CN205476634U - Integration arch colonnade braced system reach by its integrated arch colonnade that constitutes - Google Patents
Integration arch colonnade braced system reach by its integrated arch colonnade that constitutes Download PDFInfo
- Publication number
- CN205476634U CN205476634U CN201620258175.7U CN201620258175U CN205476634U CN 205476634 U CN205476634 U CN 205476634U CN 201620258175 U CN201620258175 U CN 201620258175U CN 205476634 U CN205476634 U CN 205476634U
- Authority
- CN
- China
- Prior art keywords
- colonnade
- arch
- integration
- supporting construction
- open side
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Residential Or Office Buildings (AREA)
Abstract
The utility model belongs to the building field, concretely relates to integration arch colonnade braced system reach by its integrated arch colonnade that constitutes handsome in appearance, that mechanical properties is stable. This integration arch colonnade braced system includes reinforced concrete structure's colonnade bearing structure body, two at least floors are strideed across to colonnade bearing structure body on the height, be provided with at least one arch door opening and at least one oval door opening on the colonnade bearing structure body, arch door opening and oval door opening are respectively as the door opening of colonnade on the corresponding floor. The utility model provides an arch colonnade braced system can satisfy the bearing requirement of building, can embody architect's molding requirement again, can play fine building supported effects and architectural modeling effect, satisfactory solution the various problems that exist among the prior art.
Description
Technical field
This utility model belongs to building field, is specifically related to a kind of handsome in appearance, integrated arch colonnade support system of mechanics quality stable and the integrated arch colonnade being made up of it.
Background technology
Colonnade is to have corridor post, top cover, Lang Tai or have the building passed through for people of side retaining wall concurrently, such as gallery, claustra etc..There are the following problems for existing colonnade: first, the corridor post of colonnade is usually Dan Li's, it is independent, isolating construction between corridor post adjacent or relative on different floors or in same floor, need individually to bury each corridor post underground when building colonnade, efficiency of construction is low and distance between corridor post deviation easily occurs with relative position, eventually affects the attractive in appearance of colonnade and service life.Second, owing to existing corridor post is single vertical structure, the overall performance of whole colonnade structure is the best, and intensity is the highest, limited load bearing capacities, easily changes be damaged such as sedimentation, crack etc. because of vibrations or ground, brings potential safety hazard to people's life.3rd, existing colonnaded crescent moon door, square door or arched door are usually and corridor rod structure builds respectively, work progress needs the linking collocation considering between colonnade and door opening, thus may have influence on the perfect realization of efficiency of construction and whole architectural design intention.
Utility model content
For the problems referred to above, this utility model provides a kind of beautiful, generous, practical arch colonnade support system, this arch colonnade support system can meet the load-bearing requirements of building, the modeling requirement of architect can be embodied again, can play good building-supporting effect and architectural image effect, satisfactory solves various problems present in prior art.
This utility model is that the technical scheme that its technical problem of solution uses is: a kind ofOneBody arch colonnade support system, it includes that the colonnade supporting construction body of reinforced concrete structure, described colonnade supporting construction body in height cross at least two floor;The arch support structures of at least one arch support post that Open Side Down and the quantity opening upwards consistent with the arch support post that Open Side Down it is provided with on described colonnade supporting construction body;The arch support structures in the vertical direction of the described arch support post that Open Side Down and opening upwards interconnects, alignment, forms arched door hole and oval door opening in its under shed and upper shed;This arched door hole and oval door opening are for respectively forming the door opening of colonnade in respective storey;On described supporting construction body, the position corresponding to floor base plate is provided with the floor installation position for installing floor.
Further, in the integrated arch colonnade support system that this utility model provides, described colonnade supporting construction body in height crosses over two floors;It is provided with three arch support posts that Open Side Down and the arch support structures of three opening upwards on described integration arch colonnade supporting construction body;Arch support post and the arch support structures in the vertical direction of opening upwards that Open Side Down align two-by-two, form three arched door holes and three oval door openings respectively;Arched door hole is for the colonnade of ground floor, and oval door opening is for the colonnade of the second layer.
Further, in the integrated arch colonnade support system that this utility model provides, described colonnade supporting construction body in height crosses over two floors;It is provided with two arch support posts that Open Side Down and the arch support structures of two opening upwards on described integration arch colonnade supporting construction body;Arch support post and the arch support structures in the vertical direction of opening upwards that Open Side Down align two-by-two, form two arched door holes and two oval door openings respectively;Arched door hole is for the colonnade of ground floor, and oval door opening is for the colonnade of the second layer.
Further, in the integrated arch colonnade support system that this utility model provides, between the adjacent arch support post that Open Side Down of described any two and the arch support structures of adjacent with its in the vertical direction two opening upwards, it is additionally provided with petal hole.
