CN205557233U CN201620040359.6U CN201620040359U CN205557233U CN 205557233 U CN205557233 U CN 205557233U CN 201620040359 U CN201620040359 U CN 201620040359U CN 205557233 U CN205557233 U CN 205557233U
Authority
CN
China
Prior art keywords
cement concrete
layer
concrete pavement
grouting
injected hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620040359.6U
Other languages
Chinese (zh)
Inventor
陈作韶
马银华
晋风春
林建平
彭宗志
晁哲
张婷
周煜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Qinglian Highway Development Co Ltd
Chongqing Jiaotong University
Original Assignee
Guangdong Qinglian Highway Development Co Ltd
Chongqing Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Qinglian Highway Development Co Ltd, Chongqing Jiaotong University filed Critical Guangdong Qinglian Highway Development Co Ltd
Priority to CN201620040359.6U priority Critical patent/CN205557233U/en
Application granted granted Critical
Publication of CN205557233U publication Critical patent/CN205557233U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model discloses a cement concrete pavement structure of board at bottom of coming to nothing is handled through grout, there is the cement concrete pavement sheet layer of injected hole to restore district composite of fields grouting layer with being located to come to nothing including distributing, compound grouting layer is bilayer structure, the utility model discloses a cement concrete pavement structure of board at bottom of coming to nothing is handled through grout through special grouting layer structure, improves grouting layer's whole toughness and crack resistance, and the emaciated face of satisfying the need vacancy is effectual fills and the reinforcement, plays the effect that combines road surface and basic unit and makes it to become whole, effectually plays waterproof infiltration effect, can provide long -term durable even supporting to cement concrete pavement's plate body, the life on improvement road surface.

