闭组合电器)之间连接的一个单独气室,气室内部有可拆卸连接油气式变压器与GIS(Gas Insulated Substation气体绝缘全封闭组合电器)的ABC三相主回路导电杆。如果需要对油气式变压器进行出厂试验或现场交接验收检测试验时,则需要拆除该气室,在油气式变压器高压输出位置安装专门带有外套管的试验装置后,才可以按照国家标准GB50150—2006《电气装置安装工程电气设备交接试验标准》的高压试验项目及方法对油气式变压器进行验收试验;如果需要对油气式变压器进行定期检测试验时,则需要排除该气室内部的SF6气体,然后打开盖板,拆除ABC三相主回路导电杆,再通过盖板引孔,按照行业标准Q/GDW1168—2013《输变电设备状态检修试验规程》的高压试验项目及方法对油气式变压器进行常规试验。Connecting gas chamber: The so-called connecting gas chamber is a separate gas chamber connected between the oil-gas transformer and GIS (Gas Insulated Substation gas-insulated fully enclosed combined electrical appliance). ABC three-phase main circuit conductive rod of Substation gas insulated fully enclosed combined electrical appliance). If it is necessary to carry out the factory test or on-site handover acceptance test for the oil-gas transformer, the air chamber needs to be removed, and a special test device with an outer casing is installed at the high-voltage output position of the oil-gas transformer before it can be used in accordance with the national standard GB50150-2006 The high-voltage test items and methods in the "Electrical Equipment Installation Engineering Electrical Equipment Handover Test Standard" conduct acceptance tests on oil-gas transformers; if periodic inspection tests are required on oil-gas transformers, the SF6 gas inside the gas chamber needs to be removed, and then opened Remove the cover plate, remove the ABC three-phase main circuit conductive rod, and then pass through the lead hole of the cover plate, and conduct routine tests on the oil-gas transformer according to the high-voltage test items and methods of the industry standard Q/GDW1168-2013 "Test Regulations for Condition Maintenance of Power Transmission and Transformation Equipment" .

实用新型内容Utility model content

传统意义上的油气式变压器与GIS间的连接气室盖板,只是一种用于拆除内部ABC三相导电杆连接和密封功能。In the traditional sense, the connecting air chamber cover plate between the oil-gas type transformer and GIS is only used to remove the connection and sealing function of the internal ABC three-phase conductive rod.

为解决上述技术问题,本实用新型提供一种用于油气式变压器与GIS连接气室的盖板试验装置,解决了油气式变压器试验时需要将连接气室排气、充气、拆除连接气室盖板和内部导电杆的问题。In order to solve the above technical problems, the utility model provides a cover plate test device for connecting the gas chamber of the oil-gas transformer and GIS, which solves the need to exhaust, inflate, and remove the cover of the connecting gas chamber during the test of the oil-gas transformer. Problems with plates and internal conductive rods.

本实用新型是通过以下技术方案实现的:The utility model is achieved through the following technical solutions:

一种用于油气式变压器与GIS连接气室的盖板试验装置,其特征在于包括固定连接在连接气室上的绝缘板和连接气室内部固定在绝缘板上的波纹管,所述的绝缘板上设有定位销,用于固定动试验导电杆,所述的波纹管与动试验导电杆固定相连,动试验导电杆穿过绝缘板和波纹管与凹型触头相连,绝缘板上设有一接地接线柱,接地接线柱设置在密封罩内。A cover plate test device for connecting an oil-gas transformer to a GIS gas chamber, characterized in that it includes an insulating plate fixedly connected to the connecting gas chamber and a bellows fixed on the insulating plate inside the connecting gas chamber. There are positioning pins on the board for fixing the dynamic test conductive rod. The bellows are fixedly connected with the dynamic test conductive rod. The dynamic test conductive rod passes through the insulating plate and the bellows to connect with the concave contact. The grounding terminal is arranged in the sealing cover.

其中,所述的密封罩与绝缘板之间设有密封胶垫。Wherein, a sealing rubber pad is provided between the sealing cover and the insulating plate.

其中,所述的密封胶垫设置在连接气室的盖板孔处。Wherein, the sealing rubber pad is arranged at the hole of the cover plate connecting the air chamber.

其中,所述的凹型触头在试验位置时与连接气室内部的主回路导电杆相连。Wherein, the concave contact is connected to the main circuit conductive rod connected to the inside of the gas chamber when it is in the test position.

其中,所述的动试验导电杆在运行位置时短路连接并与接地接线柱相连。Wherein, the conductive rod of the dynamic test is short-circuited and connected to the grounding terminal when it is in the running position.

其中,所述的动试验导电杆的材质为铜材质或镀锌材质。Wherein, the material of the dynamic test conducting rod is copper or galvanized.

其中,所述的密封罩的材质为塑钢材质。Wherein, the sealing cover is made of plastic steel.

其中,所述的凹型触头的材质为软性金属材质。Wherein, the material of the concave contact is soft metal.

其中,所述的软性金属材质为黄铜材质或镀锌材质。Wherein, the soft metal material is brass or galvanized.

本实用新型提供一种在盖板上安装三相用于高压试验引出的盖板试验装置,利用原连接气室的盖板孔,在绝缘板上安装三相试验导电装置。当需要进行油气式变压器试验时,打开连接气室上的塑钢密封罩,拆除绝缘板上的三相接地接线柱,推动盖板上的动试验导电杆,使其内部波纹管带动试验导电杆及凹型触头接触到主回路导电杆后,拧紧定位销即可进行高压试验;当在运行状态时,松开定位销,借助波纹管回弹力使动试验导电杆离开主回路导电杆,拧紧定位销,并将绝缘盖板外部三相动试验导电杆短路接地即可。塑钢密封罩的高度按照运行状态时试验导电杆外部高度而定。The utility model provides a cover plate test device which installs three phases on the cover plate and is used for high-voltage test lead-out. The three-phase test conductive device is installed on the insulating plate by using the cover plate hole originally connected to the gas chamber. When the oil-gas transformer test is required, open the plastic-steel sealing cover on the connecting air chamber, remove the three-phase grounding terminal on the insulating plate, push the dynamic test conductive rod on the cover plate, and make the inner bellows drive the test conductive rod After the concave contact contacts the conductive rod of the main circuit, tighten the positioning pin to carry out the high-voltage test; when it is in the running state, loosen the positioning pin, and use the bellows rebound force to make the dynamic test conductive rod leave the main circuit conductive rod, tighten the positioning pin pin, and short-circuit the conductive rod of the three-phase dynamic test outside the insulating cover to ground. The height of the plastic-steel sealing cover is determined according to the external height of the test conductive rod in the running state.

与现有技术相比,本实用新型的有益效果如下:Compared with the prior art, the beneficial effects of the utility model are as follows:

本实用新型实现了在电力系统正常运行过程中需要进行定期试验时,可通过本连接气室盖板试验装置缩短工作时间,节省人工,比较传统需要对连接气室进行排气、充气、静放等程序才能完成的工作,实现了外部简单操作就能完成油气式变压器本体试验工作,有效的提高了工作效率,省时省力,本实用新型保证了供电可靠性、提高了检修试验质量,降低了安全风险,保障人身、电网、设备的安全。本实用新型设计新颖,结构合理,不需要改变原连接气室结构,只在原盖板上改装即可,且组装快捷、绝缘可靠,操作简单,极大限度的保障了人身安全,具有较好经济效益和社会效益。The utility model realizes that when a regular test is required during the normal operation of the power system, the working time can be shortened by the test device for the cover plate of the connecting air chamber, and labor is saved. Compared with the traditional method, the connecting air chamber needs to be exhausted, inflated, and placed statically. The work that can only be completed by waiting for the program can complete the test work of the oil-gas type transformer body with simple external operations, which effectively improves the work efficiency and saves time and effort. The utility model ensures the reliability of power supply, improves the quality of maintenance tests, and reduces the Safety risks, ensuring the safety of people, power grids, and equipment. The utility model is novel in design and reasonable in structure. It does not need to change the structure of the original connecting air chamber, only the original cover plate can be refitted, and the assembly is quick, the insulation is reliable, the operation is simple, the personal safety is guaranteed to the greatest extent, and it is economical. benefits and social benefits.

