CN205663189U - Floor hangs mould device - Google Patents

Floor hangs mould device Download PDF

Info

Publication number
CN205663189U
CN205663189U CN201620451635.8U CN201620451635U CN205663189U CN 205663189 U CN205663189 U CN 205663189U CN 201620451635 U CN201620451635 U CN 201620451635U CN 205663189 U CN205663189 U CN 205663189U
Authority
CN
China
Prior art keywords
floor
lower mold
membrane module
mold assemblies
upper die
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620451635.8U
Other languages
Chinese (zh)
Inventor
李存进
陈文�
姜能
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUNAN SANY CONSTRUCTION INDUSTRY Co.,Ltd.
Sany Construction Technology Co Ltd
Original Assignee
Sany Housing Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sany Housing Industry Co Ltd filed Critical Sany Housing Industry Co Ltd
Priority to CN201620451635.8U priority Critical patent/CN205663189U/en
Application granted granted Critical
Publication of CN205663189U publication Critical patent/CN205663189U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model discloses a floor hangs mould device, including last membrane module, lower membrane module, coupling assembling and sealing member. Wherein, go up the membrane module, set up the top at the floor. The membrane module through coupling assembling, is connected with last membrane module down to the laminating sets up the bottom at the floor. The sealing member sets up the both sides of membrane module under for clearance between sealed floor and the lower membrane module. This floor hangs mould device on the one hand can go up mould, membrane module down through coupling assembling connections, not only the installation dismantle convenient, connect reliably, intensity is high, only go up the membrane module in addition and is covered in the pouring is distinguished, lower membrane module accessible dismantlement or cut coupling assembling and pull down, the reuse rate height has reduced the pouring cost, on the other hand, through lower membrane module and sealing member for the pouring raw materials provides holding power and leakproofness, can further improve the pouring solid nature, avoid the concrete to build the mould that rises that the back produced, leak the material phenomenon, and then improve the pouring quality, realize low cost, high -quality seam and pour into a mould.

