CN205676831U - The mud monitoring of dam sump and cleaning system - Google Patents

The mud monitoring of dam sump and cleaning system Download PDF

Info

Publication number
CN205676831U
CN205676831U CN201620532301.3U CN201620532301U CN205676831U CN 205676831 U CN205676831 U CN 205676831U CN 201620532301 U CN201620532301 U CN 201620532301U CN 205676831 U CN205676831 U CN 205676831U
Authority
CN
China
Prior art keywords
sump
mud
dam
cleaning system
bridge machine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620532301.3U
Other languages
Chinese (zh)
Inventor
方杰
周杰
李胜兵
吴胜华
曹春建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Huadong Engineering Corp Ltd
Original Assignee
PowerChina Huadong Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Huadong Engineering Corp Ltd filed Critical PowerChina Huadong Engineering Corp Ltd
Priority to CN201620532301.3U priority Critical patent/CN205676831U/en
Application granted granted Critical
Publication of CN205676831U publication Critical patent/CN205676831U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Landscapes

  • Sewage (AREA)

Abstract

The utility model provides mud monitoring and the cleaning system of a kind of dam sump, including mud monitor, described mud monitor stretches into bottom the sump of dam, the monitoring of described mud and cleaning system also include the high-lift bridge machine being arranged on dam top, offer below described high-lift bridge machine and hang thing hole, described thing hole of hanging is by hanging the inlet communication of object depth well and sump, connecting slurry collecting bucket below described high-lift bridge machine, described slurry collecting bucket can move up and down under described high-lift bridge machine effect in hanging object depth well.The utility model monitors the accumulation of mud situation bottom sump by mud monitor, once exceedes safe altitude, reports to the police, and is cleared up by the mud to alluvial bottom sump for the cleaning plant, plays a protective role pipeline and water pump group.

Description

The mud monitoring of dam sump and cleaning system
Technical field
The utility model relates to dam mud leakage water draining technology, belongs to Hydraulic and Hydro-Power Engineering field.
Background technology
It in order to discharge the percolating water in dam depended on two sides massif therewith, bottom dam, is provided with seepage drainage catchments Well and draining pump house, in order to discharge percolating water in dam body in time, to ensure the operation safety of dam.Dam is from foundation dredging To dam top pouring, often last for several years, even in order to ensure the safety of dam, after dam cast is bound, in dam Still in the grouting carrying out necessity and closure in portion's each layer gallery, to guarantee that dam is even gone up a century in coming few decades and can be stablized And safe operation.Seepage of dam drainage system then puts into operation already, containing high calcareous concrete during dam grouting Mud is unavoidably mixed into the percolating water of dam, along each layer seepage drainage gallery, is finally pooled to the seepage collection bottom dam Well, is discharged outside factory by drainage system.
Owing to seepage sump is typically located at the bottom of dam, and have inconvenient traffic, the concrete being deposited in sump Cannot discharge smoothly, be substantially all and need to be discharged by draining pump and drainpipe, the water quality density owing to being mixed with concrete is long-range In normal water quality density, draining pump power of motor is in overload operation, long-play, then the draining pump life-span significantly shortens, if Standby fault rate is higher, and even some power station equipment faults cause cannot discharging percolating water in time, affect dam safety;This type of draining Pump is many with longer lifting pipe, and dismounting is time-consumingly longer, and it is laborious to take a lot of work, and also brings very big puzzlement to operation maintenance personnel, Currently also there is no preferable way to solve problems.
It is, thus, sought for safer reliable drainaging scheme and system operation maintenance mode, to reduce the event of equipment Barrier rate, improves the reliability of drainage system, it is ensured that the operation safety of dam.
Content of the invention
Technical problem to be solved in the utility model is to provide mud monitoring and the cleaning system of a kind of dam sump, The accumulation of mud situation of sump at the bottom of dam can be monitored and clear up.
The utility model solves mud monitoring and the cleaning system of technical problem the technical scheme is that dam sump System, including mud monitor, described mud monitor stretches into bottom the sump of dam, and the monitoring of described mud and cleaning system are also Including be arranged on the high-lift bridge machine at dam top, offering and hang thing hole below described high-lift bridge machine, described thing hole of hanging is by hanging Object depth well and the inlet communication of sump, connect slurry collecting bucket below described high-lift bridge machine, described slurry collecting bucket can Move up and down in hanging object depth well under described high-lift bridge machine effect.
While using technique scheme, the utility model can also use or combine employing further below Technical scheme:
Being provided with sump hard shoulder in described sump, described sump hard shoulder is provided with temporary drainage pipe and interim row Water pump.
Described mud monitor is connected to warning device.
The porch of described sump is provided with plugging device.
The beneficial effects of the utility model are: the utility model monitors the mud bottom sump by mud monitor Alluvial situation, once exceedes safe altitude, reports to the police, and is carried out clearly by the mud to alluvial bottom sump for the cleaning plant Reason, plays a protective role to pipeline and water pump group.
Brief description
Fig. 1 is overall structure figure of the present utility model.
Detailed description of the invention
Referring to the drawings.
The mud monitoring of dam sump of the present utility model and cleaning system, including mud monitor 3, described mud is supervised Surveying instrument 3 and stretching into bottom the sump of dam, the monitoring of described mud and cleaning system also include being arranged on the high-lift of dam top Bridge machine 8, offers below described high-lift bridge machine 8 and hangs thing hole, and described thing hole of hanging is by hanging the import of object depth well 7 and sump even Logical, connect slurry collecting bucket 21 by hoist cable below described high-lift bridge machine 8, described slurry collecting bucket 21 can soar described Move up and down in hanging object depth well 7 under Cheng Qiao machine 8 effect, carry out slurry transportation and hang out.
It is provided with sump hard shoulder 24 in described sump, described sump hard shoulder 24 can arrange temporary drainage pipe 22 and temporary drainage pump 23, and place temporary source as required.
Described mud monitor 3 is connectable to warning device, and the porch of sump can arrange plugging device.
At ordinary times, the sedimentation thickness of sump can be monitored by the mud monitor 3 arranging bottom sump, works as mud When monitor 3 monitors the Installation Elevation that the slurry thickness depositing bottom sump has exceeded draining pump group, monitor system alarm, Notice repair and maintenance personnel.Repair and maintenance personnel, after receiving information, will carry out mud first with plugging device closure clear The gutter of the shunting gallery of the side that is connected with sump of reason, uses plugging device to carry out closure and sump hard shoulder simultaneously Through flow hole block, after guaranteeing that ne-leakage water enters sump for clearance, sump hard shoulder 24 sets up and faces When discharge pipe line and draining pump and draining power supply, the ponding on the alluvial mud bottom sump is pumped to hard shoulder another In the sump body of wall of side.After ponding pump drainage is clean, by artificial or mechanical excavating equipment mud put into or shovels into In slurry collecting bucket, utilize high-lift bridge machine 8, by hanging object depth well 7 and hanging thing hole, slurry collecting bucket 21 is winched to draining pump house Then mud in slurry collecting bucket 21 poured in trailer by layer, is transported to outside factory stack the appointed place of discarded building waste.

