CN205753283U - A kind of line box fixing device - Google Patents
A kind of line box fixing device Download PDFInfo
- Publication number
- CN205753283U CN205753283U CN201620453934.5U CN201620453934U CN205753283U CN 205753283 U CN205753283 U CN 205753283U CN 201620453934 U CN201620453934 U CN 201620453934U CN 205753283 U CN205753283 U CN 205753283U
- Authority
- CN
- China
- Prior art keywords
- line box
- hole
- module
- fixing device
- stuck
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Connection Or Junction Boxes (AREA)
Abstract
The utility model discloses a kind of line box fixing device, be used for filling wall line box is installed.This line box fixing device specifically includes stuck-module and fixed plate.Wherein, the hole, location for sheathed filling wall line box it is provided with on stuck-module, the aperture area in hole, location is more than the base area filling wall line box, it is provided with horizontal control lines perpendicular to one another and longitudinally controlled line on stuck-module, stuck-module is additionally provided with the bolt hole for removably connecting with filling wall;Fixed plate removably connects with stuck-module, and the length of fixed plate is more than the width in hole, location.Use the line box fixing device that this utility model provides, it is possible to ensure that filled wall is reached the standard grade the installation quality of box, it is ensured that after construction, line box absolute altitude is consistent, line box surfacing.
Description
Technical field
This utility model relates to technical field of building construction, particularly to a kind of line box fixing device.
Background technology
Filling wall and refer to the body of wall of frame structure, rise and go along with sb. to guard him and compartmentation, weight is undertaken by beam column, fills out
Fill wall not load-bearing.In building construction process, generally require the line box to filled wall and install.
In prior art, it is usually and directly line box is installed in filled wall, rely on regarding of staff
Feel that the installation site to line box is adjusted and fixes.For a long time, in installation process, even if one opens
Beginning to obtain the most perfect by the installation site plan of line box, line box absolute altitude is consistent, and line box face is the most smooth, but after
Needing to smear cement mortar around online box in continuous work progress, line box often moves in this process
Dynamic, after causing construction to complete, line box absolute altitude is inconsistent, the face out-of-flatness of line box, have a strong impact on construction quality and
Outward appearance, it is impossible to meet construction reference requirement.For a long time, this form of construction work installation quality one to line box
Directly it is difficult to control.Visible, in prior art, when the line box of filled wall is installed, not only install
Construction trouble, and line box installed height mark differs, and flatness is poor, and line box is installed undesirable, needs
Repeatedly to keep in repair, to cause waste of material, the most economical and the most practical.
Therefore, how to improve filled wall and reach the standard grade the installation quality of box, be current those skilled in the art urgently
Technical problem to be solved.
Utility model content
In view of this, this utility model provides a kind of for installing the line box fixing device filling wall line box,
Ensure that filled wall is reached the standard grade the installation quality of box, it is ensured that after construction, line box absolute altitude is consistent, line box surface
Smooth.
For achieving the above object, the following technical scheme of this utility model offer:
A kind of line box fixing device, is used for installing filling wall line box, and described line box fixing device includes:
Stuck-module, described stuck-module is provided with the hole, location for sheathed filling wall line box, described
The aperture area in hole, location, more than the base area of described filling wall line box, described stuck-module is provided with
Horizontal control lines perpendicular to one another and longitudinally controlled line, described stuck-module is additionally provided with for filling
The bolt hole that wall removably connects;
The fixed plate removably connected with described stuck-module, the length of described fixed plate is more than described location
The width in hole.
Preferably, in above-mentioned line box fixing device, hole, described location is hole, square location.
Preferably, in above-mentioned line box fixing device, described fixed plate is corresponding with on described stuck-module to be set
It is equipped with screw hole.
Preferably, in above-mentioned line box fixing device, both sides, hole, described location have been respectively provided with at least two
Described screw hole.
Preferably, in above-mentioned line box fixing device, in the longitudinal direction in hole, described screw hole the most described location
Heart line is arranged symmetrically with, and the horizontal center line that described screw hole is near hole, described location is arranged.
Preferably, in above-mentioned line box fixing device, both sides, hole, described location have been respectively provided with at least one
Bolt hole.
Preferably, in above-mentioned line box fixing device, described longitudinally controlled line and the longitudinal direction in hole, described location
Centrage overlaps.
Preferably, in above-mentioned line box fixing device, described horizontal control lines and the base in hole, described location
Line overlaps.
Preferably, in above-mentioned line box fixing device, described stuck-module includes right module and left side mould
The profile specular of block, the profile of described left module and described right module.
