Prior art keywords
pond
sludge
sedimentation tank
water
core barrel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720460674.9U
Other languages
Chinese (zh)
Inventor
崔有为
方钰文
冉登宇
相辰橦
张嘉辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Zhonghan Huide Environmental Technology Co., Ltd.
Original Assignee
Beijing University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing University of Technology filed Critical Beijing University of Technology
Priority to CN201720460674.9U priority Critical patent/CN206985883U/en
Application granted granted Critical
Publication of CN206985883U publication Critical patent/CN206985883U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Separation Of Suspended Particles By Flocculating Agents (AREA)
  • Filtration Of Liquid (AREA)

Abstract

Deck runoff pollution processing integrated apparatus, belongs to technical field of sewage.The runoff treatment device combines preliminary sedimentation tank, flocculation basin and second pond, and wherein preliminary sedimentation tank is located at device outermost, and the cylindrical space in preliminary sedimentation tank center is flocculation basin and second pond, and flocculation basin is located above second pond;Overflow launder is provided between preliminary sedimentation tank and second pond, flocculation basin bottom is communicated with the delivery port of flocculation basin and second pond.Filter is located at bottom of device.Device bottommost is waste liquid cylinder and sludge working area.After emergent safe disposal pond is transformed, the device can be interfaced, and emergent safe disposal pond is divided into two ponds of size by reforming mode with a dividing plate, Initial Runoffs of the little Chi for collecting 30min before bridge floor, is handled after collection by runoff treatment device.Great Chi only has the emergent memory function for collecting harmful influence leakage.Overflow launder is provided with the top of dividing plate, after little Chi is filled with, the runoff overflow continued to flow into enters in great Chi and discharged.