Claims (4)

1. the mud of dam sump is monitored and cleaning system, it is characterised in that: include mud monitor, described mud monitor Stretching into bottom the sump of dam, the monitoring of described mud and cleaning system also include the high-lift bridge machine being arranged on dam top, Offer below described high-lift bridge machine and hang thing hole, described thing hole of hanging by hanging the inlet communication of object depth well and sump, described height Connecting slurry collecting bucket below lift bridge machine, described slurry collecting bucket can hang object depth well under described high-lift bridge machine effect Inside move up and down.
2. the mud of dam sump as claimed in claim 1 is monitored and cleaning system, it is characterised in that: in described sump Being provided with sump hard shoulder, described sump hard shoulder is provided with temporary drainage pipe and temporary drainage pump.
3. the mud of dam sump as claimed in claim 1 is monitored and cleaning system, it is characterised in that: described mud is monitored Instrument is connected to warning device.
4. the mud of dam sump as claimed in claim 1 is monitored and cleaning system, it is characterised in that: described sump Porch is provided with plugging device.
CN201620532301.3U 2016-06-01 2016-06-01 The mud monitoring of dam sump and cleaning system Active CN205676831U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620532301.3U CN205676831U (en) 2016-06-01 2016-06-01 The mud monitoring of dam sump and cleaning system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620532301.3U CN205676831U (en) 2016-06-01 2016-06-01 The mud monitoring of dam sump and cleaning system

Publications (1)

Publication Number Publication Date
CN205676831U true CN205676831U (en) 2016-11-09

Family

ID=57434904

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620532301.3U Active CN205676831U (en) 2016-06-01 2016-06-01 The mud monitoring of dam sump and cleaning system

Country Status (1)

Country Link
CN (1) CN205676831U (en)

Similar Documents

Publication Publication Date Title
CN203259870U (en) Intelligent control system for prevention and treatment of city rainfall flood
CN204662649U (en) A kind of integral intelligent pumping plant
CN201874614U (en) Drainage structure for emptying overhaul of derivation tunnel
CN206621840U (en) A kind of efficiently removable three-level sedimentation tank device
CN202689175U (en) Water collecting well desilting system
CN104975648B (en) Combined system underground Rainwater Storage Tank
CN205557464U (en) Type of can decontaminating intelligence flood control dam
CN107354949B (en) Cyclic utilization system for the Metro station excavation water resource close to high slope
CN205894042U (en) Discharge system of slurry leakage water
CN103603666A (en) Tailing pond sand excavation method
CN109056879A (en) A kind of riverway sludge cleaning plant and construction method
CN205676831U (en) The mud monitoring of dam sump and cleaning system
CN108824348A (en) A kind of water-break system and its construction using steel structure derrick formula withdrawal nozzle
CN208949967U (en) A kind of subsurface stormwater recovery system
CN206971368U (en) Municipal rain, sewage pumping station sludge lifting system
CN106437842B (en) The auxiliary that subway crosses dewatering type tunnel between sea area simultaneous transfers drainage pumping plant
CN204023484U (en) In a kind of Substation Station, use prevention waterlogging device automatically
CN205676862U (en) The drainage equipment examination and repair system of mud leakage water
CN208167944U (en) It crosses sea, cross river section drainage pumping plant
CN217601482U (en) Water precipitation recovery and purification device in foundation pit process
CN208563239U (en) A kind of water-break system using steel structure derrick formula withdrawal nozzle
CN205672666U (en) Seepage of dam water sedimentation filtration system
CN209339302U (en) A kind of dredging dredger for drainage pipeline inspection well
CN208949951U (en) A kind of riverway sludge cleaning plant
CN205676854U (en) The drainage system of dam mud leakage water

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant