CN205530346U - Equipment is assembled in prefabrication of wisdom piping lane - Google Patents

Equipment is assembled in prefabrication of wisdom piping lane Download PDF

Info

Publication number
CN205530346U
CN205530346U CN201620306406.7U CN201620306406U CN205530346U CN 205530346 U CN205530346 U CN 205530346U CN 201620306406 U CN201620306406 U CN 201620306406U CN 205530346 U CN205530346 U CN 205530346U
Authority
CN
China
Prior art keywords
equipment
assembled
connecting plate
arranged above
lifting platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620306406.7U
Other languages
Chinese (zh)
Inventor
任雪松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Qianhai Guanhua Urban Pipe Gallery Intelligent Technology Co Ltd
Original Assignee
Shenzhen Qianhai Guanhua Urban Pipe Gallery Intelligent Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Qianhai Guanhua Urban Pipe Gallery Intelligent Technology Co Ltd filed Critical Shenzhen Qianhai Guanhua Urban Pipe Gallery Intelligent Technology Co Ltd
Priority to CN201620306406.7U priority Critical patent/CN205530346U/en
Application granted granted Critical
Publication of CN205530346U publication Critical patent/CN205530346U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses an equipment is assembled in prefabrication of wisdom piping lane, including assembling equipment base, equipment reducing gear box, promoting connecting plate and material lifting platform, it installs stereoplasm rubber shell to assemble equipment base top, motor control switch installs hydraulic pressure oil pipe way in the top, hydraulic pressure oil pipe just installs the promotion hydraulic pump on the road, it is connected with to promote the hydraulic pump below promote the connecting plate, it installs control circuit board to promote the connecting plate below, control circuit board installs liquid crystal operating panel in the below, liquid crystal operating panel below intercommunication has automatic variator protector, install automatic variator protector top the material lifting platform, material lifting platform top is installed and is assembled the facility switching. Beneficial effect lies in: the equipment volume is less, and the seam adopts automatic extending structure, is formed with the seam and imitates the protection, and the cost of transportation is lower.