Description

Deck runoff pollution processing integrated apparatus
Technical field
Deck runoff pollution processing integrated apparatus and processing method are the utility model is related to, belongs to sewage disposal technology neck Domain.
Background technology
The cross-domain important water body basin of bridge, it is the important pivot of road traffic.It is stagnant as the carrier of communications and transportation, bridge floor Stay polluter caused by a large amount of vehicles.These polluters can enter directly into bridge by sleet runoff and be crossed over In water body, or even farmland is accumulated near bridge.These bridge floor pollution of circulation things can be to bridge water body, especially drinking water Source protection water body, form pollution risk;Farmland nearby can be also polluted, causes accumulation of the pollutant on food chain, the mankind are pacified It is complete to produce risk.Deck runoff pollution seems more serious in ecological sensitive areas, is gradually paid attention in recent years by people.By grinding Study carefully groups of contaminants in deck runoff into the rainwater for finding deck runoff initial stage containing more solid suspension, COD, ammonia nitrogen, The even pollutant such as heavy metal.This pollutant washes away by precipitation runoff to be directly discharged in receiving water body.Marked according to country Accurate regulation, emergent safe disposal pond must be had across the bridge of three-level above water body.Its function is the car to hazmats Hazardous chemical after generation accident is collected storage, prevents from bringing risk of environmental pollution to sensitive water body.But by Simply met an urgent need in emergency disposal pond and collect road surface accident hazard product, it does not have purification function to be rainfall runoff.According to dangerous material Accident statistics, emergency disposal pond frequency of use is low, causes the waste of resource and leaves unused.Therefore, in the bridge across ecological sensitive areas Section establishes effective processing rainfall runoff water treatment facilities, processing work(of the increase safe pool in rainfall runoff based on emergent safe pool It can be necessary.
Early-stage Study shows that deck runoff is a kind of pollution sources of intermittent discharge, and it is influenceed to show by area and weather Write.The discharge of runoff rainwater has intermittence, and runoff water is influenceed by rainfall intensity and rainfall duration.The runoff formed every time Flow is also non-constant.Summer torrential rain forms a large amount of runoff waters in a short time, and runoff caused by the light rain of spring and autumn is very It is small, in some instances it may even be possible to can not form runoff.Root is it was found that the concentration of deck runoff pollutant has obvious changing rule.Rainfall 30 The minute Runoff contaminants concentration of discharge is higher.Pollutant concentration is substantially already below water environment quality standard after 30 minutes Two level water body standard specified in (GB 3838-2002).And Initial Runoff is very high to the contribution rate of pollutant, therefore first 30 points The Initial Runoff of clock turns into the emphasis of processing.By water quality detection, the dirts such as COD, SS, ammonia nitrogen, Pb are mainly contained in deck runoff Contaminate thing.These water quality and production water feature are totally different from municipal wastewater and industrial wastewater, have distinct characteristic.At present, still There is not the technology and method that bridge floor rainfall runoff is handled.
The characteristics of bridge floor rainfall runoff, proposes tightened up requirement for deck runoff processing.First, ecological sensitive areas one As be all located at the field away from city, manual maintenance is inconvenient.Therefore, the automation for the treatment of technology and facility and long-range The ability of monitoring is the key for solving this problem.Secondly, the typically no utilizable power supply of bridge of ecological sensitive areas.Cause This, the power supply of horsepower requirements and equipment to equipment is also an outstanding request.In addition, there are the river and river of large area under bridge Beach, typically no too big vacant lot are used for building for device.Therefore, the processing equipment built using fail- safe pond requires design It is compact, it is easily installed and debugs.
To sum up, existing water technology scheme all cannot be directly used to the processing of deck runoff.Based on expressway across quick Feeling the overall technology for solving runoff pollution of water body research and development and integration apparatus turns into an urgent demand of current road landslide.
Utility model content
It is practical new for deck runoff water quality pollutant feature and emission equivalent at initial stage, and the characteristics of consider bridge zone Type a set of integrated deck runoff treatment technology and device.Treatment technology is using precipitation, coagulation, precipitation and ion exchange work Skill, the processing requirement purification of the runoff of bridge floor rainwater can be realized.Based on the technology, the fail- safe pond set using bridge floor, Utility model is a set of to collect processing deck runoff integration apparatus using safe pool.The technology and integration apparatus apparatus structure Compact, floor space is small.And intelligent control and monitoring system are used, using solar cell for supplying power, realize bridge zone runoff rain The collection and processing of water.
The deck runoff pollution processing integrated apparatus of the utility model, including pollution processing integrated apparatus such as Fig. 1, should Pollution processing integrated apparatus mainly includes water-locator (1), preliminary sedimentation tank (2), flocculation basin (4), second pond (8), filter (9) With solar energy equipment (15);
