CN205781379U CN201620461827.7U CN201620461827U CN205781379U CN 205781379 U CN205781379 U CN 205781379U CN 201620461827 U CN201620461827 U CN 201620461827U CN 205781379 U CN205781379 U CN 205781379U
Authority
CN
China
Prior art keywords
door type
type frame
bracket
girder
sides
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620461827.7U
Other languages
Chinese (zh)
Inventor
侯小祥
刘争平
任建旭
丁子全
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway First Survey and Design Institute Group Ltd
Original Assignee
China Railway First Survey and Design Institute Group Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway First Survey and Design Institute Group Ltd filed Critical China Railway First Survey and Design Institute Group Ltd
Priority to CN201620461827.7U priority Critical patent/CN205781379U/en
Application granted granted Critical
Publication of CN205781379U publication Critical patent/CN205781379U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Elevator Door Apparatuses (AREA)

Abstract

This utility model relates to a kind of 9m span heavy duty, assembled, the comprehensive hanger system of bridge-type.The most conventional each systematic pipeline mounting process, support and the pipeline of whole installation aspect are disorderly and unsystematic, are difficult to meet the process requirements of maintenance factory workshop.This utility model includes parallel two girder, and girder two ends are erected on the bracket that both sides are arranged and form single span structure;Article two, girder two ends are down-set door type frame under the bracket being perpendicular to girder, the down-set both sides door type frame having twice to be perpendicular to girder in the middle part of two girders between door type frame under bracket;It is provided with screw mandrel between door type frame top and the bottom of adjacent both sides door type frame under bracket;It is provided with screw mandrel between the bottom of adjacent both sides door type frame.This utility model uses pin-connected panel to install with bracket for fulcrum, it is not necessary to welding, simple installation;Stability Analysis of Structures, loading capacity can reach 8 tons;From heavy and light, 25Kg/M.

Description

A kind of 9m span heavy duty, assembled, the comprehensive hanger system of bridge-type
Technical field
This utility model relates to a kind of comprehensive pipeline integrated hangar system structure, is specifically related to a kind of 9m span heavy duty, assembled, the comprehensive hanger system of bridge-type.
Background technology
Large-scale maintenance factory internal pipeline gets more and more, become increasingly complex, existing various draft tube liner, air conditioning piping and various fire-fighting and spray pipe, there is again automatic alarm, monitoring, acousto-optic, the signal electric lines of force such as broadcast, and overhaul factory's limited space, at present when carrying out factory's pipeline designs, according to the design specification of each system and requirement is used to arrange corresponding pipeline voluntarily by each specialty, typically no pipeline layout suspension and support, a lot of spaces pipeline is caused more to concentrate, even position conflict is interfered, indoor pipeline is caused often to occur arranging unreasonable, invest uneconomical, outward appearance is unsightly, consider the most comprehensive problem.
And the most conventional each systematic pipeline mounting process, support and the pipeline of whole installation aspect are disorderly and unsystematic, not only it is difficult to meet the process requirements of maintenance factory workshop, and this field standard is relatively low, still use traditional shape steel bracket, the use requirement of present stage all can not be met plus welding and coating paint, outward appearance or durability.So do not only result in construction, transformation and upgrade task amount greatly, and safety, maintainability, reliability and economy with the having higher standard requirement to system operation.Therefore make full use of advanced technology and successful experience, system that large-scale maintenance factory pipeline is carried out general space management research is the most very urgent, imperative.
Summary of the invention
The purpose of this utility model is to provide a kind of 9m span heavy duty, assembled, the comprehensive hanger system of bridge-type, it is adaptable in building, the layering of various pipelines and cable bridge is installed.
The technical scheme that this utility model is used is:
A kind of 9m span heavy duty, assembled, the comprehensive hanger system of bridge-type, it is characterised in that:
Including two parallel girders, girder two ends are erected on the bracket that both sides are arranged and form single span structure;
Article two, it is hung with door type frame under the bracket being perpendicular to girder below girder two ends, the down-set both sides door type frame having twice to be perpendicular to girder in the middle part of two girders between door type frame under bracket;
It is provided with screw mandrel between door type frame top and the bottom of adjacent both sides door type frame under bracket;It is provided with screw mandrel between the bottom of adjacent both sides door type frame.
Distance between the door type frame of twice both sides is 3 meters, and the distance between both sides door type frame with door type frame under adjacent bracket is 3 meters.
The end that screw mandrel is positioned at bottom the door type frame of both sides is fixed by the multi-direction screw connecting piece arranged bottom the door type frame of both sides.
Screw mandrel is positioned at the end at door type frame top under bracket to be fixed by the bracket otic placode arranged on bracket.
Under bracket, door type frame and both sides door type frame are the rectangle frame structure of layering.
This utility model has the advantage that
This utility model uses pin-connected panel to install with bracket for fulcrum, it is not necessary to welding, simple installation;Stability Analysis of Structures, loading capacity can reach 8 tons;From heavy and light, 25Kg/M.
Accompanying drawing explanation
Fig. 1 is this utility model elevation.
Fig. 2 is this utility model plane graph.
Fig. 3 is door type frame structure chart under bracket.
Fig. 4 is both sides door type frame structure charts.
In figure, 1-girder, door type frame under 2-bracket, 3-both sides door type frame, 4-screw mandrel, the multi-direction screw connecting piece of 5-, 6-bracket otic placode, 7-bracket.
Detailed description of the invention
Below in conjunction with detailed description of the invention, this utility model is described in detail.
A kind of 9m span heavy duty that this utility model relates to, assembled, the comprehensive hanger system of bridge-type, including two parallel girders 1, girder 1 two ends are erected on the bracket 7 that both sides are arranged and form single span structure.Article two, it is hung with door type frame 2 under the bracket being perpendicular to girder 1 below girder 1 two ends, the down-set both sides door type frame 3 having twice to be perpendicular to girder 1 in the middle part of two girders 1 between door type frame 2 under bracket, under bracket, door type frame 2 and both sides door type frame 3 are connected with three-dimensional connector with girder 1.Distance between twice both sides door type frame 3 is 3 meters, and the distance between both sides door type frame 3 with door type frame 2 under adjacent bracket is 3 meters, and single span structure adds up to 9 meters, it is ensured that minimum spacing 3 meters has a strong point.Under the bracket at two ends, door type frame 2 is bolted on bracket 7 by special heavy duty suspension bracket hanger, clamping fixed with beam.
It is provided with screw mandrel 4 between door type frame 2 top and the bottom of adjacent both sides door type frame 3 under bracket;It is provided with screw mandrel 4 between the bottom of adjacent both sides door type frame 3.The end that screw mandrel 4 is positioned at bottom both sides door type frame 3 is fixed by the multi-direction screw connecting piece 5 arranged bottom both sides door type frame 3.Screw mandrel 4 is positioned at the end at door type frame 2 top under bracket to be fixed by the bracket otic placode 6 arranged on bracket 7.
Under bracket, door type frame 2 and both sides door type frame 3 are by U-shaped finished product channel-section steel, push button snap close, right-angle connector composition, and structure is the rectangle frame of layering, arranges tube bank in layer as required, and pipeline can be fixed in tube bank.Restrain the opening surface being fixed on U-lag steel by tube bank button pad screw mandrel.Cable bridge can be laid in door type frame, is screwed on the long aperture of U-lag steel.
Content of the present utility model is not limited to cited by embodiment, the conversion of any equivalence that technical solutions of the utility model are taked by those of ordinary skill in the art by reading this utility model description, is claim of the present utility model and is contained.

Claims (5)

