CN205712076U - 施工桩体结构 - Google Patents

施工桩体结构 Download PDF

Info

Publication number
CN205712076U
CN205712076U CN201620363954.3U CN201620363954U CN205712076U CN 205712076 U CN205712076 U CN 205712076U CN 201620363954 U CN201620363954 U CN 201620363954U CN 205712076 U CN205712076 U CN 205712076U
Authority
CN
China
Prior art keywords
pile body
steel pipe
construction
coated
reinforcing bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620363954.3U
Other languages
English (en)
Inventor
梁枫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Coal Yangtze River infrastructure Co., Ltd
Original Assignee
Chengdu LVDI Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu LVDI Technology Co Ltd filed Critical Chengdu LVDI Technology Co Ltd
Priority to CN201620363954.3U priority Critical patent/CN205712076U/zh
Application granted granted Critical
Publication of CN205712076U publication Critical patent/CN205712076U/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

本实用新型公开了一种施工桩体结构,包括第一桩体,第一桩体呈空心结构,其外侧包覆有第二桩体,第二桩体呈实心结构,第二桩体外侧包覆有钢管,钢管与第二桩体之间灌注有水泥砂浆材料层,钢管内且位于水泥砂浆材料层上开有钢筋插孔,钢筋插孔竖向贯穿水泥砂浆材料层设置,钢管外侧包覆有钢混材料结构层,钢混材料结构层与钢管之间连接有固定筋,固定筋不止一个,本实用新型的施工桩体结构设计合理,具有良好的凝固连接性,桩体自身牢固性好,承受力度大,不会出现断裂等问题,大大增强了整体加固效果,可以更好的用于土木桩体支撑中。

