stirring pool
sedimentation tank
stirring
grug feeding
feeding jar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520935125.3U
Other languages
Chinese (zh)
Inventor
王芬
王宇飞
季民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin University
Original Assignee
Tianjin University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin University filed Critical Tianjin University
Priority to CN201520935125.3U priority Critical patent/CN205740459U/en
Application granted granted Critical
Publication of CN205740459U publication Critical patent/CN205740459U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Separation Of Suspended Particles By Flocculating Agents (AREA)

Abstract

The utility model discloses a kind of packaged type earth's surface water body algal tufa emergency flight control integrated apparatus, including the first stirring pool, second stirring pool, sedimentation tank, water leg, intake pump, effusion meter, first grug feeding jar and the second grug feeding jar, first stirring pool, second stirring pool and sedimentation tank are arranged side by side successively, the contour setting in upper end of the sludge bucket at the end of the first stirring pool and the second stirring pool and sedimentation tank, the lower surface of the first stirring pool and the second stirring pool is connected with support, the bottom of the second stirring pool and sedimentation tank are provided with connected entrance, communicated by overfall on the top of the first stirring pool and the second stirring pool, first, two grug feeding jars pass through pipeline respectively with first, second stirring pool connects, support and sedimentation tank are flexibly connected with the flat board of platform trailer.This utility model may move, and algal tufa is broken out and disastrous destruction can be caused to process in time water ecological setting by compact conformation.Hydraulic detention time is short, and coagulant, flocculation aid dosage are little, and treatment effect is good.