Description

A kind of wisdom piping lane precast assembly equipment
Technical field
This utility model relates to plant equipment aspect, particularly relates to a kind of wisdom piping lane precast assembly equipment.
Background technology
The corridor of wisdom piping lane, i.e. pipeline.In chemical industry and associated class factory thereof, a lot of pipelines are brought together, and arrange outside device or Factory Building, are usually aloft, prop up with support, form the appearance similar with corridor.Also there is minority wisdom piping lane located underground.General all in "ON" type.The main place laid concentrated by large-scale plant pipeline, and it is made up of steel construction or the column of reinforced concrete structure, crossbeam and truss, can be divided into single or multiple lift by type, transitable or impassabitity etc..Comprehensive wisdom piping lane (Japan claims " common trench ", Taiwan to claim " Common Ducts "), it is simply that the comprehensive corridor of underground urban duct.I.e. build a tunnel space at Urban Underground, by electric power, communication, the various utilities pipelines such as combustion gas, heat supply, plumbing are integrated in one, it is provided with special access hole, hoisting port and monitoring system, implement unified planning, Uniting, unified construction and management, be important infrastructure and " life line " ensureing city operations.In developed country, common trench has existed for century more than one, and while system is gradually improved, its scale also has increasing trend.Play " city integrated wisdom piping lane engineering legislation " (GB50838-2015) of enforcement on June 1st, 2015, " the city integrated wisdom piping lane engineering legislation " of version in 2012 has been carried out bigger amendment and perfect, the promotion of wisdom piping lane construction comprehensive to China serves positive effect, this edition specification emphasizes that the most all pipelines must enter corridor, but also expand the classification of comprehensive wisdom piping lane, increase cable wisdom piping lane newly.The pre-splicing equipment volume of wisdom piping lane that China uses at present is relatively big, uses whole section of means of transportation transport, and cost of transportation is higher, does not have seam defencive function.
Utility model content
Based on this, it is necessary to for prior art problem, it is provided that a kind of wisdom piping lane precast assembly equipment.
nullFor solving prior art problem,The utility model discloses a kind of wisdom piping lane precast assembly equipment,Including assembled plant bottom case、Equipment reduction box、Promote connecting plate and material lifting platform,Described assembled plant bottom case is arranged above vulcanie housing,Described vulcanie housing is arranged above device drives motor,Described device drives motor is arranged above described equipment reduction box,Described equipment reduction box is provided above motor control switch,Described motor control switch is arranged above hydraulic oil pipeline,Described hydraulic oil pipeline is arranged above promoting hydraulic pump,Connect below described promotion hydraulic pump and have described lifting connecting plate,Below described lifting connecting plate, control circuit plate is installed,Below described control circuit plate, liquid crystal operation panel is installed,Described liquid crystal operation lower panels is communicated with automatic telescopic seam protector,Described automatic telescopic seam protector is arranged above described material lifting platform,Described material lifting platform is arranged above assembled facility switching.
In said structure, assembled equipment is carried out operating control by described liquid crystal operation panel, and described lifting connecting plate pulls described material lifting platform to move, and described hydraulic oil pipeline transport hydraulic oil, described equipment reduction box controls equipment operating rate.
In order to improve assembled equipment work efficiency further, described assembled plant bottom case is connected by bolt with described vulcanie housing, and described device drives motor is connected by bolt with described equipment reduction box.
In order to improve assembled equipment work efficiency further, described motor control switch is arranged on described device drives motor by screw, and described promotion hydraulic pump is connected by bolt with described lifting connecting plate.
In order to improve assembled equipment work efficiency further, described control circuit plate is connected by wire with described liquid crystal operation panel, and described automatic telescopic seam protector is connected by bolt with described material lifting platform.
Having the beneficial effects that: equipment volume is less, seam uses automatic telescopic structure, and abutment joint forms effectively protection, and cost of transportation is relatively low.
Accompanying drawing explanation
Fig. 1 is the front view of a kind of wisdom piping lane precast assembly equipment described in the utility model;
Fig. 2 is the right view of a kind of wisdom piping lane precast assembly equipment described in the utility model.
Description of reference numerals is as follows:
1, assembled plant bottom case;2, vulcanie housing;3, device drives motor;4, equipment reduction box;5, motor control switch;6, hydraulic oil pipeline;7, hydraulic pump is promoted;8, connecting plate is promoted;9, control circuit plate;10, liquid crystal operation panel;11, automatic telescopic seam protector;12, material lifting platform;13, assembled facility switching.
Detailed description of the invention
For the ease of understanding this utility model, below with reference to relevant drawings, this utility model is described more fully.Accompanying drawing gives preferred embodiment of the present utility model.But, this utility model can realize in many different forms, however it is not limited to embodiment described herein.On the contrary, providing the purpose of these embodiments is to make the understanding to disclosure of the present utility model more thorough comprehensively.
It should be noted that be referred to as " being fixed on " another element when element, it can be directly on another element or can also there is element placed in the middle.When an element is considered as " connection " another element, and it can be directly to another element or may be simultaneously present centering elements.Term as used herein " vertical ", " level ", "left", "right" and similar statement are for illustrative purposes only.
Unless otherwise defined, all of technology used herein and scientific terminology are identical with belonging to the implication that those skilled in the art of the present utility model are generally understood that.It is intended merely to describe the purpose of specific embodiment at term used in the description of the present utility model herein, it is not intended that in limiting this utility model.Term as used herein " and/or " include the arbitrary and all of combination of one or more relevant Listed Items.
nullRefer to Fig. 1 to Fig. 2,The utility model discloses a kind of wisdom piping lane precast assembly equipment,Including assembled plant bottom case 1、Equipment reduction box 4、Promote connecting plate 8 and material lifting platform 12,Assembled plant bottom case 1 is arranged above vulcanie housing 2,Vulcanie housing 2 is in order to protect assembled device interior part,Vulcanie housing 2 is arranged above device drives motor 3,Device drives motor 3 is with thinking that assembled equipment work provides power,Device drives motor 3 is arranged above equipment reduction box 4,Reduction box 4 is in order to control assembled equipment operating rate,Equipment reduction box 4 is provided above motor control switch 5,Motor control switch 5 runs in order to control motor,Motor control switch 5 is arranged above hydraulic oil pipeline 6,Hydraulic oil pipeline 6 is in order to transport hydraulic oil,Hydraulic oil pipeline 6 is arranged above promoting hydraulic pump 7,Promote hydraulic pump 7 in order to promote lifting connecting plate motion,Promote to connect below hydraulic pump 7 and have lifting connecting plate 8,Promote connecting plate 8 in order to pull material lifting platform to move,Promote, below connecting plate 8, control circuit plate 9 is installed,Control circuit plate 9 is in order to control assembled each element of equipment,Liquid crystal operation panel 10 is installed below control circuit plate 9,Liquid crystal operation panel 10 is in order to carry out operating control to assembled equipment,Automatic telescopic seam protector 11 it is communicated with below liquid crystal operation panel 10,Automatic telescopic seam protector 11 is protected in order to automatic telescopic abutment joint position,Automatic telescopic seam protector 11 is arranged above material lifting platform 12,Material lifting platform 12 is in order to carry out handling control to assembled equipment,Material lifting platform 12 is arranged above assembled facility switching 13,Assembled facility switching 13 is in order to control the open and close of assembled equipment.
Installation process of the present utility model is as follows: assembled plant bottom case 1 is connected by bolt with vulcanie housing 2; device drives motor 3 is connected by bolt with equipment reduction box 4; motor control switch 5 is arranged on device drives motor 3 by screw; hydraulic pump 7 is promoted to be connected by bolt with promoting connecting plate 8; control circuit plate 9 is connected by wire with liquid crystal operation panel 10, and automatic telescopic seam protector 11 is connected by bolt with material lifting platform 12.
In sum, assembled equipment operating noise is detected by liquid crystal operation panel 10, promotes connecting plate 8 vibrations when assembled equipment work and makes reflection, and hydraulic oil pipeline 6 transports lubricating oil, and equipment reduction box 4 carries out shock detection when assembled equipment work.
Embodiment described above only have expressed several embodiments of the present utility model, and it describes more concrete and detailed, but therefore can not be interpreted as the restriction to this utility model the scope of the claims.It should be pointed out that, for the person of ordinary skill of the art, without departing from the concept of the premise utility, it is also possible to make some deformation and improvement, these broadly fall into protection domain of the present utility model.Therefore, the protection domain of this utility model patent should be as the criterion with claims.

