CN205532619U - Loess tunnel support system - Google Patents

Loess tunnel support system Download PDF

Info

Publication number
CN205532619U
CN205532619U CN201620329220.3U CN201620329220U CN205532619U CN 205532619 U CN205532619 U CN 205532619U CN 201620329220 U CN201620329220 U CN 201620329220U CN 205532619 U CN205532619 U CN 205532619U
Authority
CN
China
Prior art keywords
tunnel
support system
loess
foam concrete
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620329220.3U
Other languages
Chinese (zh)
Inventor
昝文博
赖金星
张玉伟
来弘鹏
刘禹阳
李又云
张梦泽
贺思悦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changan University
Original Assignee
Changan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changan University filed Critical Changan University
Priority to CN201620329220.3U priority Critical patent/CN205532619U/en
Application granted granted Critical
Publication of CN205532619U publication Critical patent/CN205532619U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a loess tunnel support system, including advance support, the primary structure with rigid support etc. Is strutted to the flexibility, and each structural layer is according to the construction process in proper order immediately following executing the work. Advance support passes through the advanced small pipe grouting pre -reinforcing country rock, the flexibility is strutted to assemble through prefabricated foam concrete piece adoption bolted connection and is formed, seam between all prefabricated foam concrete pieces adopts elasticity rubber packing pad waterproof seal, rigid support includes that it arranges a week to follow the tunnel hoop, the steel pipe concrete arch that longitudinal separation was arranged puts up and fills the precast reinforced concrete section of jurisdiction between steel pipe concrete arch frame, through vertical steel bar connection between two adjacent pin steel pipe concrete arch frame, pass through bushing between the steel pipe hoop, pass through bolted connection between the precast reinforced concrete section of jurisdiction. The utility model discloses when effectively guaranteeing tunnel structure safety, the process is simple, and the construction progress is fast, the high quality, and water -proof effects is good.

