Compound snap-in stake barrier wall structure
Technical field
This utility model relates to a kind of compound snap-in stake barrier wall structure.
Background technology
At present, in the design of China's foundation pit stope support and construction, arrangement and method for construction and engineering method is often used to have soil nail wall, campshed, cement-soil gravity type retaining wall, diaphram wall etc..1. soil nail wall: this engineering method construction equipment is simple, and construction method is easy.Soil nailing passes through soil layer ability relatively by force, can prevent subsoil water and the erosion of rainwater and soil erosion, better economy.But the soft formations such as this engineering method, is only applicable to more than level of ground water or through artificial gravelly sand and boulder bed, mud are the most inapplicable, need to take the outer underground space in hole big for soil nailing simultaneously.2. campshed supporting construction method: though it is simple to have construction machinery and technique, adapts to the advantage that the scope of soil layer is wide, but it is high to there is cost, long in time limit, there is additionally required the defect arranging waterproof tent antiseepage.3. cement-soil gravity type retaining wall engineering method: there is construction equipment and simple for process, the reliable advantage of water isolating, but it is big to still suffer from cement consumption, uneconomical, structure takes up room greatly, is normally only applicable to soft soil foundation pit, cutting depth is less than 7M, the shortcoming big on surrounding enviroment impact of constructing.4, diaphram wall engineering method: wall stiffness is big, there is " gear soil " and " water proof " dual function, Supporting Structure deformation is little, but there is spoir and waste mud is many, cement, steel consumption big, cost is high, shortcoming long in time limit, meet powder soil horizon easily causes landslip of the sides of the trench to seep water simultaneously, and wall body and seam crossing are also easily generated infiltration phenomenon.
In a word, above conventional pattern foundation pit supporting structure barrier wall structure, owing to supporting cost is high, the construction period is long, or is limited the factor restrictive function on (level of ground water, neighboring buildings basis and cannot the outer draining of wall etc.) by on-the-spot site condition, it is difficult to meet the requirement designed with construction unit.
Utility model content
It is low that the technical problems to be solved in the utility model is to propose a kind of cost, and the duration is short, energy-saving material, mechanization degree high and safety is high, and has the compound snap-in stake barrier wall structure of the effect of good pattern foundation pit supporting structure.
To this end, compound snap-in stake barrier wall structure of the present utility model, including: some Soil-cement pile bodies;Also include some anchor cable drilling & grouting piling pile bodies, between every two described anchor cable drilling & grouting piling pile bodies, be disposed with at least Soil-cement pile body;Described anchor cable drilling & grouting piling pile body and the described engaged layout of Soil-cement pile body;Described anchor cable drilling & grouting piling pile body includes that capping beam, described capping beam are located at the top of described anchor cable drilling & grouting piling pile body;It is provided with steel reinforcement cage and prestress anchorage cable in described anchor cable drilled press-grouting pile body, wherein, one end of described prestress anchorage cable is fixed on described steel reinforcement cage on one end of the described bottom of described anchor cable drilling & grouting piling pile body, and the other end of described prestress anchorage cable is anchored on described capping beam by anchoring body.
Above-mentioned compound snap-in stake barrier wall structure, also include: anchor pole, described anchor pole one end is fixing with anchor cable drilling & grouting piling pile body to be connected, and the other end is adapted for insertion in the soil body, and described anchor pole coordinates with described anchor cable drilling & grouting piling pile body to stop described anchor cable drilling & grouting piling pile body to be shifted over.
Above-mentioned compound snap-in stake barrier wall structure, described anchor pole is base expanding and base expanding anchor pole, and described base expanding and base expanding anchor support one end in the soil body has radially protruding part.
Above-mentioned compound snap-in stake barrier wall structure, is disposed with three described Soil-cement pile bodies between two described anchor cable drilling & grouting piling pile bodies, wherein, described anchor cable drilling & grouting piling pile body and described cement mixing method body form continuous snap-fit arrangement.
This utility model has the following technical effect that with for prior art
Barrier wall structure the most of the present utility model is by being disposed with at least Soil-cement pile body between every two described anchor cable drilling & grouting piling pile bodies;Described anchor cable drilling & grouting piling pile body and described soil cement stir and block the engaged layout of pile body.For above design, anchor cable drilling & grouting piling pile body primarily serves the effect of block body and dash, and primarily serve sealing effect with the Soil-cement pile body of its snap-fit arrangement, and assist the effect playing gear soil, so, with in prior art with prior art uses two campshed bodies arrange compared with, i.e., one row's concrete drill hole guncreting pile body, one row's cement mixing method body, for same construction environment, the Soil-cement pile body of employing part substitutes used concrete drill hole guncreting pile body, the quantity making relatively costly and baroque concrete drill hole guncreting pile body decreases, structure also becomes relatively easy, thus greatly reduce the engineering time, reduce construction costs.Additionally;Described anchor cable drilling & grouting piling pile body in this utility model includes that capping beam, described capping beam are located at the top of described anchor cable drilling & grouting piling pile body;It is provided with steel reinforcement cage and prestress anchorage cable in described anchor cable drilled press-grouting pile body, wherein, one end of described prestress anchorage cable is fixed on described steel reinforcement cage on one end of the described bottom of described body, and the other end of described prestress anchorage cable is anchored on described capping beam by anchoring body;This structure designs, and by increasing prestress anchorage cable at anchor cable drilling & grouting piling pile body, such that it is able to allow pile body have good anti-floating and resistance to plucking, and then just can play preferably gear soil effect using this anchor cable drilling & grouting piling pile body of lesser amt.