Description

施工桩体结构
技术领域
本实用新型涉及一种桩体结构,特别涉及一种施工桩体结构。
背景技术
土木工程是建造各类工程设施的科学技术的统称。它既指所应用的材料、设备和所进行的勘测、设计、施工、保养维修等技术活动,也指工程建设的对象,即建造在地上或地下、陆上或水中,直接或间接为人类生活、生产、军事、科研服务的各种工程设施,例如房屋、道路、铁路、运输管道、隧道、桥梁、运河、堤坝、港口、电站、飞机场、海洋平台、给水和排水以及防护工程等。土木工程中常常见到打桩,现有的桩大多数是先打好地基,然后往打好的地基中填充水泥,再在水泥层上砌上一层层的砖头,这样操作起来比较的繁琐,不仅影响了施工进度,而且自身支撑性能存在一定的不足,不能更好的用于土木工程中。
发明内容
本实用新型要解决的技术问题是:克服上述问题,提供一种设计合理,具有良好的凝固连接性的施工桩体结构。
为了实现上述目的,本实用新型采用的技术方案是这样的:本实用新型的施工桩体结构,包括第一桩体,第一桩体呈空心结构,其外侧包覆有第二桩体,第二桩体呈实心结构,第二桩体外侧包覆有钢管,钢管与第二桩体之间灌注有水泥砂浆材料层,钢管内且位于水泥砂浆材料层上开有钢筋插孔,钢筋插孔竖向贯穿水泥砂浆材料层设置,钢管外侧包覆有钢混材料结构层,钢混材料结构层与钢管之间连接有固定筋,固定筋不止一个。
进一步的,作为一种具体的结构形式,本实用新型所述固定筋两两对称呈十字交叉结构排列在钢混材料结构层与钢管之间。
进一步的,作为一种具体的结构形式,本实用新型所述钢管厚度至少为三十毫米。
进一步的,作为一种具体的结构形式,本实用新型所述钢筋插孔不止一个。
进一步的,作为一种具体的结构形式,本实用新型所述钢筋插孔对应固定筋设置。
进一步的,作为一种具体的结构形式,本实用新型所述固定筋采用预应力钢索结构。
与现有技术相比,本实用新型的优点在于:本实用新型的施工桩体结构设计合理,具有良好的凝固连接性,桩体自身牢固性好,承受力度大,不会出现断裂等问题,大大增强了整体加固效果,可以更好的用于土木桩体支撑中。
附图说明
下面结合附图和实施例对本实用新型进一步说明。
图1为本实用新型的结构示意图;图中:1.第一桩体;2.第二桩体;3.钢管;4.钢混材料结构层;5.钢筋插孔;6.固定筋。
具体实施方式
现在结合附图对本实用新型作进一步详细的说明。这些附图均为简化的示意图,仅以示意方式说明本实用新型的基本结构,因此其仅显示与本实用新型有关的构成。
如图1所示的本实用新型施工桩体结构的优选实施例,包括第一桩体1,第一桩体1呈空心结构,其外侧包覆有第二桩体2,第二桩体2呈实心结构,第二桩体2外侧包覆有钢管3,钢管3与第二桩体2之间灌注有水泥砂浆材料层,钢管3内且位于水泥砂浆材料层上开有钢筋插孔5,钢筋插孔5竖向贯穿水泥砂浆材料层设置,钢管3外侧包覆有钢混材料结构层4,钢混材料结构层4与钢管3之间连接有固定筋6,固定筋6不止一个。
所述固定筋6两两对称呈十字交叉结构排列在钢混材料结构层与钢管之间。固定加强效果更强。
所述钢管3厚度至少为三十毫米。可以有效防止钢管3过薄影响使用性。
所述钢筋插孔5不止一个。便于插放更多钢筋。
所述钢筋插孔5对应固定筋6设置。避免插放时对周边造成开裂等问题。
所述固定筋6采用预应力钢索结构。使用效果更好。
本实用新型的施工桩体结构设计合理,具有良好的凝固连接性,桩体自身牢固性好,承受力度大,不会出现断裂等问题,大大增强了整体加固效果,可以更好的用于土木桩体支撑中。第一桩体1呈空心结构,其外侧包覆有第二桩体2,第二桩体2呈实心结构,设计合理,可以选择在第一桩体1灌注浆体,也可以选择不灌注,根据实际需要进行选择;第二桩体2外侧包覆有钢管3,钢管3与第二桩体2之间灌注有水泥砂浆材料层,钢管3内且位于水泥砂浆材料层上开有钢筋插孔5,钢筋插孔5竖向贯穿水泥砂浆材料层设置,使其能更大程度的提高整体支撑强度;钢管3外侧包覆有钢混材料结构层4,钢混材料结构层4与钢管3之间连接有固定筋6,固定筋6不止一个,能更好的起到加固作用。
以上述依据本实用新型的理想实施例为启示,通过上述的说明内容,相关工作人员完全可以在不偏离本项发明技术思想的范围内,进行多样的变更以及修改。本项发明的技术性范围并不局限于说明书上的内容,必须要根据权利要求范围来确定其技术性范围。

Claims (6)

1.一种施工桩体结构,包括第一桩体,其特征在于:第一桩体呈空心结构,其外侧包覆有第二桩体,第二桩体呈实心结构,第二桩体外侧包覆有钢管,钢管与第二桩体之间灌注有水泥砂浆材料层,钢管内且位于水泥砂浆材料层上开有钢筋插孔,钢筋插孔竖向贯穿水泥砂浆材料层设置,钢管外侧包覆有钢混材料结构层,钢混材料结构层与钢管之间连接有固定筋,固定筋不止一个。
2.根据权利要求1所述的施工桩体结构,其特征在于:所述固定筋两两对称呈十字交叉结构排列在钢混材料结构层与钢管之间。
3.根据权利要求1所述的施工桩体结构,其特征在于:所述钢管厚度至少为三十毫米。
4.根据权利要求1所述的施工桩体结构,其特征在于:所述钢筋插孔不止一个。
5.根据权利要求1所述的施工桩体结构,其特征在于:所述钢筋插孔对应固定筋设置。
6.根据权利要求1所述的施工桩体结构,其特征在于:所述固定筋采用预应力钢索结构。
CN201620363954.3U 2016-04-27 2016-04-27 施工桩体结构 Expired - Fee Related CN205712076U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620363954.3U CN205712076U (zh) 2016-04-27 2016-04-27 施工桩体结构