Description

A kind of loess tunnel support system
[technical field]
This utility model relates to constructing tunnel support technology field, is specifically related to a kind of loess tunnel support system.
[background technology]
In recent years, along with the fast development of China western part Canal in Loess Area transport development cause, Henan, Shaanxi, Gansu, Qinghai and other places Build large quantities of loess tunnel.Widely used New Austrian Tunneling Method in rock tunnel in the past is still continued to use in the design of loess tunnel, construction, Use gunite concrete as preliminary bracing, deform basicly stable after apply secondary lining, secondary lining is mainly as safety stock. But, owing to loess is very big with the differences of mechanical properties of rock, has and significantly meet water settlement by soaking, and necessarily press from both sides during gunite concrete With water, loess country rock absorbs the moisture in concrete and easily becomes unstable, reduces self.According to on-the-spot test As a result, loess tunnel construction process generally exists pressure from surrounding rock is big, deflection big, the deformation persistent period is long, need in deformation not Apply lining cutting in the case of Wen Ding in time, cause secondary lining to assume responsibility for bigger load, undertake sometimes even over preliminary bracing Load.
At present, loess tunnel all occurs in that series of problems during early stage construction and later stage operation, change as big in construction period country rock Shape, unstability so cave in, preliminary bracing cracking, secondary Lining cracks, Tunnel Water Leakage etc. during operation.Therefore, only take Conventional New Austrian Tunneling Method measure, it is difficult to ensure that loess tunnel structural safety, needs to combine the special engineering characteristic of loess and tunnel stress becomes New Supporting mode and construction method thereof that shape properties study is necessary ensure constructing tunnel, operation security.
[utility model content]
The purpose of this utility model is defect and the deficiency existed for prior art, it is provided that a kind of loess tunnel support system, should System can effectively solve the problem that the problems such as large deformation, percolating water and the Lining cracks that current loess tunnel generally exists, thus ensures tunnel The safety and stablization of road structure.
For achieving the above object, this utility model is by the following technical solutions:
A kind of loess tunnel support system, including advance support, advance support is arranged in tunnel surrounding, enclosing for Strengthening Tunnel Rock, the surface configuration at tunnel surrounding has flexible support, and flexible support covers the surface of full tunnel surrounding, at the interior table of flexible support Being provided with rigid protection on face, along the circumference in tunnel, rigid protection is arranged one week, and along the longitudinal direction in tunnel, rigid protection is spaced Arrange.
Described advance support includes advanced tubule 1 and by the advanced tubule 1 slip casting country rock that slip casting is formed in country rock.
Described advanced tubule 1 is arranged at tunnel tunnel face in the range of 120 ° of vault, circumferentially disposed along tunnel, advanced tubule 1 spacing circumferential along tunnel is 30cm~50cm, and outer limb is 3 °~5 °, a length of 6m~8m.
The grouting serous fluid of advance support is cement-sodium silicate double liquid.
Described flexible support includes precast foam concrete block 2, is bolted and seals between precast foam concrete block 2, The inner side being arranged on country rock wall forms flexible support, precast foam concrete block 2 offers lock foot anchoring stock hole, at this lock foot anchoring stock Being provided with lock foot anchoring stock 3 in hole, lock foot anchoring stock 3 is for being anchored in country rock by precast foam concrete block 2.
It is full of bonding agent in gap between described precast foam concrete block 2, and in seam, is provided with elastic rubber gasket 7, Elastic rubber gasket 7 is adhesively fixed with precast foam concrete block 2 by bonding agent.
Seam between described precast foam concrete block 2 all staggers setting.
Described rigid protection includes concrete filled steel tube bow member 9, and concrete filled steel tube bow member 9 circumferentially disposed a week along tunnel, along tunnel The longitudinally spaced layout in road, is filled with prefabricated reinforced concrete section of jurisdiction 8 between adjacent concrete filled steel tube bow member 9.
Described concrete filled steel tube bow member 9 includes hollow steel pipe 4, is full of concrete 5 in hollow steel pipe 4, along tunnel hoop, The seam crossing of the hollow steel pipe 4 being disposed adjacent is arranged with sleeve pipe 6, and the hollow steel pipe 4 being disposed adjacent is connected by sleeve pipe 6.
Along the longitudinal direction in tunnel, it is provided with longitudinal reinforcement between the two Pin concrete filled steel tube bow members 9 being disposed adjacent, the two of longitudinal reinforcement End is connected with concrete filled steel tube bow member 9 respectively.
Compared with prior art, the utility model has the advantage of:
This utility model improves country rock by arranging advance support and reinforces country rock, improves the self-bearing capacity of country rock, it is possible to increase The safety of construction, by arranging flexible support in the inner side of country rock wall, it is possible to making deformation develop, stress has discharged, logical Crossing and arrange rigid protection in the inner side of flexible support, the strength and stiffness higher by the concrete filled steel tube bow member of rigid protection can have Effect ground controls deformation, it is ensured that the safety of structure.
Further, being tightly connected between precast foam concrete block, therefore flexible support has waterproof effect, can set specially Put waterproof layer, cost-effective.
Further, use elastic rubber gasket between precast foam concrete block seam, absorbed by elastic rubber gasket Because of deformation energy during tunnel deformation, advantageously ensure that the safety of tunnel structure.
This utility model is suitable for the stress of loess tunnel, deformation behaviour, makes deformation develop by flexible support, and stress is Release, utilizes the strength and stiffness that concrete filled steel tube bow member is higher to control deformation, resists load, it is ensured that tunnel structure safety;It is suitable for In having the loess engineering of surrounding rock characteristic of vertical joints and notable settlement by soaking, whole process realizes " anhydrous, dustless " construction, it is to avoid Construction water causes Loess Collapsibility, improves tunnel construction environment;By foam concrete and elastic rubber gasket sealed waterproof effect Good, cancel special waterproof layer;The all components of assembled support system can batch production prefabricated, construction speed is fast, good water-proof effect, Cost is low, and construction quality is reliable.
[accompanying drawing explanation]
Fig. 1 is tunnel support system cross-sectional configuration schematic diagram of the present utility model;
Fig. 2 is tunnel support system longitudinal plane structure schematic diagram of the present utility model;
Fig. 3 is to use this utility model schematic cross-sectional view when constructing tunnel;
Fig. 4 is to use this utility model schematic longitudinal section when constructing tunnel;
Wherein: 1 advanced tubule, 2 precast foam concrete blocks, 3 lock foot anchoring stocks, 4 hollow steel pipes, 5 perfusions are mixed Solidifying soil, 6 sleeve pipes, 7 elastic rubber gaskets, 8 prefabricated reinforced concrete sections of jurisdiction, 9-armored concrete bow member.
[detailed description of the invention]
With detailed description of the invention, this utility model is described in detail below in conjunction with the accompanying drawings.
Seeing Fig. 1 and Fig. 2, this utility model includes advance support, flexible support and rigid protection, advance support, flexible support With rigid protection by working procedure successively immediately following applying, advance support is for arrange advanced tubule 1 along arch, tunnel contour line, and leads to Crossing advanced tubule 1 and inject the pre-reinforcement country rock that cement-sodium silicate double liquid is formed in country rock, flexible support is by prefabricated bubble Foam concrete block 2 is assembled, is bolted between precast foam concrete block 2, at all precast foam concrete blocks 2 Between seaming position use elastic rubber gasket 7 seal waterproof, elastic rubber gasket 7 is bonded in prefabricated bubble by bonding agent On foam concrete block 2, and making bonding agent fill sealing gasket groove, lock foot anchoring stock hole reserved on precast foam concrete block 2 is installed Lock foot anchoring stock 3;Rigid protection includes along tunnel circumferentially disposed one week, the concrete filled steel tube bow member 9 of longitudinally spaced setting and being filled in Prefabricated reinforced concrete section of jurisdiction 8 between concrete filled steel tube bow member 9, prefabricated reinforced concrete section of jurisdiction 8 be bolted assembly and Become.
Advance support is applied along tunnel circumference in the range of 120 ° of vault at tunnel tunnel face by advanced tubule 1, the least leads Pipe circumferential distance is 30cm~50cm, and outer limb is 3 °~5 °, a length of 6m~8m.
Concrete filled steel tube bow member 9 is for by being formed to hollow steel pipe 4 luminal perfusion concrete 5;
Monocoque structure is formed by longitudinal reinforcement welding, by set between hollow steel pipe 4 hoop between concrete filled steel tube bow member 9 Pipe 6 connects.
See Fig. 3,4, implement this utility model construction method time, first excavated section is divided into the most successively and topping bar (I, II), get out of a predicament or an embarrassing situation (III, IV) and inverted arch part V, top bar (I, II), get out of a predicament or an embarrassing situation (III, IV) and inverted arch part V Use benching tunnelling method faulting of slab ends excavation, top bar (I, II), the distance controlling got out of a predicament or an embarrassing situation (III, IV) and stagger before and after inverted arch part V At 4m~6m, the reserved central core soil II of excavation of topping bar, the staggered excavation of arranged on left and right sides of getting out of a predicament or an embarrassing situation (III, IV);
Specifically include following steps:
Along 120 °, arch, tunnel scope excavation contour line, apply advanced tubule 1 and cementing-waterglass dual slurry pre-reinforcement is enclosed Rock, advanced tubule 1 circumferential distance is 30cm~50cm, and outer limb is 3 °~5 °, a length of 6m~8m;
Carry out topping bar under the protection of advanced tubule supporting I excavation and reserved central core soil II, top bar and I excavate every time Drilling depth is the width of 1 times of precast foam concrete block 2;Seaming position between all precast foam concrete blocks 2 uses binding agent Bonding elastic rubber gasket 7, and make binding agent fill sealing gasket groove;
Inside country rock wall corresponding above the I that tops bar, it is bolted assembled precast foam concrete block 2, and by prefabricated Lock foot anchoring stock 3 is installed in lock foot anchoring stock hole reserved on foam concrete block 2;
Excavation central core soil II, excavation drilling depth is the width of 1~2 times of precast foam concrete block 2 every time, central core soil II 2m~3m distance is remained with face of topping bar;
Excavating left side III of getting out of a predicament or an embarrassing situation, excavation drilling depth controls, at 1~2 times of precast foam concrete block width, then to pass through bolt every time Spreading is got out of a predicament or an embarrassing situation left part precast foam concrete block 2, and partial precast foam concrete block 2 connects into entirety with topping bar, and Lock foot anchoring stock 3 is installed by lock foot anchoring stock hole reserved on precast foam concrete block 2;
Excavating right side IV of getting out of a predicament or an embarrassing situation, construction procedure is with the left side III that gets out of a predicament or an embarrassing situation;
The soil body of excavation inverted arch part V, the width that drilling depth is 1-2 times of precast foam concrete block 2 of excavation, then passes through every time The precast foam concrete block 2 of bolt assembly inverted arch part, and flexible support corresponding with upper and lower step part immediately connects into whole Body, makes flexible support close cyclization;
Immediately following applying rigid protection layer, set up hollow steel pipe 4, connected by sleeve pipe 6 between hollow steel pipe hoop, and by longitudinally Reinforcing bar and previous Pin concrete filled steel tube bow member 9 connect into monocoque structure;
Assembled prefabricated reinforced concrete section of jurisdiction 8 between two Pin concrete filled steel tube bow members 9, along the circumference in tunnel, precast reinforced mixed Solidifying soil section of jurisdiction 8 is bolted together;
By the reserved injected hole on hollow steel pipe 4 to hollow steel pipe luminal perfusion concrete 5, form concrete filled steel tube bow member 9;
Repeat above construction procedure, carry out tunnel and persistently excavate.
By assembled support system and the construction method thereof of above-mentioned utility model, it is provided with advance support, flexible support and rigidity and props up Protecting, advance support improves country rock and reinforces country rock, improves self;Flexible support makes deformation develop, and stress is Release, flexible support seaming position uses elastic rubber gasket sealed waterproof effect good, can cancel special waterproof layer;Rigidity is propped up Protect the strength and stiffness utilizing concrete filled steel tube bow member higher and control deformation, it is ensured that structural safety;Whole process realizes " anhydrous, nothing Dirt " construction, it is to avoid construction water causes Loess Collapsibility, improves tunnel construction environment;Use assembled support system, all components Can batch production prefabricated, construction speed is fast, and construction quality is reliable.

