CN205628994U - Rapid rounding device for wind power generation tower cylinder joint - Google Patents

Rapid rounding device for wind power generation tower cylinder joint Download PDF

Info

Publication number
CN205628994U
CN205628994U CN201620324597.XU CN201620324597U CN205628994U CN 205628994 U CN205628994 U CN 205628994U CN 201620324597 U CN201620324597 U CN 201620324597U CN 205628994 U CN205628994 U CN 205628994U
Authority
CN
China
Prior art keywords
strut
vaulting pole
dynamic
wind power
power generation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620324597.XU
Other languages
Chinese (zh)
Inventor
李三虎
康永杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN SHENGJIAYI ELECTRONICS Co Ltd
Original Assignee
TIANJIN SHENGJIAYI ELECTRONICS Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN SHENGJIAYI ELECTRONICS Co Ltd filed Critical TIANJIN SHENGJIAYI ELECTRONICS Co Ltd
Priority to CN201620324597.XU priority Critical patent/CN205628994U/en
Application granted granted Critical
Publication of CN205628994U publication Critical patent/CN205628994U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to a rapid rounding device for wind power generation tower cylinder joint, include: decide the vaulting pole and with decide the vaulting pole that moves that the vaulting pole matches and connects, it opens and to have a holding chamber of running through just to decide the vaulting pole lateral wall the interior roof and the interior diapire in holding chamber have hinged a U type hanging frame respectively symmetrically, it runs through to move the vaulting pole install through the pivot in the holding chamber decide the centre of vaulting pole, move and be equipped with can be respectively with two on the vaulting pole the arch that hanging frame matches and connects, the running roller is all installed to the tip deciding the vaulting pole and move the vaulting pole, when two hanging frame cup joint respectively moving the vaulting pole on and the equal joint of its tip in the arch time, can retrain and decide the vaulting pole and move the position relation between the vaulting pole. The utility model discloses compare in the prior art structure is more ingenious, the use is more convenient, can enough realize the better round effect that props, it can be less to prop round effect deviation moreover.