Pollution processing integrated apparatus entirety outer layer is outer cylinder (42), interior in pressing close to for outer cylinder (42) inner upper point Lateral parts are preliminary sedimentation tank (2), and preliminary sedimentation tank (2) is barreled structure, and preliminary sedimentation tank (2) includes core barrel (18) and core barrel (18) The spiral shape swash plate (17) of lateral surface, core barrel (18) and outer cylinder (42) coaxially, between core barrel (18) and outer cylinder (42) With space, multiple spiral shape swash plate (17) layerings are fixed between the space of core barrel (18) and outer cylinder (42);Spiral shape is oblique Plate has space between (17);Sludge from primary sedimentation tank bucket (11), preliminary sedimentation tank are provided with below outer cylinder (42) inside center bucket (18) The big mouth lateral surface of sludge bucket (11) is fixed with the sealing of outer cylinder (42) inner surface;The bottom of core barrel (18) is second pond sludge Funnel (11 '), big mouth lateral surface and the sealing of core barrel (18) inner surface of second pond sludge funnel (11 ') are fixed;Second pond is dirty Mud funnel (11 ') is above Sludge from primary sedimentation tank bucket (11);Between second pond sludge funnel (11 ') and Sludge from primary sedimentation tank bucket (11) Axially there is space, the water-locator of ring-type is provided between second pond sludge funnel (11 ') and Sludge from primary sedimentation tank bucket (11) space (1);The center of second pond sludge funnel (11 ') and Sludge from primary sedimentation tank bucket (11) is equipped with sewage draining exit respectively by discharge pipeline (12) It is connected with sludge working area (14);The upper port bucket wall of core barrel (18) is provided with V-shaped overflow launder (3);Core barrel (18) it is interior Portion top is flocculation basin (4);Flocculation basin (4) includes drum dividing plate (44), drum dividing plate (44) with core barrel (18) coaxially, drum There is space, the lower end of drum dividing plate (44) is conical bottom of pond (40), bottom of pond (40) between dividing plate (44) and core barrel (18) Seal and fix with the inner surface of core barrel (18), drum dividing plate (44) lower surface is fixed with bottom of pond (40) sealing, drum dividing plate (44) lower end is provided with water inlet (25), and preferably water inlet (25) is arch, there is multiple water inlets (25), such as 4;
Outer cylinder (42) upper end is provided with support (43), and motor and decelerator (24) are provided with support (43), electronic Machine and decelerator (24) are connected with agitating shaft (19), and agitating shaft (19) is extended down into drum dividing plate (44), agitating shaft (19) top is mounted with frame type agitating blade (21), and frame type agitating blade (21) extend into drum dividing plate (44) and core barrel (18) between space;In agitating shaft (19), bottom be mounted with Intermic formulas agitating paddle (20), Intermic formulas are stirred Oar (20) is mixed in drum dividing plate (44), the bottom of agitating shaft (19) is fixed to bottom of pond (40) by three pin bearing blocks (23) On;The center of bottom of pond (40) is provided with delivery port (26);Bottom of pond (40) inside is second pond (8) to bottom of pond (40) below;Second pond (8) Including spiral shape swash plate, central water pipe and water-locator (7), the lower end of central water pipe is water-locator, central water pipe and delivery port (26) connect, multiple spiral shape swash plate spiral stacked distributions are fixed on the surrounding of central water pipe, have sky between spiral shape swash plate Gap;Water-locator is above second pond sludge funnel (11 ');Filter (9) is provided with below Sludge from primary sedimentation tank bucket (11);Two The bucket wall of the central upper portion bucket (18) of heavy pond (8) is connected provided with hole by pipeline (41) with filter (9);Filter (9) it is provided with drainpipe (10) and carries out draining;The top of outer cylinder (42) is provided with solar energy equipment (15), solar energy equipment (15) For providing electrical drive power needed for operating;Chemicals dosing plant (6) is further fixed on support and is used for flocculation basin dosing.
Waste liquid cylinder (13) is provided with below filter (9), for holding the waste liquid of filter (9) backwash;It is dirty Mud working area (14) also is located at below filter (9).
Deck runoff pollution processing integrated apparatus also includes rain-collecting port (28), horizontal water pipe (29), water-main (30), receipts Collect processing system;One rain-collecting port (28), each rain-collecting port and a horizontal water pipe (29) are set every a segment distance on bridge floor Connection, each horizontal water pipe (29) are connected with water-main (30), water-main (30) and collection processing system implementing, the collection processing system implementing Including safe pool, safe pool includes little Chi (32), great Chi (34), and little Chi (32), great Chi are separated between (34) using dividing plate, always Water pipe (30) and triple valve (31) connection, two other mouth of triple valve (31) is connected with little Chi (32), great Chi (34) respectively, small Pond (32) is connected with pollution processing integrated apparatus (36), and the water after processing is discharged into river nearby by outlet pipe (10).Pollution Automatic control device (16) is additionally provided with processing integrated apparatus, control automatically device (16) be used for control valve, chemicals dosing plant (6), The operating of motor and decelerator (24).
Because preceding 30min Runoff contaminants concentration is higher, concentration is substantially below national two level water body standard after 30min, Therefore collection processing system implementing only collects Initial Runoff with before processing 30min, and the runoff after 30min can be without processing directly row Go out.30min deck runoff before collection processing system implementing intercepts by control triple valve (31).
Dividing plate top between little Chi (32), great Chi (34) sets overflow launder (33), and great Chi pool walls top sets spout hole (38);The mounting plane of pollution processing integrated apparatus (36) is lower 1~2m than little Chi (32) pond, for producing certain head, Current in driving pollution processing integrated apparatus (36).
Little Chi valves (35) connect little Chi 32 and pollution processing integrated apparatus (36), and great Chi valves (37) are big for emptying Water in pond (34).
