CN205712087U - A kind of partially prestressed concrete pile tube of grid form of reinforcement - Google Patents
A kind of partially prestressed concrete pile tube of grid form of reinforcement Download PDFInfo
- Publication number
- CN205712087U CN205712087U CN201620269867.1U CN201620269867U CN205712087U CN 205712087 U CN205712087 U CN 205712087U CN 201620269867 U CN201620269867 U CN 201620269867U CN 205712087 U CN205712087 U CN 205712087U
- Authority
- CN
- China
- Prior art keywords
- concrete pile
- reinforcement
- pile tube
- steel
- prestressed concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
The utility model discloses the partially prestressed concrete pile tube of a kind of grid form of reinforcement, including concrete pile body and the steel reinforcement cage being arranged in described concrete pile body, described steel reinforcement cage includes presstressed reinforcing steel, non-prestressing tendon and tubular bar-mat reinforcement, described presstressed reinforcing steel and non-prestressing tendon be arranged in parallel, and described tubular bar-mat reinforcement is fixing with presstressed reinforcing steel and non-prestressing tendon to be connected.The tubular bar-mat reinforcement that the prestressed high-strength concrete pile of the utility model grid form of reinforcement uses butt welding to be formed forms framework of steel reinforcement as stirrup with deformed bar, nonprestressed reinforcement welding, high-strength concrete is used to pour, the pile tube being formed is when bearing horizontal loading, the framework of steel reinforcement that can be formed by grid arrangement of reinforcement, is provided higher anti-side rigidity, ductility for pile tube and suppression diagonal crack produces and the ability of development.
Description
Technical field
The utility model belongs to pile tube field, the partially prestressed concrete pile tube of especially a kind of grid form of reinforcement.
Background technology
Prestressed concrete pipe pile is also known as pile tube or PHC, since the eighties, and the antidetonation to PHC pile tube for the researcher
Performance has carried out substantial amounts of research and test, the advantage compared to other pile-type for the pile tube in combination with theoretical calculation analysis.
Prestressed high-strength concrete pile is made up of cylindrical shape pile body, steel hoop, end plate, deformed bar and tie hoop.
Bigger vertical bearing capacity and certain anti-side rigidity can be provided, use pile tube as architecture basics structural system at building knot
Structure is applied quite varied.
The prestressed high-strength concrete pile of research and development mainly improves emphatically its vertical bearing capacity at present, high to prestressing force
The anti-seismic performance research of reinforced concrete pile tube is less.Building after residential building occurs overall toppling at Shanghai lotus flower in 2009,
Engineering field to pile tube water resistant the shortcoming of flat Lack of support pay attention to all the more.
Utility model content
Utility model purpose: provide the partially prestressed concrete pile tube of a kind of grid form of reinforcement, to solve existing pile tube
The problem of component Lack of support when by horizontal loading.
Technical scheme: the partially prestressed concrete pile tube of a kind of grid form of reinforcement, including concrete pile body and being arranged at
Steel reinforcement cage in described concrete pile body, described steel reinforcement cage includes presstressed reinforcing steel, non-prestressing tendon and tubular bar-mat reinforcement, institute
Stating presstressed reinforcing steel and non-prestressing tendon be arrangeding in parallel, described tubular bar-mat reinforcement is fixing with presstressed reinforcing steel and non-prestressing tendon even
Connect.
In a further embodiment, the two ends of described concrete pile body are provided with end plate, and the inner side of described end plate is fixing even
Connecing some anchor ribs, described non-prestressing tendon is fixing with anchor rib to be connected.The grid of described tubular bar-mat reinforcement is rhombus, net
The angle of lattice is 30 °~150 °.In tubular bar-mat reinforcement, the length of side of grid is 50~400 millimeters.Described concrete pile body
Two ends are provided with the cuff of cladding concrete pile body, and described cuff is fixing with end plate to be connected.Recessed along being circumferentially provided with of cuff
Trace.Described presstressed reinforcing steel and non-prestressing tendon interval are arranged.The intensity of described concrete pile body is C60~C80.Close mixed
The mesh-density of the bar-mat reinforcement of solidifying soil pile body end plate is more than the mesh-density of the bar-mat reinforcement in the middle part of concrete pile body.
