CN205721201U - Fail safe system for transformer substation - Google Patents
Fail safe system for transformer substation Download PDFInfo
- Publication number
- CN205721201U CN205721201U CN201620315220.8U CN201620315220U CN205721201U CN 205721201 U CN205721201 U CN 205721201U CN 201620315220 U CN201620315220 U CN 201620315220U CN 205721201 U CN205721201 U CN 205721201U
- Authority
- CN
- China
- Prior art keywords
- communication network
- online
- lockset
- main frame
- communication
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000004891 communication Methods 0.000 claims abstract description 85
- 230000011664 signaling Effects 0.000 claims abstract description 8
- 238000013480 data collection Methods 0.000 claims description 3
- 230000007246 mechanism Effects 0.000 claims description 3
- 238000000034 method Methods 0.000 description 6
- 230000008569 process Effects 0.000 description 5
- 238000006243 chemical reaction Methods 0.000 description 4
- 230000008901 benefit Effects 0.000 description 2
- 238000012790 confirmation Methods 0.000 description 2
- 238000010276 construction Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000012423 maintenance Methods 0.000 description 2
- 238000012544 monitoring process Methods 0.000 description 2
- 238000004088 simulation Methods 0.000 description 2
- 230000005540 biological transmission Effects 0.000 description 1
- 239000004020 conductor Substances 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000012546 transfer Methods 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
- 238000012795 verification Methods 0.000 description 1
Landscapes
- Selective Calling Equipment (AREA)
Abstract
The utility model discloses a kind of fail safe system for transformer substation, including anti-error main frame, communication adapter, off-line lockset, the first communication network, the second communication network, gateway coordinator, online computer key, some controllers and online lockset;Described first communication network and the second communication network are got in touch with by gateway coordinator;Anti-error main frame realizes the remote operation to online lockset by communication adapter, the first communication network, gateway coordinator, the second communication network, controller;Online lockset gathers the status information of primary equipment, is uploaded to anti-error main frame in real time;Operation order is handed down to online computer key by the first communication network by anti-error main frame, and by online computer key, off-line lockset is unlocked operation;The real remote signalling of off-line lockset is uploaded to anti-error main frame by online computer key, the first communication network and communication adapter.This utility model overcomes " off-line operation " and the problem of " walking idle running " that in prior art, five-preventing system exists.
Description
Technical field
This utility model relates to a kind of fail safe system for transformer substation, belongs to power safety technique field.
Background technology
Owing to power transformation station equipment is various, voltage is higher, electric fault-operation accident occurs again and again and it is very harmful, is likely to result in power equipment damage, large-area power-cuts, even human casualty accident.Department of State Grid clearly proposes to cause the high voltage electric equipment of maloperation to must be equipped with error-proof device, and this error-proof device should possess five kinds of anti-error functions: prevent deciliter chopper by mistake;Prevent on-load from dividing, close disconnecting switch;Prevent band cable address (conjunction) earth lead (grounding switch);Prevent line with ground (grounding switch) from closing chopper (disconnecting switch);Prevent from being strayed into band point interval, i.e. " five prevent ".
Along with improving constantly of Substation Automation System, five-preventing system is widely used in transformer station, and five-preventing system can be prevented effectively from the electric power accident that transformer station is caused in operation, maintenance, maintenance process due to artificial maloperation.Five-preventing system the most frequently used in prior art is mainly to be made up of anti-error main frame, communication adapter, computer key, off-line lockset etc., operator generate operation order after the operation that will carry out being simulated preview on anti-error main frame, by communication adapter, operation order being downloaded to computer key, operator hold computer key and unlock off-line lockset to the on-the-spot content according to operation order.This system common problem is " off-line operation " and " walking idle running ", and anti-error main frame cannot obtain lockset and equipment state in real time, and system exists potential safety hazard.
Summary of the invention
This utility model purpose is to provide a kind of fail safe system for transformer substation, and this system can be effectively prevented from prior art five-preventing system " off-line operation " and the problem of " walking idle running ".
For achieving the above object, this utility model one fail safe system for transformer substation, including anti-error main frame, communication adapter, off-line lockset, the first communication network, the second communication network, gateway coordinator, online computer key, some controllers and online lockset;Described first communication network is used for telecommunication, and the second communication network is used for field data collection, and the first communication network and the second communication network are got in touch with by gateway coordinator;Anti-error main frame realizes the remote operation to online lockset by communication adapter, the first communication network, gateway coordinator, the second communication network, controller;Online lockset gathers the status information of primary equipment, is uploaded to anti-error main frame in real time by controller, the second communication network, gateway coordinator, the first communication network, communication adapter;Grid switching operation bill is handed down to online computer key by the first communication network by anti-error main frame, and by online computer key, off-line lockset is unlocked operation;The real remote signalling of off-line lockset is uploaded to anti-error main frame by online computer key, the first communication network and communication adapter.
