CN205473862U - Hot -blast furnace coal gas turbocharging system - Google Patents

Hot -blast furnace coal gas turbocharging system Download PDF

Info

Publication number
CN205473862U
CN205473862U CN201620317100.1U CN201620317100U CN205473862U CN 205473862 U CN205473862 U CN 205473862U CN 201620317100 U CN201620317100 U CN 201620317100U CN 205473862 U CN205473862 U CN 205473862U
Authority
CN
China
Prior art keywords
pressure
gas
trt
air stove
valve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201620317100.1U
Other languages
Chinese (zh)
Inventor
王冬雁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huatian Engineering and Technology Corp MCC
Original Assignee
Huatian Engineering and Technology Corp MCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huatian Engineering and Technology Corp MCC filed Critical Huatian Engineering and Technology Corp MCC
Priority to CN201620317100.1U priority Critical patent/CN205473862U/en
Application granted granted Critical
Publication of CN205473862U publication Critical patent/CN205473862U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Blast Furnaces (AREA)

Abstract

The utility model discloses a hot -blast furnace coal gas turbocharging system mainly can not provide the problem of suitable coal gas pressure for the hot -blast furnace to the gaspipe network under the prior art, provided a hot -blast furnace coal gas turbocharging system, include TRT facility export gas piping and hot -blast furnace gas piping with outside coal gas main pipe net intercommunication, TRT facility export gas piping and hot -blast furnace gas piping pass through the by pass line intercommunication, be provided with pressure regulating valve on the TRT export gas piping, set up pressure measuring equipment on the by pass line, pressure regulating valve with the pressure measuring equipment interlocking, wherein, the entry of by pass line with pressure regulating valve sets gradually along TRT export gas piping's airflow direction. The utility model discloses can improve the coal gas pressure of hot -blast furnace to the system is simple, and safe and reliable, strong, the maintenance convenience of commonality can not exert an influence to original facility.