Description

A kind of Rapid rounding device for wind power generation tower cylinder joint
Technical field
This utility model belongs to wind power equipment mounting auxiliary technical field, particularly relates to a kind of wind power tower shell ring fast Speed circle-supporting device.
Background technology
At present, the pylon in Large-scale Wind Turbines typically uses the instruments such as sledgehammer, chock, fixed block and electric welding to set The standby hopeless limit strength that carries out is docked, owing to two shell rings being mutually butted are extremely difficult to preferable circularity at circle circle, school bowlder, Certainly exist ovality in various degree, thus shell ring can be made to install there is following difficulty: docking efficiency is low, and speed is slow; During because of two shell ring docking, fixed block to be often welded on two shell ring ends, and docking welding needs to lay fixed block behind location, Carry out the docking of lower portion, therefore, damage the surface quality around two shell ring circumferential welds.At present, pipe has pole on the market Formula circle-supporting device, this device not only uses inconvenience, and it is undesirable to hold round effect, and shell ring is easily damaged on the top of pole. For solving technical problem of the prior art, patent ZL201320662902.2 discloses a kind of wind power tower shell ring and quickly supports Circle device, including two isometric struts, hinge is passed through at the middle part of said two strut, the end peace of described strut Equipped with running roller, the axis of described running roller is parallel with the axis of described bearing pin, and the close side of said two strut is cut with scissors respectively Connecing thread bush block, said two thread bush block is connected by the threaded rod of TBE (threaded both ends), the screw thread at described threaded rod two ends Oppositely oriented.Although technique scheme solves above-mentioned technical problem to a certain extent, but, this technical scheme self Yet suffer from some technical problems to need to solve, such as: two struts are superimposed by bearing pin and hold round, so can make Obtaining the circle obtained by two struts is not in the same plane, thus appearance effect deviation;Take up room excessive etc..
Summary of the invention
This utility model provides one compared to existing technologies for solving technical problem present in known technology, knot Structure is the most ingenious, it is the most convenient to use, can either realize preferably holding round effect, and the effect deviation held round can be less Rapid rounding device for wind power generation tower cylinder joint.
This utility model is adopted the technical scheme that by solving technical problem present in known technology:
A kind of Rapid rounding device for wind power generation tower cylinder joint, including: determine strut and the dynamic strut matched with determining strut, described Determine strut sidewall and have a containing cavity run through and the inner roof wall of described containing cavity and interior diapire is hinged with a U with being respectively symmetrically Type hitching frame, described dynamic strut runs through described containing cavity and is arranged on the described center determining strut, described dynamic support by rotating shaft Bar is provided with projection that can be matched with two described hitching frames respectively, and the described end determining strut and dynamic strut is respectively mounted There is running roller, when two hitching frames are socketed on dynamic strut and when its end is all connected in projection respectively, can retrain and determine support Position relationship between bar and dynamic strut.
For solving technical problem of the prior art, this utility model is provided with technique scheme.
Compared with prior art, improvements of the present utility model are as follows:
The first: this utility model improves to be determined the structure of strut and determines the position relationship between strut and dynamic strut, it may be assumed that Described determining strut sidewall and have a containing cavity run through, described dynamic strut runs through described containing cavity and is arranged on institute by rotating shaft Stating the center determining strut, this measure can be effectively prevented from because the circle determining strut obtained during holding round with dynamic strut is not Occurring holding round the situation of effect deviation in the same plane, dynamic strut runs through containing cavity and can substantially keep and determine strut existing It is generally aligned in the same plane during holding round, effectively solves technical problem of the prior art.
It two is: this utility model improves the annexation determined between strut and dynamic strut, it may be assumed that described containing cavity interior Roof and interior diapire are hinged with a U-shaped hitching frame with being respectively symmetrically, described dynamic strut be provided with can respectively with described in two The projection that hitching frame is matched, when two hitching frames are socketed on dynamic strut and when its end is all connected in projection respectively, The position relationship determined between strut and dynamic strut can be retrained.
In this design, in order to retrain dynamic strut and the position relationship determined between strut, this utility model is designed with Hitching frame, why design its in containing cavity, be to determine, in order to save, the locational space that strut entirety takies, so, When without using hitching frame, hitching frame can be positioned in containing cavity by operator, convenient and simple;It addition, why Design hitching frame is U-shaped, is to determine strut for the ease of socket is described, especially for the ease of by hitching frame and described protruding phase Connect, so, when two hitching frames are socketed on dynamic strut and when its end is all connected in projection respectively, can The position relationship between strut and dynamic strut is determined in constraint.Determine between strut and dynamic strut to the most stably limit Relation, operator also can be after hitching frame be socketed in described projection, and on the free end of described projection, twist-on one is fixed Nut.