Description

Cement concrete pavement structure through grouting treatment plat-bottom escape
Technical field
This utility model relates to a kind of repaired pavement structure, particularly to a kind of cement concrete pavement structure through grouting treatment plat-bottom escape.
Background technology
The grouting material being currently used for administering cement road surface plate bottom empty is various in style, uneven, grouting effect is not fine, a lot of road decks occurred again coming to nothing or the situation of panel breaking in after filling period duration 2,3 years, not only waste substantial amounts of human and material resources, and it is likely to result in the further destruction on road surface, cement panel easily produces new crack, expand old crack, Pavement Condition declines until destroying rapidly, highly impact the serviceability of road, lose the life-span of cement concrete pavement, cause huge economic loss.
The space pattern in plat-bottom escape region is complicated, exists with a kind of random polymorphic structure after grouting material hardening between panel and basic unit, and stress concentration effect is obvious.Simultaneously, the residual attachment of the dirt such as purt mud, purt slurry in district's forming process of coming to nothing, can interfacial adhesion between appreciable impact grouting material and levels, under the long term of temperature and load, it is necessary to consider the ability that thin layer grouting body works alone with the form that separates with levels.In this condition, grout blanket stress is unfavorable, fracture easily occurs and then seriously crushes, after rainwater enters at Under Dynamic Load under easily again wash away come to nothing (secondary comes to nothing), make panel again be in the unfavoured state come to nothing.Therefore, for this angle, cement mortar class grouting material, in addition to must possessing the basic demand such as the good fluidity of existing specification proposition, early anti pressured intension height, must also possess superperformance in terms of the mechanical index such as toughness, cracking resistance (including plastic shrinkage cracking resistance).If additionally, the plastic shrinkage of grouting material, drying shrinkage are relatively big, also easily cause the secondary at the bottom of plate and come to nothing phenomenon, therefore the material that resisted shrinkage ability is good should be selected.
In sum, in order to reach the most durable plat-bottom escape regulation effect, the most durable uniformly supporting is provided to the plate body of cement concrete pavement, this will propose higher requirement to the physical and mechanical property of grouting material so that it has good toughness, cracking resistance and resisted shrinkage ability.
Utility model content
In view of this, the purpose of this utility model is to provide a kind of cement concrete pavement structure through grouting treatment plat-bottom escape, by special grout blanket structure, improve overall flexibility and the crack resistance of grout blanket, road pavement is come to nothing and is located effectively to be filled with and reinforcement, makes overall, effectively plays and prevents oozing effect under water, and reduce and even eliminate secondary and come to nothing risk, improve the service life on road surface.
Cement concrete pavement structure through grouting treatment plat-bottom escape of the present utility model, including the Cement Concrete Pavement Slab layer of injected hole being distributed and being positioned at the compound grouting layer of the restoring area that comes to nothing, described compound grouting layer is double-decker;
Further, the two-layer of described compound grouting layer is different material layer;
Further, described compound grouting layer is made up of PP fiber reinforced cement slurry upper strata and light water mud lower floor;
Further, described panel layer is distributed injected hole, and described injected hole penetration surface flaggy also runs through basic unit;
Further, described panel layer is uncracked integral slab, and injected hole is distributed along panel layer is overall in plum blossom-shaped, and the injected hole distance away from face plate edge is to arrange not less than 500mm;
Further, described panel layer is slit plate, and injected hole is distributed in four limits of panel layer and arranges with away from edges of boards edge 500mm;
Further, the crack periphery at slit plate is distributed injected hole, and described injected hole is arranged more than 300mm with crack distance;
Further, described injected hole high-strength mortar sealing of hole is floating.
The beneficial effects of the utility model: the cement concrete pavement structure through grouting treatment plat-bottom escape of the present utility model, the understructure of compound grouting layer for carrying out reinforcement (subsurface material good fluidity to the structure below basic unit and basic unit, penetration is strong, intensity is enough, effect is that space is filled, crack is repaired, materials reinforcing etc., ensure the bearing capacity of infrastructure), for the space of coming to nothing filling between panel and basic unit, (upper layer of material hardening process has certain micro-expansibility to superstructure, resisted shrinkage performance after hardening is good, antiseepage, cracking resistance, toughness, resistant to breakage performance is strong, ensure that interlayer come to nothing process durability), panel is made to obtain uniformly, lasting is effectively supporting.
By special grout blanket structure, improve overall flexibility and the crack resistance of grout blanket, road pavement is come to nothing and gap is effectively filled with and reinforcement, recover function and the road surface globality of road surface each structure interlayer, effectively play and prevent oozing effect under water, the plate body of cement concrete pavement can be provided the most durable uniform supporting, improve the service life on road surface.
Accompanying drawing explanation
With embodiment, this utility model is further described below in conjunction with the accompanying drawings:
Fig. 1 is structural representation of the present utility model;
Fig. 2, Fig. 3, Fig. 4 are the planar structure schematic diagram of Cement Concrete Pavement Slab layer.
Detailed description of the invention
Fig. 1 is structural representation of the present utility model, and Fig. 2, Fig. 3, Fig. 4 are the planar structure schematic diagram of Cement Concrete Pavement Slab layer;As shown in the figure: the cement concrete pavement structure through grouting treatment plat-bottom escape of the present utility model, including the Cement Concrete Pavement Slab layer 1 of injected hole 4 being distributed and being positioned at the compound grouting layer 2 of the restoring area that comes to nothing, described compound grouting layer 2 is double-decker;Compound grouting layer 2 is the double-decker that material is different, compound grouting layer 2 is by first grouting behind shaft or drift lining global formation, grouting material employing mobility near basic unit 3 is relatively big, the grouting material of good penetrability forms structure sheaf by slip casting, improve overall flexibility and the crack resistance of grout blanket, enable the uniform supporting that the plate body to cement concrete pavement provides the most durable.
In the present embodiment, the two-layer of described compound grouting layer is different material layer;By using the double-layer structure layer of different materials, improve underlying strength, improve bond strength between layers, improve the service behaviours such as the punishment cracking resistance of layer, toughness of coming to nothing, and then improve integrally-built bearing capacity.
In the present embodiment, described compound grouting layer 2 is made up of PP fiber reinforced cement slurry upper strata 21 and light water mud lower floor 22, and the polypropylene fibre of described PP fiber reinforced cement slurry is 9mm;Use the grout blanket of two-layer different materials, light water mud lower floor 22 is near basic unit 3, in order to reinforcement infrastructure and offer and the adhesive surface on upper strata, and PP fiber reinforced cement slurry is more preferable for the grout blanket effect of shallow-layer grouting formation, high with the adhesion strength of panel layer 1 and lower floor's micro-expansion cement slurry, be combined with lower floor and improve the resistance to compression of grout blanket, bending tensile strength on the whole, and can play toughness reinforcing, resistance is split, impervious effect, thus improves the impact resistance of pavement structure, crack resistance, impermeability and frost resistance etc. on the whole.
In the present embodiment, described injected hole 4 penetration surface flaggy 1 also runs through basic unit 3;And grouting post-grouting layer and basic unit 3 and the adhesion strength of panel layer 1 and firmness, it is ensured that grouting effect, grout hole size should be in the same size with filling nozzle.
In the present embodiment, described panel layer 1 is uncracked integral slab, and injected hole 4 is plum blossom-shaped distribution along panel layer 1 entirety, and the injected hole 4 distance away from face plate edge is to arrange not less than 500mm;Described panel layer 1 is slit plate, and injected hole 4 is distributed in four limits of panel layer 1 and arranges with away from edges of boards edge 500mm;Crack periphery at slit plate is distributed injected hole 4, and described injected hole 4 is arranged more than 300mm with crack distance;By plum blossom-shaped cloth hole when panel does not ftracture, the number concrete condition concrete analysis in hole, generally 5, the position of normal condition lower opening is not less than 500mm far from corner.Respectively increase by 1~2 holes in breaking joint both sides to there being a small amount of plate ruptured.Arrangement of boring holes is on four limits of plate, preferably away from each 500mm of edges of boards, avoids in cloth hole, plate middle position as far as possible.Slit plate considers in crack periphery cloth hole, with crack distance more than 300mm.
In the present embodiment, described injected hole 4 backfills sealing of hole with cement mortar, and described cement is identical with the cement grade of panel layer 1.
Finally illustrate is, above example is only in order to illustrate the technical solution of the utility model and unrestricted, although this utility model being described in detail with reference to preferred embodiment, it will be understood by those within the art that, the technical solution of the utility model can be modified or equivalent, without deviating from objective and the scope of technical solutions of the utility model, it all should be contained in the middle of right of the present utility model.