Description

Air stove coal gas pressure charging system
Technical field
This utility model relates to a kind of air stove coal gas pressure charging system.
Background technology
At present, Ironmaking Design must actively carry out the theory of sustainable development and recycling economy, to greatest extent Energy-saving and cost-reducing.Air stove is the big power consumer of steel plant, improves the thermal efficiency of air stove, reduces fuel consumption, Improve hot blast temperature, be the important component part of ironmaking technology.Blast funnace hot blast stove typically utilizes self-produced blast furnace Coal gas does fuel, and consumption accounts for the 40~45% of self produced gas.Reasonably the design of air stove structure, the most excellent Change Regenerator Structure and rational bricking, to save blast furnace gas, are to reduce process energy consumption, establishing resource saving The important means of type enterprise.The commonly used regenerative hot blast stove of air stove, the high temperature produced by gas-fired Checker brick in regenerator are heated by flue gas, then change stove on air by the checker brick heated by cold air heating. In view of heat transfer and accumulation of heat, the structure of current checker brick has the trend become increasingly complex, 5 holes that the past is conventional Or 7 hole checker brick have developed into the cellular checker brick such as hole, 19 holes even 37, to increase changing of heat storage Hot side amass, and the flow velocity that flue gas to be ensured and air blast are in passage at turbulent range to improve the thermal efficiency, but with Together be that air stove coal gas system resistance is greatly increased, gas pressure demand brings up to~15KPa.At present The blast furnace quantity of domestic iron and steel enterprises is typically from several more to tens, and the pressure that coal gas system is incorporated into the power networks is About 10KPa, because the use pressure of most of coal gas users is 6~8KPa, it is impossible to improve whole pipe The operating pressure of net meets the requirement of air stove, thus affects the raising of Blast Temperature.
Utility model content
For the problems referred to above, this utility model provides a kind of system simple, can stablize and be effectively improved hot blast The air stove coal gas pressure charging system of producer gas pressure.
For reaching above-mentioned purpose, this utility model air stove coal gas pressure charging system includes and outside gas main net The TRT facility exit gas piping of connection and air stove gas piping;Described TRT facility exit gas piping Connected by by-pass line with air stove gas piping, described TRT outlet gas piping is provided with pressure and adjusts Joint valve, described by-pass line arranges pressure gauge, and described pressure-regulating valve fills with described pressure measxurement Put interlocking;Wherein, entrance and the described pressure-regulating valve of described by-pass line exports gas piping along TRT Airflow direction sets gradually.
Further, described bypass gas piping upward pressure measurement apparatus uses logic control three to select two.
Further, described air stove gas piping connects with outside gas main, described air stove gas pipe Quick opening valve, described quick opening valve and TRT facility and the shutdown of pressure-regulating valve or fault letter it is provided with on road Number interlocking;Wherein, the outlet of described quick opening valve and described by-pass line is along described air stove gas piping Airflow direction sets gradually.
Further, described TRT facility exit gas piping is additionally provided with in parallel with described pressure-regulating valve Quick opening valve, described quick opening valve and described TRT facility and the shutdown of pressure-regulating valve or fault-signal connection Lock.
Further, the TRT facility exit gas piping in described pressure-regulating valve downstream is provided with outer net pressure Force measuring device.
Further, described pressure-regulating valve is electric press regulation valve, pneumatic pressure-regulating valve or pressure of surging Force regulating valve.
Further, described quck-opening valve is the quick opening valve that surges.
Further, described by-pass line arranges a set of partition apparatus.
Further, the end of described TRT facility exit gas piping is provided with grid-connected isolating valve, described heat Wind furnace gas piping is connected with outside gas main net by air stove partition apparatus.
In this utility model technology, the coal gas of TRT facility exit is through regulator, will be equivalent to 40%~45% Coal gas amount be importing directly into the gas entry of air stove, make the gas pressure of hot blast stove burning higher than outside coal gas The pressure of net, this utility model can stably be effectively improved air stove gas pressure.
Compared with prior art, this utility model technology has the advantage that
This utility model system is simple, highly versatile, safe and reliable, easy to maintenance, will not to other facility Produce impact.It is typically provided with isolating valve, especially before TRT facility exit pipeline is grid-connected with plant area's gas main Be small furnace TRT unit be usually after build, be designed with before the grid-connected front press and open holes of TRT export pipeline every Disconnected valve.Enforcement of the present utility model does not affect the normal supply of other external user.
With the technics comparing of traditional Gas Pressurization Station, the advantage of this utility model each side is especially apparent.By Very big in the consumption of air stove coal gas, account for the 40%~45% of blast furnace gas generating capacity, newly-built Gas Pressurization Station Disposable apparatus investment higher, the equipment operating cost in later stage is the highest, and place, air stove region is the most limited. Especially it is to be noted that: the gas using quantity of air stove is very big, if forcing to bleed from outer net to cause outside Gaspipe network pressure oscillation is relatively big, even makes neighbouring coal gas user paralyse.
This utility model reduced investment, take up an area less, economic benefit obvious, can be effectively improved and stable heating wind furnace Gas pressure, this is the essential condition that Blast Temperature improves.The gas facility that this utility model increases is few, Only just can be met blast furnace by pressure-regulating valve and one by bypass line to air stove after TRT facility hot The pressure requirements that wind furnace is personal.Advocating the today setting up energy-efficient society and Economical Enterprises, this work energetically The benefit that skill is brought is particularly evident.
Accompanying drawing explanation
Fig. 1 is the flow chart of this utility model air stove coal gas pressure charging system;
Detailed description of the invention
Below in conjunction with Figure of description, this utility model is further described.
Embodiment 1
As it is shown in figure 1, what the present embodiment air stove coal gas pressure charging system included connecting with outside gas main net TRT facility exit gas piping 1 and air stove gas piping 2;Described TRT facility exit gas piping and Air stove gas piping is connected by by-pass line 3, described TRT outlet gas piping is provided with pressure and adjusts Joint valve 4, described by-pass line arranges pressure gauge 10, described pressure-regulating valve 4 and described pressure Measurement apparatus 10 is interlocked;Wherein, entrance and the described pressure-regulating valve 4 of described by-pass line 3 goes out along TRT The airflow direction of mouth gas piping sets gradually.
The present embodiment system is simple, highly versatile, safe and reliable, easy to maintenance, other facility will not be produced Raw impact.It is typically provided with isolating valve, especially before TRT facility exit pipeline is grid-connected with plant area's gas main The TRT unit of small furnace is built after being usually, and is designed with cutting off before the grid-connected front press and open holes of TRT export pipeline Valve.The enforcement of the present embodiment does not affect the normal supply of other external user.