1. the heavy duty of 9m span, assembled, the comprehensive hanger system of bridge-type, it is characterised in that:
Including two parallel girders (1), girder (1) two ends are erected on bracket (7) the upper formation single span structure that both sides are arranged;
Article two, it is hung with door type frame (2) under the bracket being perpendicular to girder (1) below girder (1) two ends, down-set both sides door type frames (3) having twice to be perpendicular to girder (1) in two girders (1) middle part between door type frame (2) under bracket;
Screw mandrel (4) it is provided with between door type frame (2) top and the bottom of adjacent both sides door type frame (3) under bracket;It is provided with screw mandrel (4) between the bottom of adjacent both sides door type frame (3).
A kind of 9m span heavy duty the most according to claim 1, assembled, the comprehensive hanger system of bridge-type, it is characterised in that:
Distance between twice both sides door type frame (3) is 3 meters, and both sides door type frame (3) is 3 meters with distance between door type frame (2) under adjacent bracket.
A kind of 9m span heavy duty the most according to claim 1, assembled, the comprehensive hanger system of bridge-type, it is characterised in that:
Screw mandrel (4) is positioned at the end of both sides door type frame (3) bottom to be fixed by the multi-direction screw connecting piece (5) of both sides door type frame (3) bottom setting.
A kind of 9m span heavy duty the most according to claim 1, assembled, the comprehensive hanger system of bridge-type, it is characterised in that:
Screw mandrel (4) is positioned at the end at door type frame under bracket (2) top to be fixed by the upper bracket otic placode (6) arranged of bracket (7).
A kind of 9m span heavy duty the most according to claim 1, assembled, the comprehensive hanger system of bridge-type, it is characterised in that:
Under bracket, door type frame (2) and both sides door type frame (3) are the rectangle frame structure of layering.
CN201620461827.7U 2016-05-20 2016-05-20 A kind of 9m span heavy duty, assembled, the comprehensive hanger system of bridge-type Active CN205781379U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620461827.7U CN205781379U (en) 2016-05-20 2016-05-20 A kind of 9m span heavy duty, assembled, the comprehensive hanger system of bridge-type

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620461827.7U CN205781379U (en) 2016-05-20 2016-05-20 A kind of 9m span heavy duty, assembled, the comprehensive hanger system of bridge-type

Publications (1)

Publication Number Publication Date
CN205781379U true CN205781379U (en) 2016-12-07

Family

ID=58118170

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620461827.7U Active CN205781379U (en) 2016-05-20 2016-05-20 A kind of 9m span heavy duty, assembled, the comprehensive hanger system of bridge-type

Country Status (1)

Country Link
CN (1) CN205781379U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106907525A (en) * 2017-04-20 2017-06-30 中天西北建设投资集团有限公司 A kind of para-seismic support installation engineering method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106907525A (en) * 2017-04-20 2017-06-30 中天西北建设投资集团有限公司 A kind of para-seismic support installation engineering method

Similar Documents

Publication Publication Date Title
CN204297955U (en) The three-dimensional accurate positioning device of crane in bridge type and crane in bridge type thereof
CN202370147U (en) Ceiling lamp groove structure of lightgage steel joist framework
CN104963407A (en) Building structure and construction method thereof
CN205639870U (en) A pipeline gallows is synthesized in heavy construction
CN205781379U (en) A kind of 9m span heavy duty, assembled, the comprehensive hanger system of bridge-type
CN204475513U (en) A kind of building structure
CN204284665U (en) A kind of diagonal-bracing type suspension and support of rationally arranging for line classification
CN205804586U (en) A kind of 12m span comprehensive hanger system of bridge-type heavily loaded, assembled
CN105587058A (en) Perforated aluminum plate curtain wall of external wall
CN203237404U (en) Passenger cabin main pipe positioning and installing device
CN205479755U (en) A synthesize integrated suspension system of pipe support that is used for motor car application storehouse of inspecting
CN203230140U (en) Overhead movable floor
CN203213321U (en) Construction structure of outer wall deformation joint of building
CN102278532A (en) Two-directional bridge frame connector
CN204139398U (en) The syndeton of a kind of curtain wall crossbeam and column
CN204475534U (en) A kind of syndeton of column node
CN205155357U (en) Crane span structure supporting component with prop up gallows installation function
CN209567694U (en) A kind of assembling type steel structure hoistway section of preset track
CN204187128U (en) A kind of cable testing bridge threeway underframe
CN104832708A (en) Pipeline pre-installing frame
CN204385887U (en) A kind of seal channel based on aluminium extruded sections
CN208074291U (en) Prefabricated for pipeline ensemble, installation precast combined holder
CN203701555U (en) Movable type pipe truss installation platform
CN218449331U (en) Layered multi-way bridge frame assembly member
CN205478716U (en) A connecting piece that is used for motor car application institute storehouse of inspecting synthesis pipe support

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: BEIJING YAOU ZHENDA TECHNOLOGY DEVELOPMENT CO.,LTD.

Assignor: CHINA RAILWAY FIRST SURVEY AND DESIGN INSTITUTE GROUP Co.,Ltd.

Contract record no.: X2022980015517

Denomination of utility model: A 9m-span heavy-duty, assembled, bridge-type integrated support and hanger system

Granted publication date: 20161207

License type: Common License

Record date: 20220919

EE01 Entry into force of recordation of patent licensing contract