Claims (8)

1. the cement concrete pavement structure through grouting treatment plat-bottom escape, it is characterised in that: include point It is furnished with the Cement Concrete Pavement Slab layer of injected hole and is positioned at the compound grouting layer of the restoring area that comes to nothing, described multiple Conjunction grout blanket is double-decker.
Cement concrete pavement structure through grouting treatment plat-bottom escape the most according to claim 1, it is special Levy and be: the two-layer of described compound grouting layer is different material layer.
Cement concrete pavement structure through grouting treatment plat-bottom escape the most according to claim 2, it is special Levy and be: described compound grouting layer is made up of PP fiber reinforced cement slurry upper strata and light water mud lower floor.
4. according to the cement concrete through grouting treatment plat-bottom escape described in claim 1-3 any claim Pavement structure, it is characterised in that: described panel layer is distributed injected hole, and described injected hole penetration surface flaggy is also Run through basic unit.
Cement concrete pavement structure through grouting treatment plat-bottom escape the most according to claim 1, it is special Levying and be: described panel layer is uncracked integral slab, injected hole is distributed along panel layer is overall in plum blossom-shaped, The injected hole distance away from face plate edge is to arrange not less than 500mm.
Cement concrete pavement structure through grouting treatment plat-bottom escape the most according to claim 1, it is special Levying and be: described panel layer is slit plate, injected hole is distributed in four limits of panel layer and away from edges of boards edge 500mm Arrange.
Cement concrete pavement structure through grouting treatment plat-bottom escape the most according to claim 6, it is special Levy and be: the crack periphery at slit plate is distributed injected hole, and described injected hole and crack distance are more than 300mm Arrange.
Cement concrete pavement structure through grouting treatment plat-bottom escape the most according to claim 7, it is special Levy and be: described injected hole high-strength mortar sealing of hole is floating.
CN201620040359.6U 2016-01-17 2016-01-17 Cement concrete pavement structure of board at bottom of coming to nothing is handled through grout Expired - Fee Related CN205557233U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620040359.6U CN205557233U (en) 2016-01-17 2016-01-17 Cement concrete pavement structure of board at bottom of coming to nothing is handled through grout