附图说明Description of drawings

图1为油气式变压器与GIS组合电器连接的立体结构示意图。Figure 1 is a three-dimensional schematic diagram of the connection between the oil-gas transformer and the GIS combined electrical appliance.

图2为油气式变压器与GIS组合电器间连接气室内部示意图。Figure 2 is a schematic diagram of the interior of the air chamber connecting the oil-gas transformer and the GIS combined electrical appliance.

图3为油气式变压器与GIS组合电器间连接气室盖板试验装置在试验位置时的示意图。Figure 3 is a schematic diagram of the gas chamber cover test device connected between the oil-gas transformer and the GIS combined electrical appliance at the test position.

图4为油气式变压器与GIS组合电器间连接气室盖板试验装置在运行位置时的示意图。Figure 4 is a schematic diagram of the gas chamber cover test device connected between the oil-gas transformer and the GIS combined electrical appliance when it is in the operating position.

图中:1、连接气室,2、主回路导电杆,3、油气式变压器,4、密封罩,5、定位销,6、接地接线柱,7、凹型触头,8、密封胶垫,9、动试验导电杆,10、波纹管,11、绝缘板,12、GIS组合电器。In the figure: 1. Connecting the air chamber, 2. Main circuit conductive rod, 3. Oil-gas transformer, 4. Sealing cover, 5. Locating pin, 6. Grounding terminal, 7. Concave contact, 8. Sealing rubber pad, 9. Conductive rod for dynamic test, 10. Bellows, 11. Insulation board, 12. GIS combined electrical appliance.

具体实施方式detailed description

下面结合实施例对本实用新型作进一步详细说明。以下实施仅为实用新型的具体实施举例,但本实用新型的设计构思并不局限于此,凡利用此构思对本实用新型进行非实质性的改动,均应在本实用新型保护范围之内。Below in conjunction with embodiment the utility model is described in further detail. The following implementations are only specific implementation examples of the utility model, but the design concept of the utility model is not limited thereto, and any insubstantial changes made to the utility model by using this concept should be within the protection scope of the utility model.

实施例Example

如图1所示,为本实用新型油气式变压器与GIS组合电器连接的立体结构示意图,油气式变压器3与GIS组合电器12之间设有连接气室1,连接气室1上设有密封罩4。As shown in Figure 1, it is a schematic diagram of the three-dimensional structure of the connection between the oil-gas type transformer and the GIS combined electrical appliance of the present invention. A connecting air chamber 1 is provided between the oil-gas type transformer 3 and the GIS combined electrical appliance 12, and a sealing cover is arranged on the connecting air chamber 1. 4.

如图2所示,为本实用新型连接气室1的内部结构示意图,连接气室1的一端与油气式变压器3相连,另一端与GIS组合电器12相连,连接气室1的内部设有三相主回路导电杆2,连接气室1上设有密封罩4。As shown in Figure 2, it is a schematic diagram of the internal structure of the connecting air chamber 1 of the present invention. One end of the connecting air chamber 1 is connected to the oil-gas type transformer 3, and the other end is connected to the GIS combined electrical appliance 12. The inside of the connecting air chamber 1 is provided with a three-phase The main circuit conductive rod 2 is provided with a sealing cover 4 on the connecting air chamber 1 .

如图3所示,为本实用新型油气式变压器与GIS组合电器间连接气室盖板试验装置在试验位置时的示意图。本实用新型提供一种用于油气式变压器与GIS连接气室的盖板试验装置,主要由密封罩4、定位销5、接地接线柱6、凹型触头7、密封胶垫8、动试验导电杆9、波纹管10、绝缘板11等组成。As shown in Figure 3, it is a schematic diagram of the test device for connecting the air chamber cover plate between the oil-gas type transformer and the GIS combined electrical appliance of the utility model when it is in the test position. The utility model provides a cover plate test device for connecting an air chamber between an oil-gas transformer and a GIS. Rod 9, bellows 10, insulating plate 11 and so on.