From technique scheme it can be seen that use this utility model provide be used for install filling wall line box
Line box fixing device, the most economical and the most practical, and construction method of installation once survives, simple and convenient,
Construction effect also complies with requirement, additionally, the line box absolute altitude after molding is consistent, and the surface of line box 5 and metope
Smooth, meet design and the requirement of technical standard.
Accompanying drawing explanation
In order to be illustrated more clearly that this utility model embodiment or technical scheme of the prior art, below will
The accompanying drawing used required in embodiment or description of the prior art is briefly described, it should be apparent that,
Accompanying drawing in describing below is only embodiments more of the present utility model, for ordinary skill people
From the point of view of Yuan, on the premise of not paying creative work, it is also possible to obtain the attached of other according to these accompanying drawings
Figure.
The structural representation of the line box fixing device that Fig. 1 provides for this utility model embodiment.
In figure: 1-bolt hole, 2-screw hole, 3-thread tapping, 4-fixed plate, 5-fills wall line box, 6-water
Flat control line, the longitudinally controlled line of 7-, 8-stuck-module.
Detailed description of the invention
The utility model discloses a kind of for installing the line box fixing device filling wall line box, it is possible to ensure
Filled wall is reached the standard grade the installation quality of box, it is ensured that after construction, line box absolute altitude is consistent, line box surfacing.
Below in conjunction with the accompanying drawing in this utility model embodiment, to the technology in this utility model embodiment
Scheme is clearly and completely described, it is clear that described embodiment is only this utility model one
Divide embodiment rather than whole embodiments.Based on the embodiment in this utility model, this area is common
The every other embodiment that technical staff is obtained under not making creative work premise, broadly falls into this
The scope of utility model protection.
Refer to the structural representation of the line box fixing device that Fig. 1, Fig. 1 provide for this utility model embodiment.
The line box fixing device that this utility model embodiment provides, is used for installing filling wall line box.This line box
Fixing device specifically includes stuck-module 8 and the fixed plate 4 removably connected with stuck-module 8.Wherein,
Being provided with hole, location on stuck-module 8, the aperture area in hole, location is more than filling wall line box 5 (hereinafter referred to as
Line box 5) base area, during construction, it is carried out by hole, location for the chassis outer side of sheathed online box 5
Location, leaves predeterminable range between inwall and the chassis outer side edges of line box 5 in hole, location, constitutes box groove;
Further, stuck-module 8 is additionally provided with the bolt hole 1 for removably connecting with filling wall, stuck-module
Horizontal control lines 6 perpendicular to one another and longitudinally controlled line 7 it is additionally provided with on 8;Additionally, the length of fixed plate 4
Degree is more than the width in hole, location.
In preferred specific embodiment, the longitudinally controlled line 7 in above-mentioned line box fixing device and hole, location
Longitudinal centre line overlap, horizontal control lines 8 with position hole hemline overlap.
In preferred specific embodiment, as shown in fig. 1, fixed plate in line box fixing device 4 with
(both sides, hole, location are respectively arranged with two screw holes to be correspondingly arranged on four screw holes 2 on stuck-module 8
2), during construction, fixed plate 4 removably connects with stuck-module 8 across hole, location and by screw hole 2.
Further, the longitudinal centre line in screw hole 2 relative localization hole is arranged symmetrically with, and screw hole 2 is close
The horizontal center line in hole, location is arranged.
In preferred specific embodiment, as shown in fig. 1, the both sides, hole, location of stuck-module 8 are respectively
At least provided with a bolt hole 1.During construction, stuck-module 8 is by thread tapping and line box 5 installation site
The filling wall at place is connected, i.e. stuck-module 8 is fixed on filling wall by thread tapping through bolt hole 1.
Additionally, as shown in fig. 1, during construction, fixed plate 4 is connected by thread tapping 3 with line box 5.
Concrete work progress is as follows:
1) snap the line
Determine the installation site filling wall line box 5 according to fine fitment construction drawing and electric installation drawing, wherein, hang down
Straight line is the longitudinal centre line of line box 5, and horizontal line is the hemline of line box 5, and same indoor water horizontal line is high
Degree error is less than 2mm.
2) dig wall chase, use particular manufacturing craft to reserve
Self-control line box particular manufacturing craft, determines according to the longitudinal centre line of line box 5 and the diameter d of built-in pipe and fills out
Filling the slotting position on wall, groove width is 15mm+d+15mm, and the degree of depth is d+15mm, it is necessary to specially
Slot according to the played line of ink marker with machinery, it is allowed to error must not exceed 5mm.