Further, in the integrated arch colonnade support system that this utility model provides, the top of described oval door opening is further opened with hole.
Further, in the integrated arch colonnade support system that this utility model provides, described integration arch colonnade supporting construction body thickness throughout is identical.
Another aspect of the present utility model, also discloses a kind of integration arch colonnade, and this integration arch colonnade employs integrated arch colonnade support system described in any of the above-described technical scheme.
The technique effect that this utility model is the most useful:
The arch support structures of this utility model use arch support post that Open Side Down and the opening upwards used of working in coordination with it is as the main bearing member of colonnade, interconnect between each primary structure member, support, the mechanical property of whole building is highly stable, and weight capacity is stronger.And, owing to can form the various door opening moulding such as arched door hole and oval door opening between each main bearing member and construction wall, the integrated arch colonnade support system that this utility model provides also has the features such as modeling effect is abundant, beautiful, generous, practical.
For convenience of to technique scheme and the understanding of technique effect, below in conjunction with specification drawings and specific embodiments, integration arch colonnade support system disclosed in this utility model and the integrated arch colonnade that is made up of it are described in detail.
Accompanying drawing explanation
Fig. 1:The reinforcing bar full-size drawing of this utility model integration arch colonnade support system;
Fig. 2:Figure 1 In A-A Sectional view;
Fig. 3:Figure 1 In B-B Sectional view;
Fig. 4:Figure 1 In C-C Sectional view;
Fig. 5:Figure 1 In D-D Sectional view;
Fig. 6:Figure 1 In E-E Sectional view;
Wherein: the 1-arch support post that Open Side Down;The arch support structures of 2-opening upwards;3-arched door hole;4-ellipse door opening;5-floor installation position;The petal hole of 6-;7-hole;8-concrete walls.
Detailed description of the invention
Seeing Fig. 1, disclose a kind of integration arch colonnade support system in this utility model preferred embodiment, this integration arch colonnade support system crosses over two floors the most altogether, it is adaptable to the construction of colonnade in double-deck building;It includes the colonnade supporting construction body of reinforced concrete structure, and this colonnade supporting construction body is provided with three arch support posts 1 that Open Side Down, interconnects and form three arched door holes 3 in its inner arched between three arch support posts 1;Described three arched door holes 3 are used as the door opening of colonnade during ground floor is built.
The above arch support structures 2 being respectively arranged with the opening upwards aligned with each other with its in the vertical direction of three arch support posts 1 that Open Side Down, arch support structures 2 and its inner arched form the arched door hole 4 of ellipse;The arched door hole 4 of described ellipse is used as the door opening of colonnade during the second layer is built.Being further opened with petal hole 6 between arch support post 1 and arch support structures 2 that any two is adjacent, the top of arch support structures 2 is provided with hole 7.
See Fig. 1, Fig. 3 and Fig. 4, integration arch colonnade support system is separately provided for installing at the floor of two floors the floor installation position 5 of floor.
Seeing Fig. 2-Fig. 5, the thickness throughout of the integrated arch colonnade support system disclosed in preferred embodiment is essentially identical.
The arch support structures 2 of this utility model use arch support post 1 that Open Side Down and the opening upwards used of working in coordination with it is as the main bearing member of colonnade, interconnect between each primary structure member, support, the mechanical property of whole building is highly stable, and weight capacity is stronger.And, owing to can form the various door opening moulding such as arched door hole 3 and oval door opening 4 between each main bearing member (arch support post 1 and arch support structures 2) and construction wall 8, the integrated arch colonnade support system that this utility model provides also has the features such as modeling effect is abundant, beautiful, generous, practical.
Claims (7)
1. one kindOneBody arch colonnade support system, it is characterised in that: this integration arch colonnade support system includes that the colonnade supporting construction body of reinforced concrete structure, described colonnade supporting construction body in height cross at least two floor;The arch support structures (2) of at least one arch support post (1) that Open Side Down and the quantity opening upwards equal with the arch support post (1) that Open Side Down it is provided with on described colonnade supporting construction body;Arch support structures (2) in the vertical direction of the described arch support post (1) that Open Side Down and opening upwards interconnects, alignment, forms arched door hole (3) and oval door opening (4) in its under shed and upper shed;This arched door hole (3) and oval door opening (4) are for respectively forming the door opening of colonnade in respective storey;On described supporting construction body, the position corresponding to floor base plate is provided with the floor installation position (5) for installing floor.