Through above-mentioned design, this utility model improves the structure determining strut and the position determining between strut and dynamic strut closes It is and improves the annexation determined between strut and dynamic strut, it is possible to efficiently solving technical problem of the prior art, Compared to existing technologies, structure is the most ingenious, it is the most convenient to use, can either realize preferably holding round effect, and And the effect deviation held round can be less.
For the ease of realizing connecting between projection and hitching frame, this utility model can also use following technical measures: institute State protruding sidewall genesis analysis and single projection along described dynamic strut to be obliquely installed relative to described dynamic strut.Longitudinally divide The projection of cloth can provide operator more to select, in order to Proper Match determines the angular relationship between strut and dynamic strut.
In order to, when without using protruding, be hidden, in order to bring unnecessary trouble, this utility model to operator Following technical measures can also be used: the sidewall of described dynamic strut is provided with and can accommodate the storage tank of described projection and described appearance Put groove to connect with described raised thread.Therefore when without using protruding, operator can by storage tank corresponding for its precession, To realize hiding.
For the ease of more securely installing running roller, this utility model can also use following technical measures: described determine strut and The end of dynamic strut is respectively provided with the U-shaped installing rack installing running roller.
This utility model has the advantage that with good effect:
Design based on technique scheme, this utility model is by improving the structure determining strut and determining strut and dynamic support Position relationship between bar and improve the annexation determined between strut and dynamic strut, it is possible to efficiently solve existing skill Technical problem in art, compared to existing technologies, structure is the most ingenious, it is the most convenient to use, can either realize relatively Good holds round effect, and the effect deviation held round can be less.
Improvement based on above-mentioned optimal technical scheme, this utility model is by the protruding genesis analysis of design, using the teaching of the invention it is possible to provide operation Person more selects, in order to Proper Match determines the angular relationship between strut and dynamic strut;Also by design storage tank with During without using protruding, hidden.The technical solution of the utility model is able to the most perfect, is more applicable for pushing away Wide use.
Accompanying drawing explanation
Fig. 1 is the axonometric chart structural representation determining strut of the present utility model;
Fig. 2 is the sectional view structural representation determining strut of the present utility model;
Fig. 3 is the axonometric chart structural representation of dynamic strut of the present utility model;
Fig. 4 is use status architecture schematic diagram of the present utility model.
In figure: 1, determine strut;2, dynamic strut;3, containing cavity;4, hitching frame;5, running roller;6, protruding;7, peace Shelve.
Detailed description of the invention
Below in conjunction with the accompanying drawings detailed description of the invention of the present utility model is described further.At this it should be noted that right Explanation in these embodiments is adapted to assist in and understands this utility model, but is not intended that restriction of the present utility model.This Outward, as long as the technical characteristic related in each embodiment of this utility model disclosed below does not constitutes punching each other Dash forward and just can be mutually combined.
Embodiment one:
Refer to Fig. 1, Fig. 2, Fig. 3 and Fig. 4, a kind of Rapid rounding device for wind power generation tower cylinder joint, including: determine strut 1 And with determining strut 1 matched dynamic strut 2, described determine strut 1 sidewall and have the containing cavity 3 run through and a described containing cavity The inner roof wall of 3 and interior diapire are hinged with a U-shaped hitching frame 4 with being respectively symmetrically, and described dynamic strut 2 runs through described containing cavity 3 And be arranged on the described center determining strut 1 by rotating shaft, described dynamic strut 2 be provided with can respectively with two described mountings The projection 6 that frame 4 is matched, the described end determining strut 1 and dynamic strut 2 is mounted on running roller 5, when two hitching frame 4 points Be not socketed on dynamic strut 2 and time its end is all connected on protruding 6, can retrain determine strut 1 and dynamic strut 2 it Between position relationship.
In the present embodiment, described protruding 6 along the sidewall genesis analysis and single protruding 6 of described dynamic strut 2 relative to institute State strut 2 to be obliquely installed.
In the present embodiment, the sidewall of described dynamic strut 2 is provided with and can accommodate the described storage tank of protruding 6 (not marking in figure) And described storage tank connects with described protruding 6 screw threads.
In the present embodiment, the described end determining strut 1 and dynamic strut 2 is respectively provided with the U-shaped installation installing running roller 5 Frame 7.
Using method:
During use, this utility model is put in the tip inside of shell ring, first, two hitching frames is socketed in respectively described dynamic On the correspondence position of strut, afterwards, dynamic strut is separated from each other, with determining strut, the angle position needed to operator, then Hitching frame is socketed in the projection corresponding to this position, can complete to hold round effect.
Being separated from each other with determining strut by dynamic strut, running roller rolls in the inner side of shell ring end, completes to hold round with this.
During installing hitching frame and projection, in order to the most stably limit the pass determining between strut and dynamic strut System, operator also can be after hitching frame be socketed in described projection, and on the free end of described projection, twist-on one fixes spiral shell Female.
These are only preferred implementation of the present utility model, it is noted that those skilled in the art are come Say, on the premise of without departing from this utility model know-why, it is also possible to make some improvements and modifications, these improve and Retouching also should be regarded as protection domain of the present utility model.