Barrier wall structure the most of the present utility model also includes anchor pole, described anchor pole one end is fixing with anchor cable drilling & grouting piling pile body to be connected, the other end is adapted for insertion in the soil body, described anchor pole coordinates the described anchor cable drilling & grouting piling pile body of prevention to be shifted over described anchor cable drilling & grouting piling pile body, the anchor pole inserted by use is so that anchor cable drilling & grouting piling pile body has preferable flexing resistance, thus is effectively improved the gear soil nature energy that barrier wall structure is overall.
Described anchor pole the most of the present utility model is base expanding and base expanding anchor pole, and described base expanding and base expanding anchor support one end in the soil body has enlarged footing.Anchor pole uses the design with enlarged footing can improve anchor pole pull resistance in soil, thus further increases the gear soil nature energy of this utility model barrier wall structure.
Accompanying drawing explanation
Below in conjunction with Figure of description, embodiment of the present utility model is specifically introduced
Fig. 1 is the structural representation that this utility model is combined snap-in stake barrier wall structure;
Fig. 2 is the structural representation of this utility model anchor cable drilling & grouting piling pile body;
Fig. 3 is the top view of steel reinforcement cage in this utility model anchor cable drilling & grouting piling pile body;
Fig. 4 is the structural representation of the preferred implementation of this utility model anchor cable drilling & grouting piling pile body;
1-Soil-cement pile body;2-anchor cable drilling & grouting piling pile body;3-capping beam;4-steel reinforcement cage;5-prestress anchorage cable;6-anchoring body;7-anchor pole;8-radially protruding part;
Detailed description of the invention
Embodiment 1
As it is shown in figure 1, one of the present utility model is combined snap-in stake barrier wall structure, including: some Soil-cement pile bodies 1;Also include some anchor cable drilling & grouting piling pile bodies 2, between every two described anchor cable drilling & grouting piling pile bodies 2, be disposed with at least Soil-cement pile body 1;Described anchor cable drilling & grouting piling pile body 2 and the described engaged layout of Soil-cement pile body 1;As shown in Figures 2 and 3, described anchor cable drilling & grouting piling pile body 2 includes that capping beam 3, described capping beam 3 are located at the top of described anchor cable drilling & grouting piling pile body 2;It is provided with steel reinforcement cage 4 and prestress anchorage cable 5 in described anchor cable drilling & grouting piling pile body 2, wherein, one end of described prestress anchorage cable 5 is fixed on described steel reinforcement cage 4 on one end of the bottom of described anchor cable drilling & grouting piling pile body 2, and the other end of described prestress anchorage cable 5 is anchored on described capping beam 3 by anchoring body 6.
As one preferred embodiment, as shown in Figure 2, described compound snap-in stake barrier wall structure also includes: anchor pole 7, described anchor pole 7 one end is fixing with anchor cable drilling & grouting piling pile body 2 to be connected, the other end is adapted for insertion in the soil body, and described anchor pole 7 coordinates with described anchor cable drilling & grouting piling pile body 2 to stop described anchor cable drilling & grouting piling pile body 2 to be shifted over.Wherein, described displacement refers to the pile body change that position occurs on its any direction, also includes pile body fracture and change in location that the part pile body that causes occurs.
As another kind of preferred implementation, as shown in Figure 4, described anchor pole 7 is base expanding and base expanding anchor pole, and described base expanding and base expanding anchor support one end in the soil body has radially protruding part 8.
As another kind of preferred implementation, described compound snap-in stake barrier wall structure, wherein, is disposed with three described Soil-cement pile bodies 1 between two described anchor cable drilling & grouting piling pile bodies 2, wherein, described anchor cable drilling & grouting piling pile body 2 forms continuous snap-fit arrangement with described Soil-cement pile body 1.
Obviously, above-described embodiment is only for clearly demonstrating example, and not restriction to embodiment.For those of ordinary skill in the field, can also make other changes in different forms on the basis of the above description.Here without also cannot all of embodiment be given exhaustive.And among the protection domain that the obvious change thus extended out or variation are created still in this utility model.