Integration arch colonnade support system the most according to claim 1, it is characterised in that: described colonnade supporting construction body in height crosses over two floors;The arch support structures (2) of three arch support posts (1) that Open Side Down and three opening upwards it is provided with on described integration arch colonnade supporting construction body;Arch support post (1) and arch support structures (2) in the vertical direction of opening upwards that Open Side Down align two-by-two, form three arched door holes (3) and three oval door openings (4) respectively;Arched door hole (3) is for the colonnade of ground floor, and oval door opening (4) is for the colonnade of the second layer.
Integration arch colonnade support system the most according to claim 1, it is characterised in that: described colonnade supporting construction body in height crosses over two floors;The arch support structures (2) of two arch support posts (1) that Open Side Down and two opening upwards it is provided with on described integration arch colonnade supporting construction body;Arch support post (1) and arch support structures (2) in the vertical direction of opening upwards that Open Side Down align two-by-two, form two arched door holes (3) and two oval door openings (4) respectively;Arched door hole (3) is for the colonnade of ground floor, and oval door opening (4) is for the colonnade of the second layer.
4. according to the integrated arch colonnade support system described in Claims 2 or 3, it is characterised in that: it is additionally provided with petal hole (6) between the adjacent arch support post (1) that Open Side Down of described any two and the arch support structures (2) of adjacent with its in the vertical direction two opening upwards.
5. according to the integrated arch colonnade support system described in Claims 2 or 3, it is characterised in that: the top of described oval door opening (4) is further opened with hole (7).
6. according to the integrated arch colonnade support system described in Claims 2 or 3, it is characterised in that: described integration arch colonnade supporting construction body thickness throughout is identical.
7. an integrated arch colonnade, it is characterised in that: this integration arch colonnade employs the integrated arch colonnade support system described in claim any one of claim 1-3.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620258175.7U CN205476634U (en) | 2016-03-31 | 2016-03-31 | Integration arch colonnade braced system reach by its integrated arch colonnade that constitutes |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620258175.7U CN205476634U (en) | 2016-03-31 | 2016-03-31 | Integration arch colonnade braced system reach by its integrated arch colonnade that constitutes |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205476634U true CN205476634U (en) | 2016-08-17 |
Family
ID=56649036
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620258175.7U Expired - Fee Related CN205476634U (en) | 2016-03-31 | 2016-03-31 | Integration arch colonnade braced system reach by its integrated arch colonnade that constitutes |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205476634U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117449646A (en) * | 2023-08-18 | 2024-01-26 | 中铁建工集团有限公司 | No platform post canopy and template system thereof |
-
2016
- 2016-03-31 CN CN201620258175.7U patent/CN205476634U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117449646A (en) * | 2023-08-18 | 2024-01-26 | 中铁建工集团有限公司 | No platform post canopy and template system thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPS62264229A (en) | Ultrahigh building | |
CN204266376U (en) | A kind of liftable floor | |
CN103397695B (en) | The concrete filled steel tube coupled column high-position conjoined structure of two-way steel truss is set | |
CN104712055A (en) | Wooden building based on concrete frameworks and construction method of wooden building | |
CN111088859A (en) | Assembled outer wall structure and mounting method thereof | |
CN205476634U (en) | Integration arch colonnade braced system reach by its integrated arch colonnade that constitutes | |
CN105220792A (en) | A kind of prefabricated concealed bracings energy-consuming shear wall and assemble method thereof | |
SE0701577L (en) | multi-storey | |
CN202831672U (en) | Detachable movable building with outer frame type composite frame structure | |
CN113737936A (en) | Connecting structure and construction method of prefabricated combined duplex balcony | |
WO2009031139A3 (en) | Reinforced load bearing precast concrete wall panels | |
CN109281390B (en) | Assembled concrete truss shear wall building structure | |
CN206916942U (en) | A kind of interior is without load-bearing pillar extra space arch multi-layer construction structure | |
CN202831440U (en) | Precast light plate type stair | |
CN206245831U (en) | A kind of superelevation steel megastructure vibration damping integrated system | |
CN212866534U (en) | Assembled coincide floor | |
CN201605589U (en) | Fixed end | |
CN211313842U (en) | Self-bearing door pocket | |
CN113789926A (en) | Assembled full-prefabricated staircase and assembled staircase building | |
CN207714516U (en) | Prefabricated panel and walling system | |
CN203462575U (en) | Concrete-filled steel tube combination column high-conjoined structure provided with two-way steel trusses | |
CN106760839A (en) | A kind of superelevation steel megastructure vibration damping integrated system | |
CN207003788U (en) | A kind of assembled horizontal hole building block | |
CN202144417U (en) | Novel elevator cab wall structure | |
CN205742983U (en) | A kind of multiplex angle parking stall support template |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160817 Termination date: 20180331 |
|
CF01 | Termination of patent right due to non-payment of annual fee |