盖板安装:在原连接气室1盖板孔上,将实用新型的专门用于油气式变压器3与GIS组合电器12连接气室1试验装置安装在盖板上,绝缘板11上安装了用于试验的动试验导电杆9、波纹管10、凹型触头7、定位销5等,调节波纹管10位置,使凹型触头7与其三相主回路导电杆2接触良好,推动动试验导电杆9,借助波纹管10来调整凹型触头7离开三相主回路导电杆2的位置,拧紧定位销5,将绝缘板11固定在连接气室本体1上,将动试验导电杆9与接地接线柱6相连,静放24小时后,进行SF6气体密封性试验和气体试验项目,合格后扣上塑钢密封罩4即可。Cover plate installation: on the cover plate hole of the original connection air chamber 1, install the utility model specially used for connecting the gas chamber 1 test device between the oil-gas type transformer 3 and the GIS combined electrical appliance 12 on the cover plate, and install the insulating plate 11 for Test the dynamic test conductive rod 9, bellows 10, concave contact 7, positioning pin 5, etc., adjust the position of the bellows 10, so that the concave contact 7 is in good contact with the three-phase main circuit conductive rod 2, and push the dynamic test conductive rod 9 , use the bellows 10 to adjust the position of the concave contact 7 away from the conductive rod 2 of the three-phase main circuit, tighten the positioning pin 5, fix the insulating plate 11 on the connecting gas chamber body 1, connect the dynamic test conductive rod 9 to the grounding terminal 6 connected, after standing for 24 hours, carry out the SF6 gas tightness test and gas test items, and buckle the plastic-steel sealing cover 4 after passing the test.

试验位置:断开油气式变压器3与GIS组合电器12回路上的断路器、隔离开关,使油气式变压器3与GIS组合电器12之间至少有一个断开点,让油气式变压器3高压输出处于悬空状态,让GIS组合电器12其余部分接地。打开油气式变压器3与GIS组合电器12连接气室1的盖板试验装置上的密封罩4,拆掉动试验导电杆9与接地接线柱6上的短路线,分别推动ABC三相动试验导电杆9,借助波纹管10弹力使其动试验导电杆9带动凹型触头7与ABC三相主回路导电杆2连接良好,绝缘板11上的三相动试验导电杆9之间及对地可承受交流电压10kV耐压水平。Test location: Disconnect the circuit breaker and isolating switch on the circuit between the oil-gas transformer 3 and the GIS combined electrical appliance 12, so that there is at least one disconnection point between the oil-gas transformer 3 and the GIS combined electrical appliance 12, so that the high-voltage output of the oil-gas transformer 3 is at In the suspended state, the remaining parts of the GIS combined electrical appliance 12 are grounded. Open the sealing cover 4 on the cover plate test device connecting the oil-gas transformer 3 and the GIS combined electrical appliance 12 to the gas chamber 1, remove the short-circuit line on the dynamic test conductive rod 9 and the grounding terminal 6, and push the ABC three-phase dynamic test to conduct electricity respectively. Rod 9, with the help of the elastic force of bellows 10, the dynamic test conductive rod 9 drives the concave contact 7 to be well connected with the ABC three-phase main circuit conductive rod 2, and the three-phase dynamic test conductive rod 9 on the insulating plate 11 can be connected to the ground. Withstand AC voltage 10kV withstand voltage level.

如图4所示,为本实用新型油气式变压器与GIS组合电器间连接气室盖板试验装置在运行位置时的示意图。As shown in Figure 4, it is a schematic diagram of the test device for connecting the air chamber cover plate between the oil-gas type transformer and the GIS combined electrical appliance of the utility model when it is in the operating position.