The runoff treatment device combines preliminary sedimentation tank, flocculation basin and second pond, and wherein preliminary sedimentation tank is located at device most Outside, the cylindrical space in preliminary sedimentation tank center is flocculation basin and second pond, and flocculation basin is located above second pond;Preliminary sedimentation tank and two sinks Overflow launder is provided between pond, flocculation basin bottom is communicated with the delivery port of flocculation basin and second pond.Filter is located at bottom of device. Device bottommost is waste liquid cylinder and sludge working area.After emergent safe disposal pond is transformed, the device can be interfaced, changes Make mode and emergent safe disposal pond be divided into two ponds of size with a dividing plate, little Chi be used to collecting 30min before bridge floor just Phase runoff, handled after collection by runoff treatment device.Great Chi only has the emergent memory function for collecting harmful influence leakage.Dividing plate Top is provided with overflow launder, and after little Chi is filled with, the runoff overflow continued to flow into enters in great Chi and discharged.
Brief description of the drawings
Fig. 1 pollution processing integrated apparatus structural representations;
Fig. 2 preliminary sedimentation tank internal structures;
Fig. 3 flocculation basins;
Fig. 4 flocculation basin pond body sectional views;
Fig. 5 runoff treatment device water flow processes;
Fig. 6 device installations diagram;
1 water-locator, 2 preliminary sedimentation tanks, 3V fonts overflow launder, 4 flocculation basins, 5 agitating devices, 6 chemicals dosing plants, 7 central water pipes and Water-locator, 8 second ponds, 9 filters, 10 drainpipes, 11 Sludge from primary sedimentation tank buckets, 11 ' second pond sludge funnels, 12 discharge pipelines, 13 waste liquid cylinders, 14 sludge working areas, 15 solar energy equipments, 16 automatic control devices, 17 spiral shape swash plates, 18 core barrels, 19 stirrings Axle, 20Intermic formulas agitating paddle, 21 frame type agitating blades, 22 shaft couplings, 23 3 pin bearing blocks, 24 motor and decelerator, 25 water inlets, 26 delivery ports, 27 pontics, 28 rain-collecting ports, 29 horizontal water pipes, 30 water-mains, 31 triple valves, 32 little Chi, 33 overflows Groove, 34 great Chi, 35 little Chi valves, 36 pollution processing integrated apparatus, 37 great Chi valves, 38 spout holes, 39 mud valves, 40 ponds Bottom, 41 pipelines, 42 outer cylinders, 43 supports, 44 drum dividing plates.
Embodiment
With reference to embodiment, the utility model is described in further detail, but the utility model is not limited to following implementation Example.
Embodiment 1
The device needs to be docked with safe pool, and needs to transform safe pool, and the device forms with safe pool One whole collection processing system implementing.
Such as Fig. 1, water is entered in preliminary sedimentation tank 2 by water inlet pipe and water-locator 1 carries out preliminary sedimentation, and the particulate matter to precipitate falls Enter to fall into sludge bucket.Wherein, preliminary sedimentation tank 2 is cylindrical shape, and positioned at the outside of whole device, the center of preliminary sedimentation tank 2 reserves a cylinder The space of shape is to flocculation basin 4 and second pond 8;The structure of preliminary sedimentation tank 2 is as shown in Fig. 2 spiral shape swash plate 17 is arranged on core barrel 18 On, spiral shape swash plate 17 increases the area of sedimentation basin, and current can slowly rise along spiral shape swash plate 17, and particulate matter is in spiral shape Gradually precipitated on swash plate 17, spiral glides, and the sedimentation basin space availability ratio so designed is and stable up to 100%, seldom Turbulization, non-water flow dead angle;
Such as Fig. 1, V-shaped overflow launder 3 is arranged at the top of preliminary sedimentation tank 2, and water passes through V-shaped overflow launder 3 when reaching 2 top of preliminary sedimentation tank Overflow is into flocculation basin 4.Agitating device 5 and dosing pump 6 the meeting continuous firing of the top of device, flocculation basin is added to by flocculant In the water of 4 outer layers, flocculation stirring is realized.Wherein, the structure of flocculation basin 4 by cylindrical shape dividing plate as shown in figure 3, be divided into internal layer and outer Layer, ectonexine volumetric ratio should be 2:1,4 arch water inlets 25 are arranged at dividing plate bottom, and the water and floccule body of outer layer are by this 4 water inlets Mouth 25 enters internal layer;The agitating device of flocculation basin includes the frame type stirring of Intermic formulas agitating paddle 20, one of agitating shaft 19, two Oar 21, shaft coupling 22, three pin bearing blocks 23, motor and decelerator 24 form, and frame type agitating blade 21 is used for stirring flocculation basin The water of outer layer, two Intermic formulas agitating paddles 20 are used for stirring the water of flocculation basin internal layer, and because intermic formulas stir Oar 20 can make current form axial circulation, can fully be contacted between floccule body, promote growing up for floccule body;Inside and outside agitating paddle It is coaxial, linear differential is formed, reaches outer layer stirring intensity height, the low effect of internal layer stirring intensity, flocculating effect is good;Agitating device Only driven using a motor, and do not need gear train, it is convenient to control and safeguard;The profile of flocculation basin pond body such as Fig. 5 Shown, bottom of pond is cone, and for section with the horizontal 10 °~15 ° of the gradient, the water and floccule body for being easy to outer layer flow into internal layer, The vertex of a cone is provided with delivery port 26, and the water and floccule body after flocculation treatment flow out from delivery port 26.
Such as Fig. 1, after flocculation, water and floccule body are flowed out by the delivery port of flocculation basin bottom together, by central water pipe and cloth Hydrophone 7 enters the bottom of second pond 8, and water slowly rises in second pond 8 along swash plate, and the floccule body of bulky grain is gradually deposited in swash plate On, finally slip into sludge bucket;Wherein, central water pipe upper end connects with the delivery port of flocculation basin, and a water-locator is installed in lower end;Two is heavy There is a delivery port upper end in pond 8, is connected with outer water tube.