Beneficial effect: the prestressed high-strength concrete pile of the utility model grid form of reinforcement uses the tubular that butt welding is formed
Bar-mat reinforcement forms framework of steel reinforcement as stirrup with deformed bar, nonprestressed reinforcement welding, uses high-strength concrete to pour,
The pile tube being formed when bearing horizontal loading, the framework of steel reinforcement that can be formed by grid arrangement of reinforcement, provide higher for pile tube
Anti-side rigidity, ductility and suppression diagonal crack produce and development ability.
Grid form of reinforcement partially prestressed concrete pile tube simple structure of the present utility model: general pile tube manufacturer
All can batch machining produce;Drawing materials conveniently: the steel wide material sources that the utility model uses, complete in specifications, it is convenient to buy,
Basis for there being specified level bearing capacity to need selects to provide a kind of new pile-type.
Brief description
Fig. 1 is longitudinal semi-cutaway of the present utility model.
Fig. 2 is cross-sectional view of the present utility model.
Fig. 3 is end view drawing of the present utility model.
Detailed description of the invention
Describe preferred embodiment of the present utility model below in conjunction with accompanying drawing in detail, but, the utility model is not limited to
Detail in above-mentioned embodiment, in technology concept of the present utility model, can be to skill of the present utility model
Art scheme carries out multiple equivalents, and these equivalents belong to protection domain of the present utility model.
This embodiment is partially prestressed concrete pile tube, and it mainly includes the 3rd deformed bar 301, and prism of third order body mixes
Solidifying soil 302, the 3rd tubular steel grid 303, the 3rd non-prestressing tendon 304, the 3rd steel hoop 305, the 3rd end plate
306 and the 3rd steel hoop indenture 307.
In this embodiment, pile concrete selects C60~C80.Pile concrete by the consumption requirement of every centrifugal pile tube,
Use charge car that fresh concrete uniformly fills up female die along mould, many as far as possible some concrete of cloth in stretch-draw one end.
Pile concrete wall thickness takes 80~130mm.Grid in tubular bar-mat reinforcement is rhombus.Tubular bar-mat reinforcement is away from stake end three
Increase mesh-density, to reach cipher round results in times stake footpath is interval.The steel grid of tubular bar-mat reinforcement resists according to required bending resistance
Cutting the difference of bearing capacity, steel grid angulation is also different, in the range from 30 °~150 °.Tubular bar-mat reinforcement
Network length of side span is at 50mm~400mm.The reinforced steel bar strength used of tubular bar-mat reinforcement resists according to required bending resistance
Cut the difference of bearing capacity, can be selected for the round reinforcing bar of hot calendering or employing first class cold-drawn low-carbon wire.Steel used by tubular bar-mat reinforcement
Muscle diameter is otherwise varied according to selected bar types difference, the round bar diameter of hot calendering between choose 6~10mm,
And first class cold-drawn low-carbon wire diameter is at 4~8mm.Nonprestressed reinforcement is different from ductility according to required bending strength,
Arrange a non-prestressing tendon between every deformed bar, it is possible to often between several deformed bars, arrange a non-pre-
Stress reinforcing bar.The reinforced steel bar strength of nonprestressed reinforcement according to the difference of required bending strength, its reinforcing bar can for HPB300,
HRB335, HRB400 and HRB500.The diameter of nonprestressed reinforcement is unsuitable with deformed bar different diameters excessive.
It is the diameter thin-wall circular steel pipe equal with pile tube external diameter that pile tube two ends are equipped with steel hoop, and end plate is identical with pile tube cross section
Circular hollow steel plate, end plate is welded on steel hoop one rear flank and is arranged on an end.It is welded with inside end plate with non-prestressing tendon with rule
Lattice, the anchor rib of equivalent amount, welding distributed points is basically identical with pile body non-prestressing tendon position.Non-prestressing tendon and anchor
Gu the mode using colligation overlap joint between reinforcing bar connects, the mode that anchor rib uses weld all around or stopple to weld with end plate is connected.Steel
Cuff is provided with two indentures on surface.Indenture is arranged at steel hoop, along the lateral arrangement two of steel hoop.