运行位置:试验结束后,松开定位销5借助波纹管10的回弹力,使ABC三相动试验导电杆9带动凹型触头7离开ABC三相主回路导电杆2,ABC三相动试验导电杆9及凹型触头7到达运行位置,拧紧定位销5,并将ABC三相试验导电杆9短路并与接地接线柱6相连,测试绝缘板11密封良好后,装设密封胶垫8,扣上塑钢密封罩4后方可运行。Operating position: After the test, loosen the positioning pin 5 and rely on the resilience of the bellows 10, so that the ABC three-phase dynamic test conductive rod 9 drives the concave contact 7 to leave the ABC three-phase main circuit conductive rod 2, and the ABC three-phase dynamic test conducts electricity. Rod 9 and concave contact 7 reach the operating position, tighten positioning pin 5, and short-circuit the ABC three-phase test conductive rod 9 and connect it to the grounding terminal 6. After the test insulation plate 11 is well sealed, install the sealing rubber pad 8 and buckle It can run after the upper plastic-steel sealing cover 4.

Claims (9)

1.用于油气式变压器与GIS连接气室的盖板试验装置,其特征在于包括固定连接在连接气室上的绝缘板和连接气室内部固定在绝缘板上的波纹管,所述的绝缘板上设有定位销,用于固定动试验导电杆,所述的波纹管与动试验导电杆固定相连,动试验导电杆穿过绝缘板和波纹管与凹型触头相连,绝缘板上设有一接地接线柱,接地接线柱设置在密封罩内。1. The cover plate test device for connecting the gas chamber of the oil-gas type transformer to the GIS is characterized in that it includes an insulating plate fixedly connected to the connecting gas chamber and a corrugated pipe fixed on the insulating plate inside the connecting gas chamber, and the insulating There are positioning pins on the board for fixing the dynamic test conductive rod. The bellows are fixedly connected with the dynamic test conductive rod. The dynamic test conductive rod passes through the insulating plate and the bellows to connect with the concave contact. The grounding terminal is arranged in the sealing cover. 2.根据权利要求1所述的用于油气式变压器与GIS连接气室的盖板试验装置,其特征在于所述的密封罩与绝缘板之间设有密封胶垫。2. The cover plate test device for connecting the air chamber between the oil-gas transformer and the GIS according to claim 1, characterized in that a sealing rubber pad is provided between the sealing cover and the insulating plate. 3.根据权利要求2所述的用于油气式变压器与GIS连接气室的盖板试验装置,其特征在于所述的密封胶垫设置在连接气室的盖板孔处。3. The cover plate test device for connecting the gas chamber between the oil-gas transformer and the GIS according to claim 2, characterized in that the sealing rubber pad is arranged at the hole of the cover plate connecting the gas chamber. 4.根据权利要求1所述的用于油气式变压器与GIS连接气室的盖板试验装置,其特征在于所述的凹型触头在试验位置时与连接气室内部的主回路导电杆相连。4. The cover plate test device for connecting the gas chamber between the oil-gas transformer and the GIS according to claim 1, characterized in that the concave contact is connected to the main circuit conductive rod inside the gas chamber when it is in the test position. 5.根据权利要求1所述的用于油气式变压器与GIS连接气室的盖板试验装置,其特征在于所述的动试验导电杆在运行位置时短路连接并与接地接线柱相连。5. The cover plate test device for connecting the gas chamber of the oil-gas transformer and GIS according to claim 1, characterized in that the conductive rod for the dynamic test is short-circuited and connected to the grounding terminal when it is in the running position. 6.根据权利要求1所述的用于油气式变压器与GIS连接气室的盖板试验装置,其特征在于所述的动试验导电杆的材质为铜材质或镀锌材质。6. The cover plate test device for connecting the gas chamber between the oil-gas transformer and the GIS according to claim 1, characterized in that the material of the dynamic test conductive rod is copper or galvanized. 7.根据权利要求1所述的用于油气式变压器与GIS连接气室的盖板试验装置,其特征在于所述的密封罩的材质为塑钢材质。7. The cover plate test device for connecting the gas chamber between the oil-gas transformer and the GIS according to claim 1, characterized in that the material of the sealing cover is plastic steel. 8.根据权利要求1所述的用于油气式变压器与GIS连接气室的盖板试验装置,其特征在于所述的凹型触头的材质为软性金属材质。8. The cover plate test device for connecting the gas chamber between the oil-gas transformer and the GIS according to claim 1, characterized in that the material of the concave contact is soft metal. 9.根据权利要求8所述的用于油气式变压器与GIS连接气室的盖板试验装置,其特征在于所述的软性金属材质为黄铜材质或镀锌材质。9. The cover plate test device for connecting the gas chamber between the oil-gas transformer and the GIS according to claim 8, characterized in that the soft metal material is brass or galvanized.
CN201620699030.0U 2016-07-05 2016-07-05 It is connected the cover plate assay device of air chamber with GIS for oil-gas type transformator Active CN205786928U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620699030.0U CN205786928U (en) 2016-07-05 2016-07-05 It is connected the cover plate assay device of air chamber with GIS for oil-gas type transformator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620699030.0U CN205786928U (en) 2016-07-05 2016-07-05 It is connected the cover plate assay device of air chamber with GIS for oil-gas type transformator