3) line box fixing device is used to position
By on sheathed for the stuck-module 8 in line box fixing device online box 5, line box 5 is positioned at fills wall
In above-mentioned fluting, the horizontal control lines 6 in line box fixing device overlaps with the horizontal line in snap the line, line box
Longitudinally controlled line 7 in fixing device and the vertical line in snap the line, to ensure the good line box 5 of subsequent installation
The rear absolute altitude making line box 5 keeps consistent and meets construction requirement;
The base both sides of online box 5 have been respectively provided with at least an installing hole, consolidating in line box fixing device
Determine plate 4 to be connected with this installing hole by thread tapping 3, make line box 5 and line box fixing device Primary Location;
In line box fixing device, the both sides in the hole, location of stuck-module 8 have been respectively provided with at least two screws
Hole 2, fixed plate 4 is provided with the screw hole 2 corresponding with the screw hole 2 on stuck-module 8, passes through spiral shell
Fixed plate 4 is connected by silk hole 2 with stuck-module 8, reaches the purpose of fixing line box 5 so that line box 5
Surfacing is remained in work progress and after construction.
4) line box is installed
Smear inside box groove by cement mortar.After cement mortar initial set four hours, line box fixing device of dismantling,
By cement mortar, line box surrounding is repaired again.
Easily know, position and quantity, this area skill are arranged for bolt hole 1 and screw hole 2
Art personnel can have multiple different schemes.Such as, bolt hole 1 is provided with three or four, lays respectively at
The upper and lower sides in hole, location or other peripheral positions in hole, location;Such as, screw hole 2 is provided with 6, point
It is not positioned at the upper and lower sides in hole, location;Etc..Therefore this utility model to this and is not specifically limited.
In a particular embodiment, the hole, location on the stuck-module 8 in above-mentioned line box fixing device is square
Hole, location, with preferably adaptive with line box 5, and reaches the purpose being accurately positioned.
In a particular embodiment, stuck-module 8 can be integral structure, it is also possible to be split-type structural.
Split-type structural refers to that stuck-module 8 is made up of right module and left module, the profile of left module with
The profile specular of right module, in order to manufacture, it is simple to dismounting.Those skilled in the art can
To select suitable scheme as required, this utility model is to this and is not specifically limited.
Additionally, the base both sides filling wall line box that this utility model provides at least are respectively provided with an installation
Hole, during construction, the fixed plate 4 in line box fixing device is by thread tapping 3 and the installation filled on wall line
Hole connects.
As fully visible, the line box fixing device that this utility model provides, the most economical and the most practical, and install
Construction method once survives, simple and convenient, and construction effect also complies with requirement, additionally, the line box after molding
Absolute altitude is consistent, the surface of line box 5 and wall surface levelling, meets design and the requirement of technical standard.
Finally, in addition it is also necessary to explanation, in this article, the relational terms of such as first and second or the like
It is used merely to separate an entity or operation with another entity or operating space, and not necessarily requires
Or imply relation or the order that there is any this reality between these entities or operation.And, art
Language " includes ", " comprising " or its any other variant are intended to comprising of nonexcludability, thus
Make to include that the process of a series of key element, method, article or equipment not only include those key elements, and
Also include other key elements being not expressly set out, or also include for this process, method, article or
The key element that person's equipment is intrinsic.In the case of there is no more restriction, by statement " including ... "
The key element limited, it is not excluded that also deposit in including the process of described key element, method, article or equipment
In other identical element.
In this specification, each embodiment uses the mode gone forward one by one to describe, and each embodiment stresses
Being the difference with other embodiments, between each embodiment, identical similar portion sees mutually.
Described above to the disclosed embodiments, makes professional and technical personnel in the field be capable of or uses
This utility model.Multiple amendment to these embodiments will be aobvious for those skilled in the art
And be clear to, generic principles defined herein can be without departing from spirit or scope of the present utility model
In the case of, realize in other embodiments.Therefore, this utility model is not intended to be limited to institute herein
These embodiments shown, and it is to fit to consistent with principles disclosed herein and features of novelty the widest
Scope.
Claims (9)
1. a line box fixing device, is used for installing filling wall line box, it is characterised in that described line box fixing device includes:
Stuck-module (8), the hole, location for sheathed filling wall line box (5) it is provided with on described stuck-module (8), the aperture area in hole, described location is more than the base area of described filling wall line box (5), it is provided with horizontal control lines (6) perpendicular to one another and longitudinally controlled line (7) on described stuck-module (8), described stuck-module (8) is additionally provided with the bolt hole (1) for removably connecting with filling wall;
The fixed plate (4) removably connected with described stuck-module (8), the length of described fixed plate (4) is more than the width in hole, described location.