With the technics comparing of traditional Gas Pressurization Station, the advantage of the present embodiment each side is especially apparent.Due to The consumption of air stove coal gas is very big, accounts for the 40%~45% of blast furnace gas generating capacity, newly-built Gas Pressurization Station Disposable apparatus investment is higher, and the equipment operating cost in later stage is the highest, and place, air stove region is the most limited. Especially it is to be noted that: the gas using quantity of air stove is very big, if forcing to bleed from outer net to cause outside Gaspipe network pressure oscillation is relatively big, even makes neighbouring coal gas user paralyse.
The present embodiment reduced investment, take up an area less, economic benefit obvious, can be effectively improved and stable heating wind furnace coal Atmospheric pressure, this is the essential condition that Blast Temperature improves.The gas facility that the present embodiment increases is few, the most logical Overvoltage force regulating valve and one just can be met blast funnace hot blast stove by bypass line to air stove after TRT facility Personal pressure requirements.Advocating the today setting up energy-efficient society and Economical Enterprises, this process bands energetically The benefit come is particularly evident.
Embodiment 2
On the basis of above-described embodiment, bypass gas piping upward pressure measurement apparatus 10 described in the present embodiment and adopt Two are selected with logic control three.
Logic control three selects two to be that a point takes three pressure signals feeding PLC, first to 3 pressure measuring values Judging, regulation system is chosen correct pressure measuring value and the aperture of regulation valve is carried out PID regulation, carries High pressure detecting reliability.
Embodiment 3
On the basis of above-described embodiment, as it is shown in figure 1, the present embodiment includes TRT facility exit gas pipe Road 1, air stove gas piping 2 and the bypass gas piping 3 connected between the two.Described TRT exports coal gas Pipeline 1 and air stove gas piping 2 all connect with outside gas main, on TRT outlet gas piping 1 It is provided with along air flow direction with secondary: the bypass entrance of gas piping 3, pressure-regulating valve 4, pressure gauge 5 And grid-connected front isolating valve, 6;Described air stove gas piping 2 is provided with along air flow direction with secondary: coal gas every Disconnected device 7, quck-opening valve 8, the outlet of by-pass line 3 and hot blast stove system gas entry;At described bypass pipe It is provided with along air flow direction with secondary on road 3: bypass gas piping partition apparatus 9, pressure gauge 10 (take Pressure mouth is near air stove).
Pressure-regulating valve 4 on TRT outlet conduit 1 and the gas pressure on bypass gas piping 3 measure dress Putting 10 interlockings, closed loop regulation hot wind supply producer gas pressure is in the numerical value needed~15KPa, described pressure measxurement Device 10 have employed logic control three and selects two, is that a point takes three pressure signals feeding PLC, first to 3 Pressure measuring value judges, regulation system is chosen correct pressure measuring value and the aperture of regulation valve is carried out PID Regulation, improves pressure detecting reliability.
On air stove gas piping, 2 are provided with partition apparatus 7, and the downstream of partition apparatus 7 is provided with quck-opening valve 8, described quick opening valve 8 and TRT facility and the shutdown of pressure-regulating valve 4 or fault-signal interlocking, to ensure The safety of system.
Outer net pressure gauge 5 is utilized to detect the pressure of outside gas main.
Described pressure-regulating valve 4 can be selected for electronic, pneumatically or hydraulically;Described quick opening valve 8 is opened soon for surging Valve, surge valve rapid sensitive, good stability, it is possible to provides TRT facility and hot blast stove system enough Protection.
The present embodiment has taken into full account the links of production run, it is possible to realize air stove gas pressure Automatically detect, control and regulate, and ensure that the operation safety of TRT and air stove.When TRT normally transports During row, being automatically adjusted hot wind supply producer gas pressure by pressure-regulating valve 4 is~15KPa, at this moment quck-opening valve 8 Being closed, during as occurred that the low warning of pressure or pressure height are reported to the police, quck-opening valve 8 interlocking is opened, now Pressure-regulating valve 4 standard-sized sheet also releases interlocking, and manual confirmation puts into operation after fixing a breakdown again;When TRT orderly closedown Or during disorderly closedown, quck-opening valve 8 interlocking is opened, and changes by independent communication in the air stove gas piping 2 of outer net Supply, now pressure-regulating valve 4 is interlocked standard-sized sheet.After TRT application startup optimization is normal, slowly close fast Valve opening 8, simultaneously regulation valve 4 start to be automatically adjusted stable air stove gas pressure for~15KPa;When because of pressure regulation Device frequent movement breaks down, and now quck-opening valve 8 is also interlocked and opened, and air stove is still by air stove gas pipe Road 2 supplies.
In the present embodiment, air stove gaspipe line partition apparatus 7 and bypass line partition apparatus 9 keep normal Open.When hot-blast furnace equipment overhauls, partition apparatus 7 and partition apparatus 9 are all closed;When pressure-regulating valve 4 Because of fault need stop the supple of gas or steam maintenance time, treat TRT planned shut-down and grid-connected isolating valve, 6 and bypass partition apparatus 9 all Can overhaul during closedown.
Embodiment 4
On the basis of above-described embodiment 3, native system can adjust according to on-site actual situations, at technological transformation item In mesh, as installing space in the downstream line of partition apparatus 7 on air stove gas piping 2 is limited, it is impossible to peace During dress quck-opening valve 8, at this moment quck-opening valve 8 can be connected in parallel with pressure-regulating valve 4, is arranged in TRT and exports coal In feed channel 1, quck-opening valve 8 herein is the most scalable for the adjustment type quck-opening valve that surges, and forms two-way regulation system The gas pressure of stable heating wind furnace further.
The present embodiment is as different from Example 3: air stove gas piping partition apparatus 7 keeps the normally off, when When TRT orderly closedown, disorderly closedown and pressure-regulating valve 4 fault, now in parallel with pressure-regulating valve 4 Quck-opening valve 8 interlocking is opened, and continues by bypass gaspipe line supply air stove.
When pressure-regulating valve 4 needs to stop the supple of gas or steam maintenance because of fault, need to wait for TRT planned shut-down and grid-connected partition Valve 6 and bypass partition apparatus 9 can overhaul when all closing, but now air stove gas piping cuts off dress Put 7 before quck-opening valve 8 cuts out manual unlocking, air stove changes and is supplied by air stove gas piping 2.
Above, preferred embodiment the most of the present utility model, but this protection domain is not limited thereto, and appoints How those familiar with the art is in the technical scope that the present embodiment discloses, the change that can readily occur in Change or replace, all should contain within the protection domain of the present embodiment.Therefore, the protection domain of the present embodiment Should be as the criterion with the protection domain that claim is defined.