Anti-error main frame of the present utility model can obtain the real time status information of online lockset and the real remote signalling of off-line lockset, the often step solution latching operation of computer key is both needed to issue operational order after anti-error main frame carries out Real-time Logic judgement, efficiently avoid temperature survey by c omputer " off-line operation " and the problem of " walking idle running ".
Accompanying drawing explanation
Fig. 1 is the five-preventing system structural representation based on wireless network of this utility model embodiment;
Fig. 2 is this utility model gateway coordinator structural representation;
Fig. 3 is this utility model controller architecture schematic diagram.
Detailed description of the invention
The utility model is described in further detail below in conjunction with the accompanying drawings.
As it is shown in figure 1, a kind of fail safe system for transformer substation, including anti-error main frame, communication adapter and off-line lockset, it is characterised in that: also include the first communication network, the second communication network, gateway coordinator, online computer key, some controllers and online lockset;Described first communication network is used for telecommunication, and the second communication network is used for field data collection, and the first communication network and the second communication network are got in touch with by gateway coordinator;Anti-error main frame realizes the remote operation to online lockset by communication adapter, the first communication network, gateway coordinator, the second communication network, controller;Online lockset gathers the status information of primary equipment, is uploaded to anti-error main frame in real time by controller, the second communication network, gateway coordinator, the first communication network, communication adapter;Grid switching operation bill is handed down to online computer key by the first communication network by anti-error main frame, and by online computer key, off-line lockset is unlocked operation;The real remote signalling of off-line lockset is uploaded to anti-error main frame by online computer key, the first communication network and communication adapter.
Anti-error main frame is equipped with the industrial computer of error resistant operation ticket software, possesses anti-false judgment function during simulation preview, prevents all kinds of maloperation from occurring during generating operation order;Possess Real-time Logic arbitration functions, according to lockset status information, current every single stepping can be carried out Real-time Logic judgement;Anti-error main frame, by serial ports and communications adapter communication, the integrated GPRS module of communications adapter, can carry out radio communication by GPRS network with gateway coordinator and online computer key, obtain online lockset state and off-line lockset reality remote signalling in real time.
Described online lockset includes remote controlled locking relay and intelligent lock, and remote controlled locking relay is for the online locking to the electrical equipment remote manipulation such as chopper and electric knife gate;Intelligent lock is for equipment states such as online locking mechanical operating mechanism, Real-time Collection ground wire, net doors.Online lockset remote operation place in transformer station, main frame as anti-error in primary cut-out, high-voltage switch etc. is remotely controlled the equipment of locking.When online lockset is operated, operator send the romote controlled locking order through logical judgment by anti-error main frame, first pass through the first communication network and operational order is issued to gateway coordinator, gateway coordinator carries out data and processes and by the second communication network, operational order be issued to controller after protocol conversion, controls the locking of online lockset.On the other hand, controller Real-time Collection online lockset state, sent to gateway coordinator by the second communication network, gateway coordinator carries out data and processes and by the first communication network, lockset information be uploaded to anti-error main frame after protocol conversion, it is achieved thereby that anti-error main frame is to on-the-spot lockset and the real-time monitoring of equipment state, the problem efficiently solving five-preventing system in prior art " off-line operation ".When wireless network breaks down, the on-line/off-line handle on intelligent controller is placed in regard to position by operator, operates online lockset by online computer key.
Off-line lockset is the place of local operation in transformer station, such as contact net electrical verification, hanging earthing conductor, local operation case locking box etc..When off-line lockset is unlocked operation, first operator are simulated preview to the operation that will carry out on anti-error main frame, operation order is generated after simulation preview is errorless, operation order is downloaded to online computer key by the first communication network or communications adapter by anti-error main frame, online computer key carries out local operation to off-line lockset after receiving operation order, often operate a step and all the real remote signalling of off-line lockset is uploaded to anti-error main frame by GPRS network, it is achieved the real-time monitoring to off-line lockset of the anti-error main frame.Anti-error main frame according to each lockset state carry out Real-time Logic accuracy of judgement errorless after, confirmation is sent to online computer key by the first communication network, online computer key just can carry out next step operation, thus can be prevented effectively from online computer key problem of " walking idle running ".
Described first communication network is GPRS network;Described second communication network is ZigBee-network.System without wiring, simple in construction, be prone to construction, given full play to the fast advantage of GPRS network long transmission distance, transfer rate and ZigBee technology automatic network-building, time delay is short, capacity is big advantage.
As shown in Figure 2, gateway coordinator has microprocessor module, GPRS communication module and ZigBee communication module, wherein microprocessor module uses Samsung's S3C2440A chip, GPRS communication module selects the MC55 chip of Siemens Company, and ZigBee communication module selects the CC2430 chip of TI company.Gateway coordinator receives, by GPRS network, the operational order that anti-error main frame issues, and carries out data through microprocessor module and processes and after communication Protocol Conversion, be issued to terminal node by ZigBee-network through router;The data that gateway coordinator can also be forwarded by ZigBee-network receiving router, through the data of microprocessor module process with communication Protocol Conversion after, by GPRS network, data are uploaded to anti-error main frame.
As it is shown on figure 3, controller controls Guan Bi and the disconnection of on-the-spot online lockset by photoisolator, the online lockset of Real-time Collection and equipment state also report to tag contact.Online lockset includes remote controlled locking relay and intelligent lock, remote controlled locking relay is for the online locking to the electrical equipment remote manipulation such as chopper and electric knife gate, intelligent lock is used for online locking mechanical operating mechanism, and can collecting device state, the state efficiently solving the equipment such as ground wire, net door cannot the problem of Real-time Collection.Intelligent controller also has on-line/off-line handle, when wireless network breaks down, handle is placed in off-line position, can be unlocked online lockset by online computer key.
Online computer key is internally integrated GPRS communication module, for off-line lockset carrying out local operation and obtaining off-line lockset state, by GPRS network, off-line lockset reality remote signalling is uploaded to anti-error main frame.Online computer key often operates a step, by GPRS network, off-line lockset state and operation information must be uploaded to anti-error main frame, so that anti-error main frame carries out Real-time Logic judgement, online computer key just can carry out next step operation after receiving the confirmation that anti-error main frame issues.Online computer key makes to be finished and is positioned over communications adapter afterwards and is charged.
Claims (5)
1. a fail safe system for transformer substation, including anti-error main frame, communication adapter and off-line lockset, it is characterised in that: also include the first communication network, the second communication network, gateway coordinator, online computer key, some controllers and online lockset;Described first communication network is used for telecommunication, and the second communication network is used for field data collection, and the first communication network and the second communication network are got in touch with by gateway coordinator;Anti-error main frame realizes the remote operation to online lockset by communication adapter, the first communication network, gateway coordinator, the second communication network, controller;Online lockset gathers the status information of primary equipment, is uploaded to anti-error main frame in real time by controller, the second communication network, gateway coordinator, the first communication network, communication adapter;Grid switching operation bill is handed down to online computer key by the first communication network by anti-error main frame, and by online computer key, off-line lockset is unlocked operation;The real remote signalling of off-line lockset is uploaded to anti-error main frame by online computer key, the first communication network and communication adapter.
Fail safe system for transformer substation the most according to claim 1, it is characterised in that: described first communication network is GPRS network;Described second communication network is ZigBee-network.
Fail safe system for transformer substation the most according to claim 1 and 2, it is characterised in that: described controller includes on-line/off-line handle.
Fail safe system for transformer substation the most according to claim 3, it is characterised in that: described online computer key is internally integrated GPRS communication module.
Fail safe system for transformer substation the most according to claim 4, it is characterised in that: described online lockset includes remote controlled locking relay and intelligent lock, and remote controlled locking relay is for chopper and the online locking of electric knife gate remote manipulation;Intelligent lock is used for online locking mechanical operating mechanism, Real-time Collection equipment working state.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620315220.8U CN205721201U (en) | 2016-04-15 | 2016-04-15 | Fail safe system for transformer substation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620315220.8U CN205721201U (en) | 2016-04-15 | 2016-04-15 | Fail safe system for transformer substation |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205721201U true CN205721201U (en) | 2016-11-23 |
Family
ID=57307676
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620315220.8U Expired - Fee Related CN205721201U (en) | 2016-04-15 | 2016-04-15 | Fail safe system for transformer substation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205721201U (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107369346A (en) * | 2017-07-20 | 2017-11-21 | 国网山东省电力公司潍坊供电公司 | The special training set of power system five-prevention operation |