Line box fixing device the most according to claim 1, it is characterised in that hole, described location is hole, square location.
Line box fixing device the most according to claim 1, it is characterised in that be correspondingly arranged on screw hole (2) on described fixed plate (4) and described stuck-module (8).
Line box fixing device the most according to claim 3, it is characterised in that both sides, hole, described location have been respectively provided with at least two described screw holes (2).
Line box fixing device the most according to claim 4, it is characterised in that the longitudinal centre line in hole, described screw hole (2) the most described location is arranged symmetrically with, and the horizontal center line setting that described screw hole (2) is near hole, described location.
Line box fixing device the most according to claim 1, it is characterised in that both sides, hole, described location have been respectively provided with at least a bolt hole (1).
Line box fixing device the most according to claim 1, it is characterised in that described longitudinally controlled line (7) overlaps with the longitudinal centre line in hole, described location.
Line box fixing device the most according to claim 1, it is characterised in that described horizontal control lines (6) overlaps with the hemline in hole, described location.
Line box fixing device the most according to claim 1, it is characterised in that described stuck-module (8) includes the profile specular of right module and left module, the profile of described left module and described right module.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620453934.5U CN205753283U (en) | 2016-05-17 | 2016-05-17 | A kind of line box fixing device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620453934.5U CN205753283U (en) | 2016-05-17 | 2016-05-17 | A kind of line box fixing device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205753283U true CN205753283U (en) | 2016-11-30 |
Family
ID=57364740
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620453934.5U Expired - Fee Related CN205753283U (en) | 2016-05-17 | 2016-05-17 | A kind of line box fixing device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205753283U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108695794A (en) * | 2018-04-08 | 2018-10-23 | 五冶集团上海有限公司 | Box installation method is electrically reserved in a kind of secondary structure wall |
CN110544901A (en) * | 2019-09-18 | 2019-12-06 | 中国二十二冶集团有限公司 | secondary structure wall line box stabilizing and positioning device and construction method |
-
2016
- 2016-05-17 CN CN201620453934.5U patent/CN205753283U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108695794A (en) * | 2018-04-08 | 2018-10-23 | 五冶集团上海有限公司 | Box installation method is electrically reserved in a kind of secondary structure wall |
CN110544901A (en) * | 2019-09-18 | 2019-12-06 | 中国二十二冶集团有限公司 | secondary structure wall line box stabilizing and positioning device and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207144170U (en) | A kind of prefabricated out-hung panel upper and lower opening waterproof connecting structure of prefabricated concrete structure | |
CN205753283U (en) | A kind of line box fixing device | |
CN207283099U (en) | A kind of wall pre-embedded hydroelectric line case positioning device | |
CN207609126U (en) | Armor for the super flat one-pass molding load bearing heat preserving terrace of super large stitches | |
CN102926538A (en) | Reaction box and construction method of reaction wall | |
CN209025439U (en) | A kind of height-adjustable Wedge device | |
CN108952165A (en) | A kind of prefabricated processing of sheath assembly in a row and pre-buried construction method | |
CN208486648U (en) | A kind of power tower stable base | |
CN103967331A (en) | Surrounding separation plate capable of ascending and descending | |
CN206976968U (en) | Adjustable distribution box | |
CN104196135A (en) | Heat-insulation construction and energy conservation process for exterior walls | |
CN207988413U (en) | Ground leveling component | |
CN207685855U (en) | A kind of anti-anti-floating large steel moulding plate device that inclines of cast-in-place concrete retaining wall | |
CN216340631U (en) | Modular passing-through stone structure | |
CN105781056B (en) | Special-shaped metope moulding can adjust gusseted point hang device | |
CN205712904U (en) | Abnormity metope moulding scalable gusseted point hang device | |
CN204962213U (en) | LED display screen floor stand installs floorbar | |
CN206558392U (en) | A kind of combined type secretly buries switch enclosure | |
CN206071066U (en) | Concreting surface smoothness precise control instrument | |
CN205530720U (en) | Integral type bathroom corner waterproof construction | |
CN202544178U (en) | Three-dimensional connection adjusting mechanism for curtain wall | |
CN204919587U (en) | Basis built -in fitting with adjustable it is two -way | |
CN211740219U (en) | Pay-off device for measuring fan-shaped structure by matching CAD software with theodolite | |
CN207812474U (en) | A kind of hanging type integrated house basis | |
CN206418796U (en) | A kind of normal formula pipe combination supporting system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20161130 Termination date: 20180517 |
|
CF01 | Termination of patent right due to non-payment of annual fee |