Description

A kind of packaged type earth's surface water body algal tufa emergency flight control integrated apparatus
Technical field
This utility model belongs to water pollution Prevention Technique field, and specifically, relating to a kind of packaged type earth's surface water body algal tufa should Anxious control integrated apparatus.
Background technology
In recent years, due to nature and the impact of anthropic factor, each pollutant entering natural water body is continuously increased, particularly nitrogen, Entering of phosphorus compound, makes Eutrophication Status aggravate, and then causes water body algal tufa frequently to break out.Algal tufa breaks out not only can Making the water surface form stench offscum, cause Fish mortality, some cyanophyceae also can produce toxin, even can cause water head site water quality Deteriorate.Algal tufa breaks out and water ecological setting can be caused disastrous destruction, has a strong impact on civil plantation environment, even threatens The safety of drinking water.Mostly current processing equipment is to be stirred respectively and precipitate, and equipment volume is big, fixed installation, it is impossible to full Full border is applied.
Utility model content
This utility model is multiple for river course algal tufa in summer, storm runoff causes surface water body water quality deterioration, form serious pollution etc. Problem, and for the tradition defects such as control algae bloom engineering flexibility is poor, capital construction cost is big, it is provided that a kind of packaged type earth's surface water body Algal tufa emergency flight control integrated apparatus.
The technical solution of the utility model is summarized as follows:
A kind of packaged type earth's surface water body algal tufa emergency flight control integrated apparatus, including first stirring pool the 4, second stirring pool 6, sinks Pond, shallow lake 10, water leg 12, intake pump 1, effusion meter the 2, first grug feeding jar 15 and the second grug feeding jar 16, inlet pipeline is successively After connecting valve, intake pump 1, effusion meter 2, the water inlet 3 with the first stirring pool 4 is connected, and the middle part of sedimentation tank is provided with tiltedly Tube fixing device 8, inclined tube fixed mount is provided with inclined tube 9, and the bottom of sedimentation tank is provided with sludge bucket 14 and discharge pipeline 13, precipitation The top in pond is communicated with water leg 12 by downflow weir 11, and the bottom of water leg 12 is provided with outlet pipe, the first stirring pool 4, Second stirring pool 6 and sedimentation tank 10 are arranged side by side successively, the end of the first stirring pool 4 and the second stirring pool 6 and the dirt in sedimentation tank The contour setting in upper end of bucket 14, the lower surface of the first stirring pool 4 and the second stirring pool 6 is connected with support 17, the second stirring The bottom in pond 6 and sedimentation tank 10 are provided with connected entrance 7, pass through overfall on the top of the first stirring pool 4 and the second stirring pool 6 5 communicate, and the first grug feeding jar 15 is connected by pipeline and the first stirring pool 4, and the second grug feeding jar 16 is by pipeline and the second stirring Pond 6 connects, and support 17 and sedimentation tank 10 are flexibly connected with the flat board of platform trailer.
Advantage of the present utility model:
This utility model may move, and algal tufa is broken out and disastrous destruction can be caused to locate in time water ecological setting by compact conformation Reason.Hydraulic detention time is short, and coagulant, flocculation aid dosage are little, and treatment effect is good.
Accompanying drawing explanation
Fig. 1 is generalized section of the present utility model.
Detailed description of the invention
With embodiment, this utility model is further described below in conjunction with the accompanying drawings.
A kind of packaged type earth's surface water body algal tufa emergency flight control integrated apparatus, including first stirring pool the 4, second stirring pool 6, sinks Pond, shallow lake 10, water leg 12, intake pump 1, effusion meter the 2, first grug feeding jar 15 and the second grug feeding jar 16, inlet pipeline is successively After connecting valve, intake pump 1, effusion meter 2, the water inlet 3 with the first stirring pool 4 is connected, and the middle part of sedimentation tank is provided with tiltedly Tube fixing device 8, inclined tube fixed mount is provided with inclined tube 9, and the bottom of sedimentation tank is provided with sludge bucket 14 and discharge pipeline 13, precipitation The top in pond is communicated with water leg 12 by downflow weir 11, and the bottom of water leg 12 is provided with outlet pipe, the first stirring pool 4, Second stirring pool 6 and sedimentation tank 10 are arranged side by side successively, the end of the first stirring pool 4 and the second stirring pool 6 and the dirt in sedimentation tank The contour setting in upper end of bucket 14, the lower surface of the first stirring pool 4 and the second stirring pool 6 is connected with support 17, the second stirring The bottom in pond 6 and sedimentation tank 10 are provided with connected entrance 7, pass through overfall on the top of the first stirring pool 4 and the second stirring pool 6 5 communicate, and the first grug feeding jar 15 is connected by pipeline and the first stirring pool 4, and the second grug feeding jar 16 is by pipeline and the second stirring Pond 6 connects, and the first grug feeding jar 15 and the second grug feeding jar 16 can be fixedly installed on the outer surface of stirring pool, support 17 and precipitation Pond 10 is flexibly connected with the flat board of platform trailer.
Embodiment 1
Use packaged type earth's surface water body algal tufa emergency flight control integrated apparatus that certain algal tufa outburst lake water is processed, this lake water Chlorophyll content is 8-25 μ g/L, and turbidity is 8-20NTU.
Process step is as follows:
1) coagulant and flocculation aid add
Pending lake water is inputted in the first stirring pool 4 and the second stirring pool 6 by intake pump, and flow is 8t/h, hydraulic detention time For 17min.Meanwhile dosing pump is from water-soluble equipped with drawing aluminium polychlorid the first grug feeding jar 15 of polyaluminium aluminum water solution Liquid adds that to make the concentration that finally adds of aluminium polychlorid in the first stirring pool 4 be 80mg/L;From equipped with polyacrylamide solution Second grug feeding jar 16 is drawn polyacrylamide solution add in the second stirring pool 6, make the final concentration of of polyacrylamide 1.0mg/L。
2) reaction
Lake water is mixed with medicament in stirring pool by agitator and is reacted 5min, and the lake water gravity flow stirred enters tube settling District, carries out being sufficiently mixed reaction.
3) precipitation
Precipitation certain time after, current along inclined tube by lower from through sedimentation tank downflow weir 11 water outlet, coagulating sedimentation thing is then by sedimentation tank The discharge pipeline periodic exhaustion at the end.
4) operational effect
Process delivery turbidity is 4-7NTU, and chlorophyll is 2-11 μ g/L.Meet " water environment quality standard " (GB3838-2002) IV class water body standard.
The flow process that above example processes sewage to this utility model is set forth, and contributes to understanding this utility model, but this reality With novel embodiment and be not restricted to the described embodiments, any without departing from the change made under this utility model principle, repair Adorn, substitute, combine, simplify, all should be the substitute mode of equivalence, within being included in protection domain of the present utility model.