Water after second pond 8 precipitates enters filter 9 by outer water tube, and filter 9 is provided with two Filter columns, interior Quartz sand filter media is filled, two conventional one of Filter columns one are standby, ensure that filter 9 will not interrupt work because of filter clogging Make, after the processing of filter 9, water is discharged by drainpipe 10;Filter 9 is furnished with supporting backwashing equipment, when wherein Need to be backwashed after a piece Filter column is fully loaded, open backwashing pump, backwashed with clear water, backwash the waste water of production Waste liquid cylinder 13 is drained into, Filter column can is continuing with after completing backwash.
The bottom of preliminary sedimentation tank and second pond is provided with sludge bucket, and two conical sludge buckets are placed with one heart, but has up and down enough Interval, the small sludge bucket in top is used for collecting second pond 8 and avales the floccule body come, and it is just heavy that the big sludge bucket in bottom is used for collecting The bulky grain sludge that can voluntarily settle in pond 2, discharge pipeline 12 have two, discharge the sludge of two sludge buckets respectively, pass through spoil disposal The regular spoil disposal of valve, the sludge of discharge go out to exist the sludge working area 14 of bottom of device.
The energy of device is provided by solar cell 15 of the frame at the top of device, and the control of device is complete by self-con-tained unit 16 Into.
After whole handling process, device effluent quality can reach national two level water body standard.
The water flow process of device is as illustrated by arrows 5.
Such as Fig. 1, device top is provided with a ring support, chemicals dosing plant 6, including medicine liquid tank and dosing is provided with support Pump;Chemicals dosing plant 6 is located at the top of flocculation basin 4, and a nephelometer is installed on the horizontal plane on the top of preliminary sedimentation tank 2, measures just heavy rear water Turbidity, i.e. flocculation basin influent turbidity, and flow meters, monitoring device flow of inlet water are installed at water inlet pipe 1.Dosing method is adopted With wet throwing method, it is pre-configured with 15% PAC solution and 2% PAM solution is placed in medicine storing pot.The control of chemicals dosing plant is also by certainly Device to be controlled to complete, the flow of dosing pump is related to turbidity, after optimum experimental, flocculation basin influent turbidity and flocculant dosage Relation, obtain dosing pump discharge after fitting and calculating and the relation of turbidity and flow of inlet water is
QPAC=Q (273.89T+3.23) × 10-4[mL/min]
QPAM=Q (2.42T+192.08) × 10-6[mL/min]
Wherein, QPACFor the flow of PAC solution, QPAMFor the flow of PAM solution, Unit/mL/min;Q is device feed water flow Amount, unit L/h;T is flocculation basin influent turbidity, unit NTU.
The installation diagram of device sets a rain-collecting port 28, stream as shown in fig. 6,27 be pontic on bridge floor every a segment distance The water for entering rain-collecting port enters horizontal water pipe 29, then enters collection processing system implementing through water-main 30, the collection processing system implementing mainly by Little Chi 32, great Chi 34 and deck runoff processing unit 36 form, and the water after processing is discharged into river nearby by outlet pipe 10;
Because preceding 30min Runoff contaminants concentration is higher, concentration is substantially below national two level water body standard after 30min, Therefore collection processing system implementing only collects Initial Runoff with before processing 30min, and the runoff after 30min can be without processing directly row Go out.30min deck runoff before collection processing system implementing intercepts by control triple valve 31, by safe pool and runoff treatment device 36 form, and have a dividing plate in safe pool, safe pool are divided into little Chi 32 and great Chi 34, little Chi 32 is used for collecting 30min before bridge floor Initial Runoff, great Chi 34 is safe pool draws away remaining part behind a part of space by little Chi 32, usually without collecting footpath The effect of stream, only serve as emergent safe disposal pond when harmful influence transport vehicle accident occurs.
Dividing plate top sets overflow launder 33, and great Chi pool walls top sets spout hole 38;Pollution processing integrated apparatus 36 Mounting plane is than the safe 1~2m of bottom of pond of little Chi 32, and for producing certain head, driving pollution is handled in integrated apparatus 36 Current;
The course of work of the system is:During generation rainfall, runoff flows into rain-collecting port 28, then through horizontal water pipe 29 and water-main 30 enter collection processing system implementing;Preceding 30min, triple valve 31 all access the water of water-main 30 in little Chi 32;After 30min, three Port valve 31 all accesses the water of water-main 30 in great Chi 34, then is discharged from great Chi valves 37, is discharged into river nearby;If water Excessive to have little time to discharge, then unnecessary water flows out from spout hole 38, prevents that water level is too high.After rainfall terminates, little Chi valves 35 are beaten Open, the medium pending water of little Chi 32 enters pollution processing integrated apparatus 36, and water after treatment handles one from pollution The outlet pipe 10 that makeup puts 36 is discharged, and is discharged into river nearby.Little Chi 32 and great Chi 34 bottom of pond may have sludge, it is therefore desirable to set Put a sludge-tank, and regular spoil disposal, open mud valve 39 during spoil disposal, sludge is discharged into sludge-tank.
The system is designed based on safe pool, still remains with the function of safe pool.The system needs to design long-range report Alert system, once dangerous chemical leakage caused by traffic accident occurs, then triggering alarm, closes all valves automatically, including Great Chi valves 37, little Chi valves 35 and mud valve 39, it could continue to open until danger excludes late gate.
Take the bridge floor deposit of certain bridge to carry out water distribution, and build a set of small testing device to simulate actual runoff treatment dress The technological process put;Experiment finds, it is just heavy can remove 66% COD, but still some COD is attached on colloid not It can be removed with just heavy;Again by flocculation after just heavy, 89% is reached to COD clearance;It is finally dense by filtering, the COD of water outlet Degree has been less than the first grade discharging mark of town B-grade sewage treatment plant specified in integrated wastewater discharge standard (GB 8978-1996) Standard, to COD clearance up to 92%.