Claims (10)

1. a loess tunnel support system, it is characterised in that include that advance support, advance support are arranged in tunnel surrounding, be used for The country rock of Strengthening Tunnel, the surface configuration at tunnel surrounding has flexible support, and flexible support covers the surface of full tunnel surrounding, Being provided with rigid protection on the inner surface of flexible support, along the circumference in tunnel, rigid protection is arranged one week, along tunnel Longitudinal direction, rigid protection interval arrange.
A kind of loess tunnel support system the most according to claim 1, it is characterised in that described advance support includes the least leading Manage (1) and by advanced tubule (1) the slip casting country rock that slip casting is formed in country rock.
A kind of loess tunnel support system the most according to claim 2, it is characterised in that described advanced tubule (1) is arranged At tunnel tunnel face in the range of 120 ° of vault, circumferentially disposed along tunnel, advanced tubule (1) is along the spacing of tunnel circumference For 30cm~50cm, outer limb is 3 °~5 °, a length of 6m~8m.
A kind of loess tunnel support system the most according to claim 2, it is characterised in that the grouting serous fluid of advance support is cement -waterglass dual slurry.
A kind of loess tunnel support system the most according to claim 1, it is characterised in that described flexible support includes preformed foam Concrete block (2), precast foam concrete block is bolted and seals between (2), is arranged on the inner side of country rock wall Forming flexible support, precast foam concrete block offers lock foot anchoring stock hole on (2), is provided with in this lock foot anchoring stock hole Lock foot anchoring stock (3), lock foot anchoring stock (3) is for being anchored in country rock by precast foam concrete block (2).
A kind of loess tunnel support system the most according to claim 5, it is characterised in that described precast foam concrete block (2) Between gap in be full of bonding agent, and in seam, be provided with elastic rubber gasket (7), elastic rubber gasket (7) It is adhesively fixed with precast foam concrete block (2) by bonding agent.
A kind of loess tunnel support system the most according to claim 5, it is characterised in that described precast foam concrete block (2) Between seam all stagger setting.
A kind of loess tunnel support system the most according to claim 1, it is characterised in that described rigid protection includes steel tube concrete Soil bow member (9), concrete filled steel tube bow member (9) circumferentially disposed a week along tunnel, longitudinally spaced layout, phase along tunnel It is filled with prefabricated reinforced concrete section of jurisdiction (8) between adjacent concrete filled steel tube bow member (9).
A kind of loess tunnel support system the most according to claim 8, it is characterised in that described concrete filled steel tube bow member (9) Including hollow steel pipe (4), being full of concrete (5) in hollow steel pipe (4), along tunnel hoop, be disposed adjacent is hollow The seam crossing of steel pipe (4) is arranged with sleeve pipe (6), and the hollow steel pipe being disposed adjacent (4) is connected by sleeve pipe (6).
A kind of loess tunnel support system the most according to claim 8, it is characterised in that along the longitudinal direction in tunnel, be disposed adjacent Two Pin concrete filled steel tube bow member (9) between be provided with longitudinal reinforcement, the two ends of longitudinal reinforcement respectively with concrete-filled steel tube arch Frame (9) connects.
CN201620329220.3U 2016-04-19 2016-04-19 Loess tunnel support system Expired - Fee Related CN205532619U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620329220.3U CN205532619U (en) 2016-04-19 2016-04-19 Loess tunnel support system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620329220.3U CN205532619U (en) 2016-04-19 2016-04-19 Loess tunnel support system