CN107368004A (en) * | 2017-09-04 | 2017-11-21 | 安徽科盟电子科技有限公司 | A kind of power system Anti-false action device based on GPRS wireless telecommunications |
CN108599380A (en) * | 2018-06-07 | 2018-09-28 | 国网山东省电力公司聊城供电公司 | A kind of Substation Operating anti-error system and method |
CN109634173A (en) * | 2018-12-12 | 2019-04-16 | 广东电网有限责任公司 | A kind of spare anti-misoperation locking operating method |
CN109658567A (en) * | 2018-12-14 | 2019-04-19 | 武汉泰可电气股份有限公司 | A kind of intelligent online five-preventing system based on low-power consumption technology of Internet of things |
CN111917179A (en) * | 2020-07-02 | 2020-11-10 | 江苏胜太电力系统有限公司 | Real-time online anti-misoperation system of transformer substation based on multimode internet of things |
CN112700995A (en) * | 2020-12-18 | 2021-04-23 | 广东电网有限责任公司 | Power distribution room maintenance method and device |
CN115273275A (en) * | 2021-04-29 | 2022-11-01 | 珠海优特电力科技股份有限公司 | Lock control method, device and system |
-
2016
- 2016-04-15 CN CN201620315220.8U patent/CN205721201U/en not_active Expired - Fee Related
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107369346A (en) * | 2017-07-20 | 2017-11-21 | 国网山东省电力公司潍坊供电公司 | The special training set of power system five-prevention operation |
CN107369346B (en) * | 2017-07-20 | 2021-09-07 | 国网山东省电力公司潍坊供电公司 | Training device special for five-prevention operation of electric power system |
CN107368004A (en) * | 2017-09-04 | 2017-11-21 | 安徽科盟电子科技有限公司 | A kind of power system Anti-false action device based on GPRS wireless telecommunications |
CN108599380A (en) * | 2018-06-07 | 2018-09-28 | 国网山东省电力公司聊城供电公司 | A kind of Substation Operating anti-error system and method |
CN109634173A (en) * | 2018-12-12 | 2019-04-16 | 广东电网有限责任公司 | A kind of spare anti-misoperation locking operating method |
CN109658567A (en) * | 2018-12-14 | 2019-04-19 | 武汉泰可电气股份有限公司 | A kind of intelligent online five-preventing system based on low-power consumption technology of Internet of things |
CN111917179A (en) * | 2020-07-02 | 2020-11-10 | 江苏胜太电力系统有限公司 | Real-time online anti-misoperation system of transformer substation based on multimode internet of things |
CN111917179B (en) * | 2020-07-02 | 2024-04-30 | 江苏胜太电力系统有限公司 | Real-time online misoperation prevention system of transformer substation based on multimode internet of things |
CN112700995A (en) * | 2020-12-18 | 2021-04-23 | 广东电网有限责任公司 | Power distribution room maintenance method and device |
CN112700995B (en) * | 2020-12-18 | 2023-03-28 | 广东电网有限责任公司 | Power distribution room maintenance method and device |
CN115273275A (en) * | 2021-04-29 | 2022-11-01 | 珠海优特电力科技股份有限公司 | Lock control method, device and system |
CN115273275B (en) * | 2021-04-29 | 2024-07-19 | 珠海优特电力科技股份有限公司 | Lockset control method, device and system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205721201U (en) | Fail safe system for transformer substation | |
CN104600849B (en) | Intelligent grid boss stands Layered Security anti-error system implementation method | |
CN101692524B (en) | Method and device for preventing faulty operation of electric power system based on wireless communication | |
CN202940643U (en) | Comprehensive anti-misoperation system for power distribution network | |
CN109787356B (en) | Transformer substation remote control anti-misoperation method and system based on IEC61850 protocol | |
CN101458505B (en) | Full-station anti-mistaking closedown design method based on IEC61850 standard | |
CN201498885U (en) | Electric power system faulty operation preventing device based on wireless communication | |
CN202034678U (en) | Error preventing system used for electrical power system | |
CN203630608U (en) | Operation anti-misoperation system of remote visualized transformer station | |
CN103199624A (en) | Smart converting station based on international electrotechnical commission (IEC) 61850 | |
CN104467183A (en) | Dispatch anti-misoperation system for regional power grid in adjustment and control integrated mode | |
CN110428533A (en) | One kind realizing the anti-error integrated intelligent lock management system of lock control based on Internet of Things | |
CN103475101A (en) | Misoperation-preventive locking management system of temporary ground wire of substation | |
CN101609332A (en) | Online three-layer synchronous anti-error locking system | |
CN102983627B (en) | Transition method of intellectualized monitoring system modification process of conventional transformer substation | |
CN202475014U (en) | Regional electrical network integrated five-preventing system | |
CN102290863A (en) | Distributed-feeder-automation-system-based remote monitoring terminal and implementation method | |
CN105446202A (en) | Five-prevention control system for transformer station | |
CN111917179B (en) | Real-time online misoperation prevention system of transformer substation based on multimode internet of things | |
CN206575227U (en) | A kind of power network operated applied to power network across standing is across five anti-monitoring systems of standing | |
CN109448481A (en) | Nuclear power station prevents the analog demenstration method and device of electric misoperation locking system | |
CN205725153U (en) | Substation relay protection hard pressing plate real time on-line monitoring device | |
CN205657497U (en) | Online management system of earthing for work line | |
CN104539045A (en) | Intelligent fault-analysis-prevention system and working method thereof | |
CN202798164U (en) | Comprehensive anti-error blocking device based on 3G wireless communication network |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20161123 Termination date: 20170415 |
|
CF01 | Termination of patent right due to non-payment of annual fee |