Claims (6)

1. deck runoff pollution processing integrated apparatus, it is characterised in that handle integrated apparatus, pollution processing including pollution Integrated apparatus mainly includes water-locator (1), preliminary sedimentation tank (2), flocculation basin (4), second pond (8), filter (9) and solar energy Device (15);
Pollution processing integrated apparatus entirety outer layer is outer cylinder (42), presses close to medial surface in outer cylinder (42) inner upper point Part is preliminary sedimentation tank (2), and preliminary sedimentation tank (2) is barrel-like structure, and preliminary sedimentation tank (2) includes core barrel (18) and core barrel (18) lateral surface Spiral shape swash plate (17), core barrel (18) and outer cylinder (42) coaxially, between core barrel (18) and outer cylinder (42) have empty Gap, multiple first spiral shape swash plate (17) layerings are fixed between the space of core barrel (18) and outer cylinder (42);Spiral shape swash plate (17) there is space between;Sludge from primary sedimentation tank bucket (11) is provided with below outer cylinder (42) inside center bucket (18), preliminary sedimentation tank is dirty The big mouth lateral surface of bucket (11) is fixed with the sealing of outer cylinder (42) inner surface;Leaked for second pond sludge the bottom of core barrel (18) Struggle against (11 '), big mouth lateral surface and the sealing of core barrel (18) inner surface of second pond sludge funnel (11 ') are fixed;Second pond sludge Funnel (11 ') is above Sludge from primary sedimentation tank bucket (11);The countershaft of second pond sludge funnel (11 ') and Sludge from primary sedimentation tank bucket (11) To with space, the water-locator of ring-type is provided between second pond sludge funnel (11 ') and Sludge from primary sedimentation tank bucket (11) space (1);The center of second pond sludge funnel (11 ') and Sludge from primary sedimentation tank bucket (11) is equipped with sewage draining exit respectively by discharge pipeline (12) It is connected with sludge working area (14);The upper port bucket wall of core barrel (18) is provided with V-shaped overflow launder (3);Core barrel (18) it is interior Portion top is flocculation basin (4);Flocculation basin (4) includes drum dividing plate (44), drum dividing plate (44) with core barrel (18) coaxially, drum There is space, the lower end of drum dividing plate (44) is conical bottom of pond (40), bottom of pond (40) between dividing plate (44) and core barrel (18) Seal and fix with the inner surface of core barrel (18), drum dividing plate (44) lower surface is fixed with bottom of pond (40) sealing, drum dividing plate (44) lower end is provided with water inlet (25);
Outer cylinder (42) upper end is provided with support (43), is provided with motor and decelerator (24) on support (43), motor with And decelerator (24) is connected with agitating shaft (19), agitating shaft (19) is extended down into drum dividing plate (44), agitating shaft (19) Top is mounted with frame type agitating blade (21), and frame type agitating blade (21) extend into the sky of drum dividing plate (44) and core barrel (18) Between gap;In agitating shaft (19), bottom be mounted with Intermic formulas agitating paddle (20), Intermic formulas agitating paddle (20) exists In drum dividing plate (44), the bottom of agitating shaft (19) is fixed in bottom of pond (40) by three pin bearing blocks (23);Bottom of pond (40) Center be provided with delivery port (26);Bottom of pond (40) inside is second pond (8) to bottom of pond (40) below;Second pond (8) includes spiral shape Swash plate, central water pipe and water-locator (7), the lower end of central water pipe is water-locator, and central water pipe is connected with delivery port (26), multiple Spiral shape swash plate spiral stacked distribution is fixed on the surrounding of central water pipe, has space between spiral shape swash plate;Water-locator is two Above heavy pond sludge funnel (11 ');Filter (9) is provided with below Sludge from primary sedimentation tank bucket (11);The top of second pond (8) The bucket wall of core barrel (18) is connected provided with hole by pipeline (41) with filter (9);Filter (9) is provided with drainpipe (10) draining is carried out;The top of outer cylinder (42) is provided with solar energy equipment (15), and solar energy equipment (15) is used to provide operating Required electrical drive power;Chemicals dosing plant (6) is further fixed on support and is used for flocculation basin dosing;
Deck runoff pollution processing integrated apparatus also include rain-collecting port (28), horizontal water pipe (29), water-main (30), at collection Reason system;One rain-collecting port (28) is set every a segment distance on bridge floor, each rain-collecting port is connected with a horizontal water pipe (29), Each horizontal water pipe (29) is connected with water-main (30), and water-main (30) and collection processing system implementing, the collection processing system implementing include Safe pool, safe pool include little Chi (32), great Chi (34), and little Chi (32), great Chi are separated between (34) using dividing plate, water-main (30) it is connected respectively with little Chi (32), great Chi (34) with triple valve (31) connection, two other mouth of triple valve (31), great Chi (34) water in passes through little Chi valves by great Chi valves (37) row such as river, little Chi (32) with pollution processing integrated apparatus (36) Door (35) connection, the water after processing are discharged into river nearby by outlet pipe (10).
2. according to the deck runoff pollution processing integrated apparatus described in claim 1, it is characterised in that in filter (9) Below be provided with waste liquid cylinder (13), for hold filter (9) backwash waste liquid;Sludge working area (14) also is located at filtering Below device (9).