Claims (9)

1. an air stove coal gas pressure charging system, including the TRT facility exit connected with outside gas main net Gas piping and air stove gas piping;It is characterized in that: described TRT facility exit gas piping and hot blast Producer gas pipeline is connected by by-pass line, and described TRT outlet gas piping is provided with pressure-regulating valve, Arranging pressure gauge on described by-pass line, described pressure-regulating valve is interlocked with described pressure gauge; Wherein, entrance and the described pressure-regulating valve of described by-pass line exports the airflow direction of gas piping along TRT Set gradually.
2. air stove coal gas pressure charging system as claimed in claim 1, it is characterised in that: described bypass gas pipe Road upward pressure measurement apparatus uses logic control three to select two.
3. air stove coal gas pressure charging system as claimed in claim 1, it is characterised in that: described air stove coal gas Pipeline connects with outside gas main, and described air stove gas piping is provided with quick opening valve, described opens soon Valve and TRT facility and the shutdown of pressure-regulating valve or fault-signal interlocking;Wherein, described quick opening valve and The outlet of described by-pass line sets gradually along the airflow direction of described air stove gas piping.
4. air stove coal gas pressure charging system as claimed in claim 1, it is characterised in that: described TRT facility goes out It is additionally provided with the quick opening valve in parallel with described pressure-regulating valve, described quick opening valve and institute on mouth gas piping State TRT facility and the shutdown of pressure-regulating valve or fault-signal interlocking.
5. air stove coal gas pressure charging system as claimed in claim 1, it is characterised in that: described pressure-regulating valve It is provided with outer net pressure gauge on the TRT facility exit gas piping in downstream.
6. air stove coal gas pressure charging system as claimed in claim 1, it is characterised in that: described pressure regulates Valve is electric press regulation valve, pneumatic pressure-regulating valve or hydraulic pressure regulation valve.
7. the air stove coal gas pressure charging system as described in claim 3 or 4, it is characterised in that: described open soon Valve is the quick opening valve that surges.
8. air stove coal gas pressure charging system as claimed in claim 1, it is characterised in that: described by-pass line On a set of partition apparatus is set.
9. air stove coal gas pressure charging system as claimed in claim 1, it is characterised in that: described TRT facility The end of outlet gas piping is provided with grid-connected isolating valve, and described air stove gas piping is cut off by air stove Device connects with outside gas main net.
CN201620317100.1U 2016-04-14 2016-04-14 Hot -blast furnace coal gas turbocharging system Withdrawn - After Issue CN205473862U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620317100.1U CN205473862U (en) 2016-04-14 2016-04-14 Hot -blast furnace coal gas turbocharging system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620317100.1U CN205473862U (en) 2016-04-14 2016-04-14 Hot -blast furnace coal gas turbocharging system

