CN205444021U - Novel integral type lift post - Google Patents

Novel integral type lift post Download PDF

Info

Publication number
CN205444021U
CN205444021U CN201620157394.6U CN201620157394U CN205444021U CN 205444021 U CN205444021 U CN 205444021U CN 201620157394 U CN201620157394 U CN 201620157394U CN 205444021 U CN205444021 U CN 205444021U
Authority
CN
China
Prior art keywords
flange
shaft
track
buried bucket
provided above
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620157394.6U
Other languages
Chinese (zh)
Inventor
徐细龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
XIAMEN JIETIAN TECHNOLOGY CO LTD
Original Assignee
XIAMEN JIETIAN TECHNOLOGY CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by XIAMEN JIETIAN TECHNOLOGY CO LTD filed Critical XIAMEN JIETIAN TECHNOLOGY CO LTD
Priority to CN201620157394.6U priority Critical patent/CN205444021U/en
Application granted granted Critical
Publication of CN205444021U publication Critical patent/CN205444021U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model discloses a novel integral type lift post, including shaft apron, ground panel, spacing nylon ring, LED lamp area, stainless steel shaft, shaft advance flange, adjusting sleeve hole, track, hydraulic pressure elevating gear, motor flange, pre -buried bucket flange, pre -buried barrel and drainage flange, pre -buried bucket top is provided with pre -buried bucket flange, the inside nested motor flange that is provided with of pre -buried bucket, motor flange top is provided with hydraulic pressure elevating gear. The utility model discloses simple structure, convenient operation adopts the spiral, pegs graft and constructs, disassembles the convenience, and the after -sales service cost is extremely low, after adopting the grafting structure, not only system stability is not influenced, can also disassemble in a flexible way, the convenient maintenance, is more convenient for through the loosening track of screwing adjustment cylinder center, kill many birds with one stone, the track top does not have the welding structure, pegs graft in spacing nylon ring through hole.