Publications (1)

Publication Number Publication Date
CN205532619U true CN205532619U (en) 2016-08-31

Family

ID=56792530

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620329220.3U Expired - Fee Related CN205532619U (en) 2016-04-19 2016-04-19 Loess tunnel support system

Country Status (1)

Country Link
CN (1) CN205532619U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105863681A (en) * 2016-06-27 2016-08-17 西北大学 Quick protecting method for sloughing and sand sliding of roof of excavated sandy loess tunnel
CN107387095A (en) * 2017-09-20 2017-11-24 中铁十四局集团有限公司 Composite lining structure after the construction method of tunnel-liner back cavity and construction
CN109083658A (en) * 2018-06-27 2018-12-25 昆明理工大学 Using concrete filled steel tube as the Tunnel Second Lining structure and its construction method of skeleton
CN110056371A (en) * 2019-05-28 2019-07-26 长安大学 A kind of tunnel morning strong supporting system and its installation method
CN110259485A (en) * 2019-07-19 2019-09-20 长安大学 A kind of loess tunnel support system and its installation method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105863681A (en) * 2016-06-27 2016-08-17 西北大学 Quick protecting method for sloughing and sand sliding of roof of excavated sandy loess tunnel
CN107387095A (en) * 2017-09-20 2017-11-24 中铁十四局集团有限公司 Composite lining structure after the construction method of tunnel-liner back cavity and construction
CN107387095B (en) * 2017-09-20 2023-11-24 中铁十四局集团有限公司 Construction method of tunnel lining back cavity and composite lining structure after construction
CN109083658A (en) * 2018-06-27 2018-12-25 昆明理工大学 Using concrete filled steel tube as the Tunnel Second Lining structure and its construction method of skeleton
CN110056371A (en) * 2019-05-28 2019-07-26 长安大学 A kind of tunnel morning strong supporting system and its installation method
CN110259485A (en) * 2019-07-19 2019-09-20 长安大学 A kind of loess tunnel support system and its installation method

Similar Documents

Publication Publication Date Title
CN105781574B (en) A kind of tunnel assembled support system and its construction method
CN205532619U (en) Loess tunnel support system
CN106761810B (en) A kind of large-deformation tunnel in soft rock supporting structure system and its construction method
CN106337686B (en) Three layers of subway station canopy structure of rocky stratum tunneling and construction method
CN101737063B (en) Ground fissure tunnel asphalt concrete composite lining and supporting method thereof
CN102536273B (en) 26-meter large-span space one-step forming construction method
CN101603429B (en) Anti-seepage structure of composite lining deformation joints of ground fissure stratum tunnel and construction method thereof
CN104653197A (en) Method for constructing extra-large variable cross section tunnel
CN106050245A (en) Supporting structure for zero distance underneath pass of existing station of rectangular tunnel section and construction method
CN204729099U (en) Rock quality layer tunneling three layers of subway station canopy structure
CN108397206A (en) Arrival method of reseptance under short stabilization zone operating mode in rich water soft soil layer
CN205503146U (en) Novel supporting construction of shallow tunnel suitable for city sensitizing range
CN105781582A (en) Novel shallow-buried tunnel support structure applicable to urban sensitive areas and construction method of novel shallow-buried tunnel support structure applicable to urban sensitive areas
CN103088830A (en) Construction method for composite outer wall structure of ultra-deep basement
CN108561156A (en) Separate tunnel changes arch supporting construction and its construction method
CN103670446B (en) Circular diversion tunnel 2/3 circle concrete-liner construction method
CN107939415A (en) Stay the micro- two step constructions method of Core Soil in the soft plastic clay tunnel of Shallow-buried Large-span
CN202787334U (en) Sealing structure of deep well casing used during tunnel construction
CN108374674B (en) Six pilot tunnels, 12 step Underground Space Excavation method for protecting support
CN105888697A (en) Fault-crossing tunnel deformation coordination type supporting structure and construction method thereof
CN207513604U (en) A kind of novel prefabricated assembled pipe canopy of soft soil tunnel pre-reinforcement
CN101824987A (en) Method for constructing structure for underground tunnel
CN110080798A (en) Sandwich-type steel compound tube piece making method suitable for shield formula TBM
CN208473885U (en) Tunnel Gushing section primary support structure with ribbing
KR102103978B1 (en) Reinforcement and waterproof structure of vertical shafts for utility interface

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160831

Termination date: 20170419

CF01 Termination of patent right due to non-payment of annual fee