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620363954.3U CN205712076U (zh) 2016-04-27 2016-04-27 施工桩体结构

Publications (1)

Publication Number Publication Date
CN205712076U true CN205712076U (zh) 2016-11-23

Family

ID=57293704

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620363954.3U Expired - Fee Related CN205712076U (zh) 2016-04-27 2016-04-27 施工桩体结构

Country Status (1)

Country Link
CN (1) CN205712076U (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105821831A (zh) * 2016-04-27 2016-08-03 成都绿迪科技有限公司 施工桩体结构

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105821831A (zh) * 2016-04-27 2016-08-03 成都绿迪科技有限公司 施工桩体结构

Similar Documents

Publication Publication Date Title
CN103912011B (zh) 明挖预制装配式地下结构
CN108867310A (zh) 先张法预应力混凝土矮肋t梁桥及其施工方法
CN104294769B (zh) 一种补桩与增大台帽组合加固已建桥台结构的施工方法
CN103938634B (zh) 一种深基坑支护结构及施工方法
CN107246005A (zh) 超大直径钻埋钢管空心基桩及其施工方法
CN202787271U (zh) 一种基坑支护用叠加式内支撑结构
CN205296878U (zh) 一种建筑现浇钢筋临时防护结构
CN104563147A (zh) 适用于岩溶区的组合结构桩基础及其施工方法
CN108374674B (zh) 六导洞十二步地下空间开挖支护方法
CN102767187A (zh) 卵石地基漩流井逆作施工方法
CN208534081U (zh) 一种老建筑构造柱的改造结构
CN204112318U (zh) 一种提高cfg压灌桩承载力的技术装置
CN204097889U (zh) 一种补桩与增大台帽组合加固已建桥台结构
CN207331426U (zh) 一种铁路双箱型钢混凝土系梁系杆拱桥
CN205712076U (zh) 施工桩体结构
CN102691267A (zh) 一种外置整体操作平台高墩施工方法
CN104612142A (zh) 一种基于复合柔性桩的整体式桥台桥梁构造及其施工方法
CN205242437U (zh) 用于220kV电缆原位保护的冗余式竖向支撑结构
CN203891047U (zh) 搭设钢平台进行陆上桥梁基础施工设备
CN105821831A (zh) 施工桩体结构
CN207727554U (zh) 一种建筑用新型混凝土实心桩
CN203603525U (zh) 石结构外加夹板梁及夹板柱加固结构
CN204919568U (zh) 浅基坑复合支护结构
CN204059396U (zh) 塔吊底部固定基础结构
CN203924043U (zh) 一种竹筋混凝土桩

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20170308

Address after: 210046 Nanjing Province, Qixia District, the new road, No., No. 5

Patentee after: JIANGSU YANGTZE RIVER MECHANIZATION BASED ENGINEERING CO., LTD.

Address before: 610000 Jinjiang District, Chengdu, East Street, 18-32 No. 1, floor 5, layer 517,

Patentee before: Chengdu Lyudi Technology Co., Ltd.

TR01 Transfer of patent right
CP01 Change in the name or title of a patent holder

Address after: 210046 No. 5 Yaoxin Avenue, Qixia District, Nanjing City, Jiangsu Province

Patentee after: Jiangsu Changjiang mechanized Foundation Engineering Co., Ltd.

Address before: 210046 No. 5 Yaoxin Avenue, Qixia District, Nanjing City, Jiangsu Province

Patentee before: JIANGSU YANGTZE RIVER MECHANIZATION BASED ENGINEERING CO., LTD.

CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 210046 Nanjing Province, Qixia District, the new road, No., No. 5

Patentee after: China Coal Yangtze River infrastructure Co., Ltd

Address before: 210046 Nanjing Province, Qixia District, the new road, No., No. 5

Patentee before: JIANGSU CHANGJIANG MECHANIZATION FOUNDATION ENGINEERING Co.,Ltd.

CP01 Change in the name or title of a patent holder
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161123

Termination date: 20210427

CF01 Termination of patent right due to non-payment of annual fee