Publications (1)

Publication Number Publication Date
CN205786928U true CN205786928U (en) 2016-12-07

Family

ID=58126267

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620699030.0U Active CN205786928U (en) 2016-07-05 2016-07-05 It is connected the cover plate assay device of air chamber with GIS for oil-gas type transformator

Country Status (1)

Country Link
CN (1) CN205786928U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106019022A (en) * 2016-07-05 2016-10-12 国网辽宁省电力有限公司丹东供电公司 Cover plate test device for connection air chamber of oil-gas type transformer and GIS and method for operating device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106019022A (en) * 2016-07-05 2016-10-12 国网辽宁省电力有限公司丹东供电公司 Cover plate test device for connection air chamber of oil-gas type transformer and GIS and method for operating device
CN106019022B (en) * 2016-07-05 2024-03-29 国网辽宁省电力有限公司丹东供电公司 Cover plate test device for connecting gas chamber between oil-gas type transformer and GIS and operation method

Similar Documents

Publication Publication Date Title
CN103353574B (en) A kind of insulation test device of GIS insulated tension pole
EP3823115B1 (en) Gas-insulated metal enclosed neutral point complete-set device
CN102004201B (en) Cable gas insulated switchgear (GIS) terminal tester
CN202059092U (en) Connection structure for connecting triphase enclosed GIS combination electric appliance with transformer
CN112731210A (en) An electrical preventive test method for main transformer without dismantling high-voltage side GIS
CN102707096B (en) Universal insulation cap for voltage withstand test of 66kV cables
CN204732774U (en) A kind of band isolation fracture GIS oil-gas casing structure
CN106483413A (en) High voltage direct current cable dry type easily-testing terminal
CN206947588U (en) Bypass cable applied to cable termination accesses servicing unit
CN105954658A (en) High-voltage cable GIS terminal test apparatus
CN211014556U (en) GIS equipment defect simulation system and platform
CN204179559U (en) A kind of GIS Direct Action Type manual operation isolation fracture
CN106019022A (en) Cover plate test device for connection air chamber of oil-gas type transformer and GIS and method for operating device
CN107727989A (en) The test method of oil-gas casing structure transformer
CN111239601B (en) Method for detecting double-break bus isolating switch in 220 KV power transformation combined electrical equipment
CN203800188U (en) 10kV handcart switch cabinet bus static contact special-purpose grounding device
CN208013362U (en) A kind of novel ac voltage withstanding detection device
CN205657374U (en) Solid insulation boundary switch cabinet
CN103944094A (en) 10-kV handcart switch cabinet bus fixed contact ground method and special grounding device thereof
CN204967217U (en) A connection structure that is used for between oil filled cable and dry -type crosslinked cable
CN105552770A (en) Connection body between high-voltage sleeve pipe of transformer and gas insulated switchgear (GIS) device
CN205543941U (en) Connector of transformer high -tension bushing and GIS equipment room
CN208862536U (en) Fault isolation device under drawing for 10kV cable
CN202599981U (en) General insulation cap for 66kV cable withstand voltage test
CN212180942U (en) An on-site AC withstand voltage test device for oil and gas transformer bushings

Legal Events

Date Code Title Description
C14 Grant of patent or utility model