Claims (4)

  1. null1. a wisdom piping lane precast assembly equipment,It is characterized in that: include assembled plant bottom case、Equipment reduction box、Promote connecting plate and material lifting platform,Described assembled plant bottom case is arranged above vulcanie housing,Described vulcanie housing is arranged above device drives motor,Described device drives motor is arranged above described equipment reduction box,Described equipment reduction box is provided above motor control switch,Described motor control switch is arranged above hydraulic oil pipeline,Described hydraulic oil pipeline is arranged above promoting hydraulic pump,Connect below described promotion hydraulic pump and have described lifting connecting plate,Below described lifting connecting plate, control circuit plate is installed,Below described control circuit plate, liquid crystal operation panel is installed,Described liquid crystal operation lower panels is communicated with automatic telescopic seam protector,Described automatic telescopic seam protector is arranged above described material lifting platform,Described material lifting platform is arranged above assembled facility switching.
  2. A kind of wisdom piping lane precast assembly equipment the most according to claim 1, it is characterised in that: described assembled plant bottom case is connected by bolt with described vulcanie housing, and described device drives motor is connected by bolt with described equipment reduction box.
  3. A kind of wisdom piping lane precast assembly equipment the most according to claim 1, it is characterised in that: described motor control switch is arranged on described device drives motor by screw, and described promotion hydraulic pump is connected by bolt with described lifting connecting plate.
  4. A kind of wisdom piping lane precast assembly equipment the most according to claim 1, it is characterised in that: described control circuit plate is connected by wire with described liquid crystal operation panel, and described automatic telescopic seam protector is connected by bolt with described material lifting platform.
CN201620306406.7U 2016-04-13 2016-04-13 Equipment is assembled in prefabrication of wisdom piping lane Expired - Fee Related CN205530346U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620306406.7U CN205530346U (en) 2016-04-13 2016-04-13 Equipment is assembled in prefabrication of wisdom piping lane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620306406.7U CN205530346U (en) 2016-04-13 2016-04-13 Equipment is assembled in prefabrication of wisdom piping lane

Publications (1)

Publication Number Publication Date
CN205530346U true CN205530346U (en) 2016-08-31

Family

ID=56790445

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620306406.7U Expired - Fee Related CN205530346U (en) 2016-04-13 2016-04-13 Equipment is assembled in prefabrication of wisdom piping lane

Country Status (1)

Country Link
CN (1) CN205530346U (en)

Similar Documents

Publication Publication Date Title
CN201475501U (en) Assembling type vertical pipe group support and installation structure with pipe structure
CN105256837A (en) Pipe gallery prefabricated member and assembled comprehensive pipe gallery
CN210424152U (en) Air pipe convenient to install
CN106320370A (en) Underground comprehensive pipe rack system
CN205557584U (en) Steel pipe corridor and large -scale utility tunnel system
CN205530346U (en) Equipment is assembled in prefabrication of wisdom piping lane
CN105544606A (en) Construction method for assembled prefabricated comprehensive pipe rack
CN105569075A (en) Assembled prefabricated comprehensive pipe rack guide positioning device
CN107269940A (en) A kind of many Pipe racks of assembled waterproof
CN103350971A (en) Device for assembling and disassembling construction jumbo in tunnel
CN206429790U (en) A kind of buried gas pipeline branch box
CN205231503U (en) Distribution cabinet
CN205369646U (en) Furred ceiling installation liftable integrated system
CN203656365U (en) Combination-type transition cable leading cage based on cable leading towards lower bridge surface
CN101818558B (en) Industrial factory building pipe shaft and installing method thereof
CN206581296U (en) Multichannel underground pipe gallery with ventilation escape mouth structure
CN207760873U (en) Assembled steel pipe gallery sewage conduct maintenance structure
CN206706828U (en) A kind of corrugated steel pipe gallery variable bit support connection structure
CN205314426U (en) Water, electrical equipment's liftable integrated system is ventilated, is supplied with in furred ceiling installation
CN216892739U (en) Assembled drainage inspection shaft
CN207032294U (en) A kind of two-tube corridor in the underground with cable Rest
CN204572491U (en) A kind of submersible type emergency repair pump
CN205577053U (en) Quick detach lavatory for building portable
CN104319709B (en) A kind of wiring mechanism of convenient alignment
CN211008471U (en) Oil-well rig counter weight base

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160831

Termination date: 20180413