Publications (1)

Publication Number Publication Date
CN205473862U true CN205473862U (en) 2016-08-17

Family

ID=56641053

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620317100.1U Withdrawn - After Issue CN205473862U (en) 2016-04-14 2016-04-14 Hot -blast furnace coal gas turbocharging system

Country Status (1)

Country Link
CN (1) CN205473862U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105671233A (en) * 2016-04-14 2016-06-15 中冶华天工程技术有限公司 Coal gas pressurizing system of hot-blast heater
CN109340580A (en) * 2018-10-24 2019-02-15 宣城亚邦化工有限公司 Coal gas superpressure safe release system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105671233A (en) * 2016-04-14 2016-06-15 中冶华天工程技术有限公司 Coal gas pressurizing system of hot-blast heater
CN109340580A (en) * 2018-10-24 2019-02-15 宣城亚邦化工有限公司 Coal gas superpressure safe release system
CN109340580B (en) * 2018-10-24 2020-09-04 宣城亚邦化工有限公司 Coal gas overpressure safety release system

Similar Documents

Publication Publication Date Title
CN104043375B (en) The mixing apparatus of high-pressure natural gas and low-pressure gas and mixed method
CN103047670B (en) Direct blowing type double-inlet and double-outlet steel ball grinding energy conservation optimization system and method thereof
CN104197324B (en) Fluidized-bed combustion boiler burning optimization adjustment control method and device
CN107314395B (en) The method of fast cutback under unit style generating set emergency situation
CN205473862U (en) Hot -blast furnace coal gas turbocharging system
CN112760439B (en) Undisturbed furnace change control method for hot blast furnace
CN103924021A (en) Blast furnace and hot blast stove constant-pressure changing system and method thereof
CN109439830A (en) It is a kind of to change furnace system applied to metallurgical blast funnace hot blast stove pressure stabilizing
CN104712904B (en) LNG meets an urgent need feeder
CN106051820B (en) A kind of pressurization igniting device and method
CN202521629U (en) Natural gas three-level pressure regulating device of shuttle kiln
CN104232823A (en) Control method for furnace exchange of hot air furnace under constant pressure
CN104498058A (en) Pressure balance control method for coke oven gas collector
CN204806439U (en) Urea pyrolysis high temperature air heat exchanger in denitration flow
CN104344414B (en) Waste heat recovery device and waste heat recovery method
CN105253889B (en) A kind of polycrystalline silicon production system and method
CN219526556U (en) BGL gasifier nitrogen gas feed system
CN203718744U (en) Flue gas waste heat recovery exhaust gas temperature control system
CN201778043U (en) Coal gas blowing device of blast furnace
CN105671233B (en) Hot blast producer gas pressure charging system
CN201331085Y (en) Independent adjusting device of gas and combustion-supporting air for burner nozzle of annular sleeve kiln
CN102588994B (en) Boiler-gas mixed-combustion gas supply pipe and gas supply method
CN214536192U (en) Waste incineration power plant furnace cooling system
CN107289426A (en) Header system boiler vapour system
CN103277197B (en) Gas turbine generating set low-calorific-value combustion control method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20160817

Effective date of abandoning: 20170609