Claims (1)

1. a packaged type earth's surface water body algal tufa emergency flight control integrated apparatus, including the first stirring pool, the second stirring pool, precipitation Pond, water leg, intake pump, effusion meter, the first grug feeding jar and the second grug feeding jar, inlet pipeline be sequentially connected with valve, intake pump, After effusion meter, the water inlet with the first stirring pool is connected, and the middle part of sedimentation tank is provided with inclined tube fixed mount, on described inclined tube fixed mount Being provided with inclined tube, the bottom of sedimentation tank is provided with sludge bucket and discharge pipeline, and the top of sedimentation tank is communicated with water leg by downflow weir, The bottom of water leg is provided with outlet pipe, it is characterized in that described first stirring pool, the second stirring pool and sedimentation tank are arranged side by side successively, The contour setting in upper end of the sludge bucket at the end of the first stirring pool and the second stirring pool and sedimentation tank, the first stirring pool and the second stirring The lower surface in pond is connected with support, and the bottom of the second stirring pool and sedimentation tank are provided with connected entrance, stir at the first stirring pool and second The top mixing pond is communicated by overfall, and the first grug feeding jar is connected by pipeline and the first stirring pool, and the second grug feeding jar passes through pipeline Being connected with the second stirring pool, support and sedimentation tank are flexibly connected with the flat board of platform trailer.
CN201520935125.3U 2015-11-20 2015-11-20 A kind of packaged type earth's surface water body algal tufa emergency flight control integrated apparatus Expired - Fee Related CN205740459U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520935125.3U CN205740459U (en) 2015-11-20 2015-11-20 A kind of packaged type earth's surface water body algal tufa emergency flight control integrated apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520935125.3U CN205740459U (en) 2015-11-20 2015-11-20 A kind of packaged type earth's surface water body algal tufa emergency flight control integrated apparatus

Publications (1)

Publication Number Publication Date
CN205740459U true CN205740459U (en) 2016-11-30

Family

ID=57388790

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520935125.3U Expired - Fee Related CN205740459U (en) 2015-11-20 2015-11-20 A kind of packaged type earth's surface water body algal tufa emergency flight control integrated apparatus

Country Status (1)

Country Link
CN (1) CN205740459U (en)

Similar Documents

Publication Publication Date Title
KR100196947B1 (en) Sewage purification apparatus
CN104310663B (en) Combined system for hydroxyl radical (.OH) strong oxidation treatment of high algae-laden water
CN108658192A (en) A kind of hi-effect coagulation device and method
CN103663650A (en) Coagulating sedimentation agent for treating low-temperature low-turbidity water
WO2015077631A1 (en) Enhanced treatment shaft
CN205710206U (en) A kind of integral type sewage processing means
CN104773880A (en) Sewage treatment technology and equipment for well drilling
CN205740459U (en) A kind of packaged type earth's surface water body algal tufa emergency flight control integrated apparatus
CN206985883U (en) Deck runoff pollution processing integrated apparatus
CN103508557B (en) Active sludge bed reaction treatment method and device
CN205740582U (en) A kind of accident sewage disposal emergency lagoon
CN214571213U (en) Emergency water supply device suitable for heavily polluted water source
CN204643928U (en) A kind of sewage plant chemicals dosing plant
CN209940726U (en) Urban tap water supply device convenient to remove and have purification performance
CN208454692U (en) A kind of coal mine sewage disposal system
CN207002356U (en) A kind of electroplating sewerage precipitation process system
CN107244762B (en) Bridge deck runoff pollution treatment integrated device and treatment method
CN202717621U (en) Environment-friendly dredging residual water metering and coagulation treatment device
CN204848513U (en) Sewage purifier
CN203200103U (en) Concentrated industrial sewage reverse osmosis membrane treatment device
CN209630689U (en) A kind of clarifying basin for sewage treatment
CN105254112A (en) Deep wastewater treatment apparatus
CN202988874U (en) Water treatment plant treatment device
CN204874138U (en) Processing apparatus of difficult biochemical organic pollutants surface water
CN107759024A (en) A kind of integrated membrane process hydridization removes the method and device of low concentration selenium-containing wastewater

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161130

Termination date: 20201120

CF01 Termination of patent right due to non-payment of annual fee