Description

A kind of novel integrated lifting column
Technical field
This utility model relates to lifting column field, is specifically related to a kind of novel integrated lifting column.
Background technology
Existing integral type lifting column many employings welding structure, production cost is high, installation bothers after sale;Top of the rail being welded on corrosion resistant plate, this structure installation bothers, disassembles after sale difficulty height;Mostly using 2,3 tracks, cylinder rocks, and impact resistant capability is poor;The most but produce little effect increasing in terms of cylinder stability, or use complicated hardware to force to remain stable, otherwise cylinder of leaving rock not as;Mostly motor flange is to be suspended in pre-buried bucket, and impact resistant capability is poor, and system can be sayed without globality.
Utility model content
The technical problems to be solved in the utility model is to provide a kind of simple in construction, safe and convenient to use, the novel integrated lifting column of good looking appearance.
nullFor solving the problems referred to above,This utility model adopts the following technical scheme that a kind of novel integrated lifting column,Including shaft cover plate、Floor panel、Spacing nylon ring、LED、Rustless steel shaft、Shaft traveling flange、Regulating sleeve hole、Track、Hydraulic lift、Motor flange、Pre-buried bucket flange、Pre-buried bucket and drainage flange,Described pre-buried bucket is provided above pre-buried bucket flange,Described pre-buried bucket nested inside is provided with motor flange,Described motor flange is provided above hydraulic lift,It is provided with track on described motor flange,Described track is cooperated with shaft traveling flange by regulating sleeve hole and is connected,Described shaft traveling flange is provided above rustless steel shaft,It is arranged with spacing nylon ring on described rustless steel shaft,Described spacing nylon ring is provided above floor panel,Described rustless steel shaft top is provided with shaft cover plate,Described pre-buried bottom of the barrel is provided with drainage flange,Fixing bolt it is provided with bottom described motor flange,Described drainage flange is provided above fixing nut,Described motor flange is cooperated with drainage flange by fixing bolt and fixing nut and is connected,It is provided with string holes and osculum on described pre-buried bucket sidewall.
As preferably, described rustless steel shaft is moved up and down in orbit by shaft traveling flange.
As preferably, described rustless steel shaft is provided above 3M reflection plaster and LED.
As preferably, described track is provided with 4, and described track is provided above tendon Bovis seu Bubali rod.
This utility model simple in construction, easy to operate, use spiral, grafting structure, disassemble conveniently, after-sales service cost is extremely low;Using after connected structure, not only system stability is unaffected, moreover it is possible to disassembles flexibly, maintain easily, and is more convenient for unscrewing track by screwing, adjusts cylinder center, achieve many things at one stroke;Top of the rail welding constructs, and is plugged in spacing nylon ring through hole;Special 4 tracks of lifting column, strengthen structural stability, increase cylinder minibus;Portion's tendon Bovis seu Bubali bar construction in orbit, neither increases lifting column cost, does not affects the appearance, can solve again cylinder and rock problem;Between motor flange and pre-buried bucket drainage flange, increase bolt structure, both can guarantee that systematic entirety, and made again road stake when being clashed into, can be difficult to practical with dissolving collision force.
Accompanying drawing explanation
In order to be illustrated more clearly that this utility model embodiment or technical scheme of the prior art, the accompanying drawing used required in embodiment or description of the prior art will be briefly described below, apparently, accompanying drawing in describing below is only embodiments more of the present utility model, for those of ordinary skill in the art, on the premise of not paying creative work, it is also possible to obtain other accompanying drawing according to these accompanying drawings;
Fig. 1 is structural representation of the present utility model;
Fig. 2 is embodiment schematic diagram of the present utility model.
Detailed description of the invention
Below in conjunction with the accompanying drawings preferred embodiment of the present utility model is described in detail, so that advantage of the present utility model and feature can be easier to be readily appreciated by one skilled in the art, thus protection domain of the present utility model is made apparent clear and definite defining.
nullRefering to shown in Fig. 1-2,A kind of novel integrated lifting column,Including shaft cover plate 1、Floor panel 2、Spacing nylon ring 3、LED 4、Rustless steel shaft 5、Shaft traveling flange 6、Regulating sleeve hole 7、Track 8、Hydraulic lift 9、Motor flange 10、Pre-buried bucket flange 12、Pre-buried bucket 13 and drainage flange 15,Described pre-buried bucket 13 is provided above pre-buried bucket flange 12,Described pre-buried bucket 13 nested inside is provided with motor flange 10,Described motor flange 10 is provided above hydraulic lift 9,It is provided with track 8 on described motor flange 10,Described track 8 is cooperated with shaft traveling flange 6 by regulating sleeve hole 7 and is connected,Described shaft traveling flange 6 is provided above rustless steel shaft 5,Spacing nylon ring 3 it is arranged with on described rustless steel shaft 5,Described spacing nylon ring 3 is provided above floor panel 2,Described rustless steel shaft 5 top is provided with shaft cover plate 1,It is provided with drainage flange 15 bottom described pre-buried bucket 13,Fixing bolt 11 it is provided with bottom described motor flange 10,Described drainage flange 15 is provided above fixing nut 16,Described motor flange 10 is cooperated with drainage flange 15 by fixing bolt 11 and fixing nut 16 and is connected,It is provided with string holes 14 and osculum 17 on described pre-buried bucket 13 sidewall.
It should be noted that described rustless steel shaft 5 is moved up and down on track 8 by shaft traveling flange 6.
It should be noted that described rustless steel shaft 5 is provided above 3M reflection plaster and LED 4.
It should be noted that described track 8 is provided with 4, described track 8 is provided above tendon Bovis seu Bubali rod.
Additionally, this utility model detailed description of the invention, including control room 20, ground level 29, sandstone bed course 25, concrete 28, hydraulic power unit 22, oil cylinder 24, expansion link 23 and lifting column 26, control room 20 is connected with the hydraulic power unit 22 of underground by arranging power line 21 in pvc pipe 27, sandstone bed course 25 is set below ground level 29, described sandstone bed course 25 is provided above concrete 28, pre-buried bucket is set in concrete 28, in pre-buried bucket, hydraulic power unit is set, is provided above oil cylinder connection expansion link at hydraulic power unit and cooperates with lifting column and be connected.
The standardized element that this utility model uses all can be commercially, shaped piece all can carry out customized according to the record with accompanying drawing of description, the concrete connected mode of each part all uses in prior art the conventional meanses such as ripe bolt, rivet, welding, machinery, part and equipment all use in prior art, conventional model, it is connected by prior art the connected mode of routine plus circuit, is not described in detail in this.
Of the present utility model ultimate principle and principal character and of the present utility model advantage have more than been shown and described.Skilled person will appreciate that of the industry; this utility model is not restricted to the described embodiments; described in above-described embodiment and description, principle of the present utility model is simply described; on the premise of without departing from this utility model spirit and scope; this utility model also has various changes and modifications, in the range of these changes and improvements both fall within claimed this utility model.This utility model claims scope and is defined by appending claims and equivalent thereof.