Claims (5)

1. a Rapid rounding device for wind power generation tower cylinder joint, including: determine strut (1) and matched with determining strut (1) Dynamic strut (2), it is characterised in that: described determine strut (1) sidewall and have a containing cavity run through (3) and described house The inner roof wall in chamber (3) and interior diapire are hinged with a U-shaped hitching frame (4) with being respectively symmetrically, and described dynamic strut (2) is run through Described containing cavity (3) is also arranged on the described center determining strut (1) by rotating shaft, and described dynamic strut (2) is provided with energy Enough projections (6) the most matched with two described hitching frames (4) respectively, described determine strut (1) and dynamic strut (2) End is mounted on running roller (5), when two hitching frames (4) are socketed on dynamic strut (2) and the equal clamping in its end respectively When protruding (6) are upper, the position relationship determined between strut (1) and dynamic strut (2) can be retrained.
A kind of Rapid rounding device for wind power generation tower cylinder joint the most according to claim 1, it is characterised in that: described projection (6) sidewall genesis analysis and single projection (6) along described dynamic strut (2) are inclined relative to described dynamic strut (2) Tiltedly arrange.
A kind of Rapid rounding device for wind power generation tower cylinder joint the most according to claim 1 and 2, it is characterised in that: described The sidewall of dynamic strut (2) is provided with and can accommodate the storage tank of described projection (6) and described storage tank and described projection (6) Screw thread connects.
A kind of Rapid rounding device for wind power generation tower cylinder joint the most according to claim 1 and 2, it is characterised in that: described The end determining strut (1) and dynamic strut (2) is respectively provided with the U-shaped installing rack (7) installing running roller (5).
A kind of Rapid rounding device for wind power generation tower cylinder joint the most according to claim 3, it is characterised in that: described fixed support The end of bar (1) and dynamic strut (2) is respectively provided with the U-shaped installing rack (7) installing running roller (5).
CN201620324597.XU 2016-04-15 2016-04-15 Rapid rounding device for wind power generation tower cylinder joint Expired - Fee Related CN205628994U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620324597.XU CN205628994U (en) 2016-04-15 2016-04-15 Rapid rounding device for wind power generation tower cylinder joint

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620324597.XU CN205628994U (en) 2016-04-15 2016-04-15 Rapid rounding device for wind power generation tower cylinder joint

Publications (1)

Publication Number Publication Date
CN205628994U true CN205628994U (en) 2016-10-12

Family

ID=57064321

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620324597.XU Expired - Fee Related CN205628994U (en) 2016-04-15 2016-04-15 Rapid rounding device for wind power generation tower cylinder joint

Country Status (1)

Country Link
CN (1) CN205628994U (en)

Similar Documents

Publication Publication Date Title
CN207045662U (en) A kind of multi-rotor aerocraft horizontal tilt folding frame
CN102619535B (en) Folding tunnel widening trolley
CN105703696A (en) Upright frame device applied to solar photovoltaic system
CN205628994U (en) Rapid rounding device for wind power generation tower cylinder joint
CN208226947U (en) A kind of photovoltaic electrification component of tilt adjustable
CN209145004U (en) A kind of steel building attachment device
CN112212092A (en) Fixing device for multi-pipeline connection
CN205056711U (en) Rapid rounding device for wind power generation tower cylinder joint
CN107508212B (en) A kind of portable installation aluminium alloy cable bracket
CN216041321U (en) Pre-supporting roof structure for subway underpass existing station
CN205056710U (en) Rapid rounding device for wind power generation tower cylinder joint
CN205948316U (en) Electronic hydraulic pressure basketball stands
CN204628999U (en) A kind of support and comprise the equipment of this support
CN209485341U (en) A kind of level bracket
CN208346654U (en) A kind of Hanging Basket for the construction of T-type beam
CN207723778U (en) A kind of adjustable tower fixation welder
CN208008211U (en) A kind of cable winding apparatus
CN212677893U (en) Supporting frame structure for agricultural greenhouse
CN205471944U (en) Inboard folding device is rolled up to film
CN205842211U (en) A kind of LNG tank formula container-type with middle mobile positioning mechanism
CN205690334U (en) A kind of Lampstand structure fallen
CN216277016U (en) Aligning and leveling assembly for assembling transfer beam
CN205764665U (en) A kind of welding box body upset frock
CN211397403U (en) Novel ladder
CN218403427U (en) Tower machine standard festival convenient to transportation dismouting

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161012

Termination date: 20170415