3. according to the deck runoff pollution processing integrated apparatus described in claim 1, it is characterised in that water inlet (25) is arch Shape, there are multiple water inlets (25).
4. according to the deck runoff pollution processing integrated apparatus described in claim 1, it is characterised in that pollution processing integration Automatic control device (16) is additionally provided with device, control automatically device (16) be used for control valve, chemicals dosing plant (6), motor and The operating of decelerator (24).
5. according to the deck runoff pollution processing integrated apparatus described in claim 1, it is characterised in that little Chi (32), great Chi (34) the dividing plate top between sets overflow launder (33), and great Chi pool walls top sets spout hole (38);Pollution processing one makeup It is lower 1~2m than little Chi (32) pond to put the mounting plane of (36), for producing certain head, driving pollution processing integrated apparatus (36) current in.
6. pollution processing integrated apparatus, it is characterised in that the pollution processing integrated apparatus mainly include water-locator (1), just Heavy pond (2), flocculation basin (4), second pond (8), filter (9) and solar energy equipment (15);
Pollution processing integrated apparatus entirety outer layer is outer cylinder (42), presses close to medial surface in outer cylinder (42) inner upper point Part is preliminary sedimentation tank (2), and preliminary sedimentation tank (2) is barreled structure, and preliminary sedimentation tank (2) includes core barrel (18) and core barrel (18) lateral surface Spiral shape swash plate (17), core barrel (18) and outer cylinder (42) coaxially, between core barrel (18) and outer cylinder (42) have empty Gap, multiple spiral shape swash plate (17) layerings are fixed between the space of core barrel (18) and outer cylinder (42);Spiral shape swash plate (17) Between have space;Sludge from primary sedimentation tank bucket (11), Sludge from primary sedimentation tank bucket are provided with below outer cylinder (42) inside center bucket (18) (11) big mouth lateral surface is fixed with the sealing of outer cylinder (42) inner surface;The bottom of core barrel (18) is second pond sludge funnel (11 '), big mouth lateral surface and the sealing of core barrel (18) inner surface of second pond sludge funnel (11 ') are fixed;Second pond sludge leaks (11 ') are struggled against above Sludge from primary sedimentation tank bucket (11);Between second pond sludge funnel (11 ') and Sludge from primary sedimentation tank bucket (11) axially With space, the water-locator (1) provided with ring-type between second pond sludge funnel (11 ') and Sludge from primary sedimentation tank bucket (11) space; The center of second pond sludge funnel (11 ') and Sludge from primary sedimentation tank bucket (11) is equipped with sewage draining exit respectively by discharge pipeline (12) and dirt Mud working area (14) connects;The upper port bucket wall of core barrel (18) is provided with V-shaped overflow launder (3);On the inside of core barrel (18) Portion is flocculation basin (4);Flocculation basin (4) includes drum dividing plate (44), drum dividing plate (44) with core barrel (18) coaxially, drum dividing plate (44) there is space between core barrel (18), the lower end of drum dividing plate (44) is conical bottom of pond (40), and bottom of pond (40) is with The inner surface sealing of heart bucket (18) is fixed, and drum dividing plate (44) lower surface is fixed with bottom of pond (40) sealing, under drum dividing plate (44) End is provided with water inlet (25);
Outer cylinder (42) upper end is provided with support (43), is provided with motor and decelerator (24) on support (43), motor with And decelerator (24) is connected with agitating shaft (19), agitating shaft (19) is extended down into drum dividing plate (44), agitating shaft (19) Top is mounted with frame type agitating blade (21), and frame type agitating blade (21) extend into the sky of drum dividing plate (44) and core barrel (18) Between gap;In agitating shaft (19), bottom be mounted with Intermic formulas agitating paddle (20), Intermic formulas agitating paddle (20) exists In drum dividing plate (44), the bottom of agitating shaft (19) is fixed in bottom of pond (40) by three pin bearing blocks (23);Bottom of pond (40) Center be provided with delivery port (26);Bottom of pond (40) inside is second pond (8) to bottom of pond (40) below;Second pond (8) includes spiral shape Swash plate, central water pipe and water-locator (7), the lower end of central water pipe is water-locator, and central water pipe is connected with delivery port (26), multiple Spiral shape swash plate spiral stacked distribution is fixed on the surrounding of central water pipe, has space between spiral shape swash plate;Water-locator is two Above heavy pond sludge funnel (11 ');Filter (9) is provided with below Sludge from primary sedimentation tank bucket (11);The top of second pond (8) The bucket wall of core barrel (18) is connected provided with hole by pipeline (41) with filter (9);Filter (9) is provided with drainpipe (10) draining is carried out;The top of outer cylinder (42) is provided with solar energy equipment (15), and solar energy equipment (15) is used to provide operating Required electrical drive power;Chemicals dosing plant (6) is further fixed on support and is used for flocculation basin dosing.
CN201720460674.9U 2017-04-28 2017-04-28 Deck runoff pollution processing integrated apparatus Active CN206985883U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720460674.9U CN206985883U (en) 2017-04-28 2017-04-28 Deck runoff pollution processing integrated apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720460674.9U CN206985883U (en) 2017-04-28 2017-04-28 Deck runoff pollution processing integrated apparatus

Publications (1)

Publication Number Publication Date
CN206985883U true CN206985883U (en) 2018-02-09

Family

ID=61391717

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720460674.9U Active CN206985883U (en) 2017-04-28 2017-04-28 Deck runoff pollution processing integrated apparatus

Country Status (1)

Country Link
CN (1) CN206985883U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107244762A (en) * 2017-04-28 2017-10-13 北京工业大学 Deck runoff pollution processing integrated apparatus and processing method
CN109095479A (en) * 2018-10-24 2018-12-28 中盐金坛盐化有限责任公司 A kind of reactor tank for the production of vacuum salt production factory bittern purifying process continous way

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107244762A (en) * 2017-04-28 2017-10-13 北京工业大学 Deck runoff pollution processing integrated apparatus and processing method
CN107244762B (en) * 2017-04-28 2023-08-15 北京工业大学 Bridge deck runoff pollution treatment integrated device and treatment method
CN109095479A (en) * 2018-10-24 2018-12-28 中盐金坛盐化有限责任公司 A kind of reactor tank for the production of vacuum salt production factory bittern purifying process continous way

Similar Documents

Publication Publication Date Title
US4536286A (en) Mobile waste water and sludge treatment for hazardous and non-hazardous fluids
CN101387119B (en) Rainwater gathering, processing and re-using system for large-sized workshop roof and method thereof
CN201132782Y (en) Purification device for oil-contaminated water and purification system with the device
CN103922506B (en) Integrated complete equipment for water quality purification treatment
CN202625977U (en) Purification and recycling device for mine and sewage
CN106517658A (en) Industrial waste water purification and cleaning equipment
CN201890788U (en) Double-layered pressure type oil remover
CN113371904A (en) Biological slow-filtration purification system and purification method for rural domestic sewage
CN102616999A (en) Sewage purifying and recycling device
CN206985883U (en) Deck runoff pollution processing integrated apparatus
CN108658306A (en) Integrated sewage treating apparatus
CN216273274U (en) Integrated high-turbidity purification device
CN205061779U (en) Novel deposit depositing reservoir
CN107973456A (en) A kind of small-sized domestic sewage treater and its processing method
CN106630249A (en) Automatic tunnel wastewater treatment system
CN107244762A (en) Deck runoff pollution processing integrated apparatus and processing method
CN207091228U (en) Food wastewater processing equipment
CN206337062U (en) Integrated electric flocculation full automatic water purifier
CN108557966A (en) The processing method of coal yard coal-contained wastewater
CN205699622U (en) Vertical sedimentation basin
CN108751611A (en) Efficient printing and dyeing wastewater treatment system and its processing method
CN203890153U (en) Complete set of water quality purification treatment all-in-one equipment
CN204661465U (en) The pre-processing device of high density cutting fluid sewage
CN201864637U (en) Waste water treatment and recycle system applicable to industrial zone
CN206337056U (en) A kind of equipment cart that oil-polluted water is handled using dynamic film device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190801

Address after: 101300 No. 51 Shunren Road, Linhe Industrial Development Zone, Shunyi District, Beijing

Patentee after: Beijing Zhonghan Huide Environmental Technology Co., Ltd.

Address before: 100124 Chaoyang District, Beijing Ping Park, No. 100

Patentee before: Beijing University of Technology