In this embodiment, longitudinal prestressing reinforcing bar and the non-pre-of the partially prestressed concrete pile tube of grid form of reinforcement should
Power muscle is wrapped up by tubular steel grid, and integrated tubular steel grid is increasing mesh-density cloth in three times of stake footpaths of stake end are interval
Put, and suitably adjust network angle and the length of side according to actual needs.The prestressed concrete pipe pile of grid form of reinforcement
Two ends are equipped with the diameter thin-wall circular steel pipe cuff equal with pile tube external diameter, and end plate mixes for the prestressing force with grid form of reinforcement
The identical circular hollow steel plate in solidifying soil pile tube cross section, end plate is welded on steel hoop one rear flank and is arranged on an end, adds inside end plate
Weldering and non-prestressing tendon same specification, the anchor rib of equivalent amount, welding distributed points and pile body non-prestressing tendon position basic
Cause.The mode using colligation overlap joint between non-prestressing tendon with anchor bar is connected, and anchor rib uses weld all around or hole with end plate
The mode of plug welding connects.
In a word, the utility model engineering structure antidetonation pile tube, especially its built-in stirrup are grid form of reinforcement, outside mixed
Solidifying soil is high-strength concrete.Vertical bearing capacity is good, and when by horizontal loading, netted form of reinforcement is compared to general
The generation of pile body diagonal crack and the inhibitory action of development are become apparent from by logical tie hoop, and its bending resistance shear-carrying capacity is compared
Having bigger lifting in prestressed concrete pipe pile, nonprestressed reinforcement can improve the ductility of pile tube itself simultaneously, compensate for
The general hypodynamic shortcoming of prestressed concrete pipe pile lateral loading.
Claims (9)
1. the partially prestressed concrete pile tube of a grid form of reinforcement, it is characterised in that include concrete pile body and set
Being placed in the steel reinforcement cage in described concrete pile body, described steel reinforcement cage includes presstressed reinforcing steel, non-prestressing tendon and tubular bar-mat reinforcement,
Described presstressed reinforcing steel and non-prestressing tendon be arranged in parallel, and described tubular bar-mat reinforcement is fixing with presstressed reinforcing steel and non-prestressing tendon even
Connect.
2. partially prestressed concrete pile tube as claimed in claim 1, it is characterised in that the two of described concrete pile body
End is provided with end plate, and the inner side of described end plate is fixing connects some anchor ribs, and described non-prestressing tendon is fixing with anchor rib even
Connect.
3. partially prestressed concrete pile tube as claimed in claim 1 or 2, it is characterised in that described tubular bar-mat reinforcement
Grid be rhombus, the angle of grid is 30 °~150 °.
4. partially prestressed concrete pile tube as claimed in claim 3, it is characterised in that grid in tubular bar-mat reinforcement
The length of side is 50~400 millimeters.
5. partially prestressed concrete pile tube as claimed in claim 2, it is characterised in that the two of described concrete pile body
End is provided with the cuff of cladding concrete pile body, and described cuff is fixing with end plate to be connected.
6. partially prestressed concrete pile tube as claimed in claim 5, it is characterised in that being circumferentially provided with along cuff
Indenture.
7. partially prestressed concrete pile tube as claimed in claim 1 or 2, it is characterised in that described presstressed reinforcing steel and
Non-prestressing tendon interval is arranged.
8. partially prestressed concrete pile tube as claimed in claim 1 or 2, it is characterised in that described concrete pile body
Intensity be C60~C80.
9. partially prestressed concrete pile tube as claimed in claim 3, it is characterised in that near concrete pile body end plate
The mesh-density of bar-mat reinforcement more than the mesh-density of the bar-mat reinforcement in the middle part of concrete pile body.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620269867.1U CN205712087U (en) | 2016-04-01 | 2016-04-01 | A kind of partially prestressed concrete pile tube of grid form of reinforcement |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620269867.1U CN205712087U (en) | 2016-04-01 | 2016-04-01 | A kind of partially prestressed concrete pile tube of grid form of reinforcement |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205712087U true CN205712087U (en) | 2016-11-23 |
Family
ID=57311743
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620269867.1U Expired - Fee Related CN205712087U (en) | 2016-04-01 | 2016-04-01 | A kind of partially prestressed concrete pile tube of grid form of reinforcement |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205712087U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105735309A (en) * | 2016-04-01 | 2016-07-06 | 江苏东浦管桩有限公司 | Prestressed concrete precast pile in form of mesh reinforcements |
CN108517985A (en) * | 2018-05-30 | 2018-09-11 | 重庆建工集团股份有限公司 | A kind of prestressing without bondn steel reinforced concrete wall and its construction method |
CN112078002A (en) * | 2020-09-26 | 2020-12-15 | 杨桂英 | Concrete pipe pile pouring equipment |
CN112482370A (en) * | 2020-11-07 | 2021-03-12 | 浙江数智交院科技股份有限公司 | Novel cross-section prestressed concrete tubular pile |
-
2016
- 2016-04-01 CN CN201620269867.1U patent/CN205712087U/en not_active Expired - Fee Related
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105735309A (en) * | 2016-04-01 | 2016-07-06 | 江苏东浦管桩有限公司 | Prestressed concrete precast pile in form of mesh reinforcements |
CN105735309B (en) * | 2016-04-01 | 2018-03-02 | 江苏东浦管桩有限公司 | A kind of prestressed concrete prefabricated pile of grid form of reinforcement |
CN108517985A (en) * | 2018-05-30 | 2018-09-11 | 重庆建工集团股份有限公司 | A kind of prestressing without bondn steel reinforced concrete wall and its construction method |
CN112078002A (en) * | 2020-09-26 | 2020-12-15 | 杨桂英 | Concrete pipe pile pouring equipment |
CN112078002B (en) * | 2020-09-26 | 2021-12-10 | 江苏省送变电有限公司 | Concrete pipe pile pouring equipment |
CN112482370A (en) * | 2020-11-07 | 2021-03-12 | 浙江数智交院科技股份有限公司 | Novel cross-section prestressed concrete tubular pile |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205712087U (en) | A kind of partially prestressed concrete pile tube of grid form of reinforcement | |
CN205653781U (en) | Some prestressed concrete sides stake of net arrangement of reinforcement form | |
CN104963415B (en) | A kind of round steel pipe binding type steel concrete column and steel beam joint structure | |
CN207331432U (en) | A kind of Novel steel pipe concrete pole | |
CN105735309B (en) | A kind of prestressed concrete prefabricated pile of grid form of reinforcement | |
CN102966101A (en) | Prestressed concrete solid square pile and making method thereof | |
CN104141298A (en) | Manufacturing and mounting method and auxiliary mounting device for reinforcement cage in pile hole | |
CN104563103A (en) | Composite-reinforcement partially-prestressed concrete solid square pile and production method thereof | |
CN104652430A (en) | Composite reinforcement partially prestressed concrete solid square pile and manufacturing method thereof | |
CN205712088U (en) | A kind of prestressed concrete square pile of grid form of reinforcement | |
CN203625894U (en) | Auxiliary device for installation of steel reinforcement cage in pile hole | |
CN203096777U (en) | Ultrasonic testing structure for concrete friction pile | |
CN105201144A (en) | Tree ring type high-strength concrete filled square steel tube column equipped with multiple spiral stirrups | |
CN203007936U (en) | Prestressed concrete solid square pile | |
CN208718381U (en) | A kind of blocking apparatus of different strength concrete | |
CN104060606A (en) | Combined splicing tubular pile and pile splicing method | |
CN203755466U (en) | Rusted reinforced concrete frame plane joint strengthening device | |
CN106948339B (en) | Steel reinforcement cage pipe penetrating guide and steel reinforcement cage pipe penetrating method | |
CN207332114U (en) | A kind of steel tube confinement concrete-filled rectangular steel tube component of sandwich | |
CN203007937U (en) | Prestressed concrete square pile | |
CN202865827U (en) | Multi-hole type hollow pile easy to sink | |
CN204753977U (en) | Cement concrete pillar | |
CN205077725U (en) | Year wheeled join in marriage multiple wire spiral square steel tube high -strength concrete post | |
CN108301560A (en) | A kind of steel core concrete column and its construction method of built-in high-strength angle steel | |
CN205676886U (en) | One pile for one column reducing steel reinforcement cage |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20161123 Termination date: 20210401 |
|
CF01 | Termination of patent right due to non-payment of annual fee |