Description

Floor hoisting die device
Technical field
This utility model relates to construction building field, particularly to a kind of floor hoisting die device.
Background technology
Laminated floor slab lifting construction is the important component part of assembled-type house structural system, showing between two pieces of floors Watering in step, tradition and the formwork way of main flow typically use and land scaffold support system, and not only efficiency of construction is low, intensity Difference, recycling rate of waterused are low, it is also difficult to the mould that rises produced after avoiding concrete placings, material leakage phenomenon, casting quality cannot ensure.Cause This, the cast-in-place seam between two pieces of laminated floor slabs the most quickly supports and dismantles, and how high-quality, the cast of low cost, It it is a difficult problem of puzzlement in current fabricated construction.
Utility model content
In view of this, the utility model proposes a kind of floor hoisting die device, to solve cast-in-place seam mesh between laminated floor slab The technical problem of front existing defects.
This utility model provides a kind of floor hoisting die device, including: upper die component, lower mold assemblies, connection assembly and close Sealing;
Upper die component, is arranged on the top of floor;
Lower mold assemblies, by connecting assembly, is connected with upper die component, is arranged on the bottom of floor with laminating;
Sealing member, is arranged on the both sides of lower mold assemblies, for sealing the gap between floor and lower mold assemblies.
Further, upper die component and lower mold assemblies, it is steel structure.
Further, a corresponding lower mold assemblies, multiple upper die component is set, and the distance of each adjacent upper die component is not More than 750 millimeters.
Further, connect assembly, including any one of split bolt threaded components latch assembly;
The first installing hole it is provided with on upper die component;
Corresponding first installing hole, on lower mold assemblies, is provided with the second installing hole;
Connect assembly and run through the first installing hole and the second installing hole, to connect upper die component and lower mold assemblies.
Further, connect assembly, also include pad, be arranged on the junction, bottom surface connecting assembly with lower mold assemblies.
Further, sealing member is elastic sealing element.
Further, upper die component, including a number of round steel and clamp;Clamp, is used for engaging round steel, and the first peace Dress hole is arranged on clamp.
Further, upper die component, including a number of angle steel, and the first installing hole is arranged on angle steel.
Further, lower mold assemblies, also include the reinforced steel being arranged on lower mold assemblies surrounding.
Further, reinforced steel, it is additionally arranged at the junction connecting assembly with lower mold assemblies.
The floor hoisting die device that this utility model provides, on the one hand can connect upper die component and lower module by connecting assembly Part, reliably, intensity is high, and in only upper die component is coated over pouring area, lower mold assemblies can for not only easy installation and removal, connection Being connected assembly by dismounting or cutting and pulled down, recycling rate of waterused is high, reduces cast cost;On the other hand, by lower module Part and sealing member are that cast raw material provides support force and sealing, can improve further cast solid property, avoid concrete placings after The mould that rises of generation, material leakage phenomenon, and then improve casting quality, it is achieved low cost, high-quality seam are poured into a mould.
Accompanying drawing explanation
The accompanying drawing constituting a part of the present utility model is further appreciated by of the present utility model for providing, and this practicality is new The schematic description and description of type is used for explaining this utility model, is not intended that improper restriction of the present utility model.? In accompanying drawing:
Fig. 1 is the structural representation of an embodiment of this utility model floor hoisting die device;
Fig. 2 is the black box enlarged drawing of an embodiment of this utility model floor hoisting die device;
Fig. 3 is the top view of an embodiment of this utility model floor hoisting die device;
Fig. 4 is the structural representation of another embodiment of this utility model floor hoisting die device;
Fig. 5 is the structural representation of an embodiment of the upper die component of this utility model floor hoisting die device;
Fig. 6 is the structural representation of another embodiment of the upper die component of this utility model floor hoisting die device;
Fig. 7 is the structural representation of an embodiment of the lower mold assemblies of this utility model floor hoisting die device;
Fig. 8 is the structural representation of another embodiment of the lower mold assemblies of this utility model floor hoisting die device.
Detailed description of the invention
It should be noted that in the case of not conflicting, the embodiment in this utility model and the feature in embodiment can To be mutually combined.Describe this utility model below with reference to the accompanying drawings and in conjunction with the embodiments in detail.
Below in conjunction with the accompanying drawings, preferred embodiment of the present utility model is described in further detail.As shown in Figure 1-2, for Seam between two pieces of laminated floor slab A of Quick pouring, this utility model provides a kind of floor hoisting die device, including: upper module Part 10, lower mold assemblies 20, connection assembly 30 and sealing member 40 (referring to Fig. 2 enlarged drawing).Wherein, upper die component 10, it is arranged on building The top of plate A.Lower mold assemblies 20, by connecting assembly 30, is connected with upper die component 10, is arranged on the bottom of floor A with laminating. Sealing member 40, is arranged on the both sides of lower mold assemblies 20, for sealing the gap between floor A and lower mold assemblies 20.Concrete, should The concrete form of sealing member 40 and set-up mode, this utility model is not construed as limiting, as long as can seal floor A and lower mold assemblies 20 it Between gap, i.e. reach invention objective of the present utility model.
In this embodiment, a specific embodiment of floor hoisting die device is given.Workmen folds cast two pieces When closing the seam between floor A, upper die component 10 and lower module can be fixed respectively by connecting upper and lower at floor A of assembly 30 Part 20, and in the both sides of lower mold assemblies 20, sealing member 40 is set, to seal the gap between floor A and lower mold assemblies 20.Fixing After this floor hoisting die device good, seam cast can be carried out at pouring area B, support so that lower mold assemblies 20 provides for cast raw material Power and sealing, a period of time to be waited for peacefully (the concrete time regarding cast raw material, environmental factors etc. depending on, general about two days), i.e. Complete seam casting process.Now, workmen can connect assembly 30 by dismounting or cutting, and removes lower mold assemblies 20, with Recycling.The floor hoisting die device that this embodiment proposes, on the one hand connects upper die component 10 and lower mold by connection assembly 30 Assembly 20, reliably, intensity is high, and only upper die component 10 is coated in pouring area, lower mold for not only easy installation and removal, connection Assembly 20 can be pulled down, and recycling rate of waterused is high, reduces cast cost;On the other hand, by lower mold assemblies 20 and sealing member 40 it is Cast raw material provides support force and sealing, can improve further cast solid property, avoid concrete placings after produce the mould that rises, leakage Material phenomenon, and then improve casting quality, it is achieved low cost, high-quality seam are poured into a mould.
Preferably, upper die component 10 and lower mold assemblies 20, it is steel structure.Relative to the mode of conventionally employed wooden model, Use upper die component 10 and the lower mold assemblies 20 of steel structure, can further improve the intensity of device, improve the table of casting and constructing Face impression quality.
Be more highly preferred to, as it is shown on figure 3, for improve lower mold assemblies 20 steadiness, can according to lower mold assemblies 20 across Length and size, a corresponding lower mold assemblies 20, multiple upper die component 10 is set.It is more highly preferred to, a lower mold assemblies 20, right 3-5 upper die component 10 (as it is shown on figure 3, a corresponding lower mold assemblies 20, be provided with 3 upper die components 10) should be set.More Preferably, the distance of each adjacent upper die component 10 is not more than 750 millimeters.
It is more highly preferred to, as it is shown in figure 1, connect assembly 30, optional but be not limited only to split bolt, threaded components, latch Any one of assembly.Corresponding, upper die component 10 arranges the first installing hole;On lower mold assemblies 20, corresponding first peace Dress hole arranges the second installing hole;Connect assembly 30 and run through the first installing hole and the second installing hole, with connect upper die component 10 and under Membrane module 20.
It is more highly preferred to, as shown in Figure 4, connects assembly 30, also include pad 31, be arranged on connection assembly 30 and lower module The junction, bottom surface of part 20, with the further stability improving connection assembly 30 and sealing.Concrete, this pad 31, optional But it is not limited only to corner pad.
It is more highly preferred to, sealing member 40, optional but be not limited only to elastic sealing element, such as rubber, silica gel, nylon etc..More Preferably, as in figure 2 it is shown, install sealing member 40 for firm, the edge of lower mold assemblies 20 can arrange convex edge, close to be fixed Sealing 40.
It is more highly preferred to, such as Fig. 3, shown in 5, upper die component 10, (it is illustrated as two circles including a number of round steel 11 Steel, preferably 20# round steel) and clamp 12.Clamp 12, is used for engaging round steel 11, and is arranged on clamp 12 by the first installing hole. This embodiment, gives a specific embodiment of upper die component 10, and it uses round steel and clamp, is combined as upper die component 10, easy installation and removal and intensity are big, can improve casting quality and efficiency further.
Being more highly preferred to, as shown in Figure 6, upper die component 10, including a number of angle steel, and the first installing hole is arranged on On angle steel, to run through connection assembly 30.This embodiment, gives another specific embodiment of upper die component 10, and it uses angle Steel is big as upper die component 10, same easy installation and removal and intensity, can improve casting quality and efficiency further.Additionally, Upper die component 10 also can use other formed steel construction, and this utility model is not construed as limiting.
It is more highly preferred to, as it is shown in fig. 7, lower mold assemblies 20, also includes the reinforced steel being arranged on lower mold assemblies 20 surrounding 21.As in figure 2 it is shown, when lower mold assemblies 20 includes reinforced steel 21, for firm installation sealing member 40, can be at reinforced steel 21 Edge is also provided with convex edge, with the sealing member 40 that is fixed.
It is more highly preferred to, as shown in Figure 8, reinforced steel 21, it is additionally arranged at the combination connecting assembly 30 with lower mold assemblies 20 Place, with the stability of firm connection assembly 30 with lower mold assemblies 20, improves upper die component 10 and the company of lower mold assemblies 20 further Connect steadiness.
The foregoing is only preferred embodiment of the present utility model, not in order to limit this utility model, all at this Within the spirit of utility model and principle, any modification, equivalent substitution and improvement etc. made, should be included in this utility model Protection domain within.

Claims (10)

1. a floor hoisting die device, it is characterised in that including: upper die component (10), lower mold assemblies (20), connection assembly (30) With sealing member (40);
Described upper die component (10), is arranged on the top of described floor (A);
Described lower mold assemblies (20), by described connection assembly (30), is connected with described upper die component (10), with by described lower mold Assembly (20) laminating is arranged on the bottom of described floor (A);
Described sealing member (40), is arranged on the both sides of described lower mold assemblies (20), is used for sealing described floor (A) and described lower mold Gap between assembly (20).
Floor hoisting die device the most according to claim 1, it is characterised in that described upper die component (10) and described lower module Part (20), is steel structure.
Floor hoisting die device the most according to claim 1, it is characterised in that a corresponding described lower mold assemblies (20), if Put multiple upper die component (10), and the distance of each adjacent described upper die component (10) is not more than 750 millimeters.
Floor hoisting die device the most according to claim 1, it is characterised in that described connection assembly (30), including to drawing spiral shell Bolt, threaded components, latch assembly any one;
Described upper die component is provided with the first installing hole on (10);
Corresponding described first installing hole, on described lower mold assemblies (20), is provided with the second installing hole;
Described connection assembly (30) runs through described first installing hole and described second installing hole, to connect described upper die component (10) With described lower mold assemblies (20).
Floor hoisting die device the most according to claim 4, it is characterised in that described connection assembly (30), also includes pad (31) junction, bottom surface of described connection assembly (30) and described lower mold assemblies (20), it is arranged on.
Floor hoisting die device the most according to claim 1, it is characterised in that described sealing member (40), for elastic sealing element.
7. according to the floor hoisting die device described in claim 4 or 5, it is characterised in that described upper die component (10), including some The round steel (11) of quantity and clamp (12);Described clamp (12), is used for engaging described round steel (11), and described first installing hole sets Put on described clamp (12).
8. according to the floor hoisting die device described in claim 4 or 5, it is characterised in that described upper die component (10), including some The angle steel of quantity, and described first installing hole is arranged on described angle steel.
9. according to the floor hoisting die device described in claim 1-6 any one, it is characterised in that described lower mold assemblies (20), Also include the reinforced steel (21) being arranged on described lower mold assemblies (20) surrounding.
Floor hoisting die device the most according to claim 9, it is characterised in that described reinforced steel (21), is additionally arranged at institute State the junction connecting assembly (30) with described lower mold assemblies (20).
CN201620451635.8U 2016-05-17 2016-05-17 Floor hangs mould device Active CN205663189U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620451635.8U CN205663189U (en) 2016-05-17 2016-05-17 Floor hangs mould device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620451635.8U CN205663189U (en) 2016-05-17 2016-05-17 Floor hangs mould device

Publications (1)

Publication Number Publication Date
CN205663189U true CN205663189U (en) 2016-10-26

Family

ID=57161430

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620451635.8U Active CN205663189U (en) 2016-05-17 2016-05-17 Floor hangs mould device

Country Status (1)

Country Link
CN (1) CN205663189U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109403217A (en) * 2018-12-13 2019-03-01 中国铁路总公司 Underwater gliders device and method for filling
CN110439266A (en) * 2019-07-29 2019-11-12 中建一局集团第三建筑有限公司 Waterproof instead hangs mould along aluminium alloy and utilizes the method on the anti-edge of its construction waterproof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109403217A (en) * 2018-12-13 2019-03-01 中国铁路总公司 Underwater gliders device and method for filling
CN110439266A (en) * 2019-07-29 2019-11-12 中建一局集团第三建筑有限公司 Waterproof instead hangs mould along aluminium alloy and utilizes the method on the anti-edge of its construction waterproof
CN110439266B (en) * 2019-07-29 2024-02-13 中建一局集团第三建筑有限公司 Waterproof reverse edge aluminum alloy hanging die and method for constructing waterproof reverse edge by using same

Similar Documents

Publication Publication Date Title
CN106869489A (en) Super High Core Walls Structure level and vertical synchronous construction top module system and construction method
CN108000689B (en) Combined template for concrete member with window frame, pouring method of combined template and concrete member
CN203334663U (en) Aluminum formwork for stairway structure
CN205663189U (en) Floor hangs mould device
CN106948519A (en) Packaging type composite performance building dismantling-free formwork
CN203361624U (en) Structure capable of rapidly detaching aluminum alloy head dies
CN207194619U (en) A kind of assembled regeneration concrete enclosure wall
CN205976072U (en) Assembly type structure wall body and prefabricated concrete structure
CN205502366U (en) Evaporate and press whole wallboard of aerated concrete
CN210032622U (en) Easy-to-detach end sealing template component
CN210597794U (en) Connecting device of prefabricated plate
CN208056107U (en) A kind of combined steel formwork support system
CN104295089A (en) Support system of cast-in-place concrete GBF honeycomb core dense-rib floor system
CN203270608U (en) Prefabricated combined pipe rack
KR20130082416A (en) Mold for tetrapod and their tetrapod
CN217150848U (en) Prefabricated fire-resistant concrete composite floor slab
CN211447763U (en) Improved post-cast strip formwork device for laminated floor
CN205804732U (en) A kind of unidirectional superimposed sheet cracking resistance water stop structure
CN205476249U (en) Quick detachable portable wall
CN108222349A (en) A kind of light steel of half assembled-foam concrete composite floor and its construction method
CN210598127U (en) Prefabricated assembled structure beam slab node support aluminum alloy template structure
CN209556351U (en) A kind of readily removable section construction aluminum alloy pattern plate
CN203939237U (en) The one-time formed erecting device of waterproof epirelief concrete component
CN206143914U (en) SC fabricated frame bearing structure system
CN220394648U (en) Invisible frame decorative well cover

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20181017

Address after: 102206, Beijing Changping District Huilongguan North Road 31 Industrial Park

Co-patentee after: Hunan 31 Construction Co., Ltd.

Patentee after: 31 Construction Technology Co., Ltd.

Address before: 410100 five, 31 industrial city, 1 road 31, Changsha economic and Technological Development Zone, Changsha, Hunan.

Patentee before: SANY Housing Project Co., Ltd.

CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 102200 1st floor, building 6, No.8 Beiqing Road, Huilongguan town, Changping District, Beijing

Patentee after: Sany Construction Technology Co.,Ltd.

Patentee after: HUNAN SANY CONSTRUCTION INDUSTRY Co.,Ltd.

Address before: 102206, Beijing Changping District Huilongguan North Road 31 Industrial Park

Patentee before: SANY CONSTRUCTION TECHNOLOGY Co.,Ltd.

Patentee before: HUNAN SANY CONSTRUCTION INDUSTRY Co.,Ltd.