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620040359.6U CN205557233U (en) 2016-01-17 2016-01-17 Cement concrete pavement structure of board at bottom of coming to nothing is handled through grout

Publications (1)

Publication Number Publication Date
CN205557233U true CN205557233U (en) 2016-09-07

Family

ID=56823834

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620040359.6U Expired - Fee Related CN205557233U (en) 2016-01-17 2016-01-17 Cement concrete pavement structure of board at bottom of coming to nothing is handled through grout

Country Status (1)

Country Link
CN (1) CN205557233U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106812119A (en) * 2017-03-10 2017-06-09 水利部交通运输部国家能源局南京水利科学研究院 Gasbag-type automatic safety device and its method for designing that face-plate of rockfill dam comes to nothing
CN111737807A (en) * 2020-07-02 2020-10-02 清华大学 Determination method for bearing capacity of angle steel connecting piece considering concrete void

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106812119A (en) * 2017-03-10 2017-06-09 水利部交通运输部国家能源局南京水利科学研究院 Gasbag-type automatic safety device and its method for designing that face-plate of rockfill dam comes to nothing
CN111737807A (en) * 2020-07-02 2020-10-02 清华大学 Determination method for bearing capacity of angle steel connecting piece considering concrete void

Similar Documents

Publication Publication Date Title
CN105839476B (en) A kind of structure for preventing railway bed from rising soil and its laying method
CN104674627B (en) A kind of seam construction method preventing old cement concrete road to add black top reflection crack
JPH111901A (en) New construction of road made from rigid material
CN206928165U (en) A kind of water penetration armored concrete basic unit
CN106436525B (en) A kind of old concrete road surface inhibits the composite construction and remodeling method of reflection crack
CN104929365B (en) Refuse of refuse burning generating plant discharging platform combined type surface construction technology
CN205557233U (en) Cement concrete pavement structure of board at bottom of coming to nothing is handled through grout
CN207749370U (en) A kind of novel railway sub-grade surface structure
CN108755979A (en) A kind of toilet moistureproof and waterproof processing method
CN110042800A (en) Concrete face rockfill dam leakage preventing structure
CN211973067U (en) Road and bridge connection transition structure for preventing and treating vehicle bump at bridge head
CN207110817U (en) Toilet threshold waterproof construction
CN104927759B (en) A kind of interface adhesive material and black overlay structure and its construction technology of changing in vain based on the material
CN209493776U (en) A kind of new-old concrete bond connected structure
RU162601U1 (en) REINFORCED NET FROM BASALT FIBER
CN207582229U (en) Compound plastic cement race track
CN207749382U (en) A kind of drainage pavement structure in sponge city
RU2318947C2 (en) Road paving construction method
KR100774446B1 (en) Repair method for pavement structure
CN205347979U (en) Novel concrete bridge face is mated formation
CN203238541U (en) Cement concrete bridge deck pavement structure capable of being applied to extreme operating environment
DE19913496B4 (en) Bodendämmelement
CN108570888A (en) It is a kind of to weaken the length mini pile construction and construction method that expansive soil foundation swells
JP7455473B2 (en) Pavement replacement method
CN209636588U (en) A kind of inside has the reinforcement subgrade and pavement of geotechnological water-permeable pipe

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160907