Claims (4)

  1. null1. a novel integrated lifting column,It is characterized in that: include shaft cover plate (1)、Floor panel (2)、Spacing nylon ring (3)、LED (4)、Rustless steel shaft (5)、Shaft traveling flange (6)、Regulating sleeve hole (7)、Track (8)、Hydraulic lift (9)、Motor flange (10)、Pre-buried bucket flange (12)、Pre-buried bucket (13) and drainage flange (15),Described pre-buried bucket (13) is provided above pre-buried bucket flange (12),Described pre-buried bucket (13) nested inside is provided with motor flange (10),Described motor flange (10) is provided above hydraulic lift (9),Track (8) it is provided with on described motor flange (10),Described track (8) is cooperated with shaft traveling flange (6) by regulating sleeve hole (7) and is connected,Described shaft traveling flange (6) is provided above rustless steel shaft (5),It is arranged with spacing nylon ring (3) on described rustless steel shaft (5),Described spacing nylon ring (3) is provided above floor panel (2),Described rustless steel shaft (5) top is provided with shaft cover plate (1),Described pre-buried bucket (13) bottom is provided with drainage flange (15),Described motor flange (10) bottom is provided with fixing bolt (11),Described drainage flange (15) is provided above fixing nut (16),Described motor flange (10) is cooperated with drainage flange (15) by fixing bolt (11) and fixing nut (16) and is connected,It is provided with string holes (14) and osculum (17) on described pre-buried bucket (13) sidewall.
  2. The novel integrated lifting column of one the most according to claim 1, it is characterised in that: described rustless steel shaft (5) is moved up and down on track (8) by shaft traveling flange (6).
  3. The novel integrated lifting column of one the most according to claim 1, it is characterised in that: described rustless steel shaft (5) is provided above 3M reflection plaster and LED (4).
  4. The novel integrated lifting column of one the most according to claim 1, it is characterised in that: described track (8) is provided with 4, and described track (8) is provided above tendon Bovis seu Bubali rod.
CN201620157394.6U 2016-03-02 2016-03-02 Novel integral type lift post Active CN205444021U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620157394.6U CN205444021U (en) 2016-03-02 2016-03-02 Novel integral type lift post

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620157394.6U CN205444021U (en) 2016-03-02 2016-03-02 Novel integral type lift post

Publications (1)

Publication Number Publication Date
CN205444021U true CN205444021U (en) 2016-08-10

Family

ID=56604777

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620157394.6U Active CN205444021U (en) 2016-03-02 2016-03-02 Novel integral type lift post

Country Status (1)

Country Link
CN (1) CN205444021U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108008682A (en) * 2017-12-01 2018-05-08 广州赞加信息科技有限公司 A kind of automatic measure control management equipment
CN111962421A (en) * 2020-07-31 2020-11-20 余长江 Integrated stainless steel lifting road pile group convenient to maintain and replace and construction process thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108008682A (en) * 2017-12-01 2018-05-08 广州赞加信息科技有限公司 A kind of automatic measure control management equipment
CN111962421A (en) * 2020-07-31 2020-11-20 余长江 Integrated stainless steel lifting road pile group convenient to maintain and replace and construction process thereof

Similar Documents

Publication Publication Date Title
CN205444021U (en) Novel integral type lift post
CN205955377U (en) A rail guard for building engineering
CN103993849A (en) Wellhead stabilizer
CN205348194U (en) It spouts compound supporting construction of stake with anchor rope soon to throw to one side to prop
CN202391451U (en) Mineral floor type integrated outburst-proof air door interlocking device
CN209411647U (en) A kind of hanger that underground piping is temporarily relocated
CN205475258U (en) Housing construction basis deep basal pit excavation construction protection structure
CN204825725U (en) Variable wave form guardrail
CN204311982U (en) The machine integrated rig of the tower tower in side
CN204238622U (en) A kind of anti-climbing high voltage transmission line tower
CN207193754U (en) A kind of urban road and bridge on highway maintenance Hanging Basket
CN109537921A (en) A kind of construction anti-falling bracket
CN109098736A (en) A kind of tunnel support device that stability is high
CN209585110U (en) Mixture of piles and concrete wall assembled piping lane with drainage arrangement
CN204059415U (en) A kind of fall arrest inspection shaft
CN207862779U (en) One road and bridge protective device
CN208652301U (en) A kind of tunnel pavement illumination device
CN207524347U (en) A kind of oil truck operation at top protective device
CN207093108U (en) Gob side entry retaining crosses cutting eye supporting facility
CN207047847U (en) One kind building pile driving equipment
CN202125297U (en) Wellhead fence device
CN206111111U (en) Drilling machine
CN206829182U (en) A kind of Combined formwork support system
CN206288820U (en) The mounting structure of the wall-attached frame of building hoist
CN109626232A (en) A kind of hanger and its assemble method that underground piping is temporarily relocated

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant