CN205277499U - Monitoring instrument for heaving floor of coal mine tunnel - Google Patents

Monitoring instrument for heaving floor of coal mine tunnel Download PDF

Info

Publication number
CN205277499U
CN205277499U CN201620016766.3U CN201620016766U CN205277499U CN 205277499 U CN205277499 U CN 205277499U CN 201620016766 U CN201620016766 U CN 201620016766U CN 205277499 U CN205277499 U CN 205277499U
Authority
CN
China
Prior art keywords
steel wire
coal mine
fixed
rope
retaining plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620016766.3U
Other languages
Chinese (zh)
Inventor
马东东
张宁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui University of Science and Technology
Original Assignee
Anhui University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui University of Science and Technology filed Critical Anhui University of Science and Technology
Priority to CN201620016766.3U priority Critical patent/CN205277499U/en
Application granted granted Critical
Publication of CN205277499U publication Critical patent/CN205277499U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

The utility model discloses a monitoring instrument for heaving floor of coal mine tunnel, include: fixed mounting is carving the scale in the fixed plate of tunnel bottom on the fixed plate left side, the fixed plate top is passed through the rope and is moved the union coupling, moves intraductal have be used for moving the soft rope that the pipe changed, soft rope is connected with the steel wire in the fixed plate exit, the steel casing pipe is installed in income drilling department to the steel wire, the steel wire terminal is fixed on carving the device that appears, carves the device that appears and is fixed in drilling department. When the top of roadway bottom plate with two when helping the rock mass produce to warp, the shape device is carved in the extrusion makes the steel wire in steel casing pipe effect rebound down, removes intraductal soft rope and slides along the pulley, makes to remove the pipe and take place to move down, and change numerical value is read out to the scale on on the left of the fixed plate.

Description

A kind of coal mine roadway pucking Monitoring equipment
Technical field
The utility model relates to a kind of coal mine roadway pucking Monitoring equipment.
Background technology
The instrument that current home and abroad colliery tunnel pucking is measured is numerous, the monitoring mostly concentrating on the machinery to tunnel pucking can not convert displacement amount to and carry out in directly observation, measuring owing to the restriction of various factors makes monitoring can not reach level of automation tunnel pucking simultaneously.
Deep mining is turned to gradually along with to coal mining, tunnel pucking problem day by day becomes serious, drastically influence the normal production of the normal production in tunnel and working face, coal production is had great significance by the deformation mechanism therefore studying tunnel pucking, and more and more building field with "nine squares", efficient colliery for China has higher practical value.
Practical novel content
This practical object is to provide a kind of coal mine roadway pucking Monitoring equipment, it is possible to the change of monitoring tunnel pucking.
Stating object for reaching above, the technical solution of the utility model is:
It is fixedly installed in the retaining plate bottom tunnel, scale is carved on the left of retaining plate, retaining plate top is connected with movable pipe by rope, the soft matter rope for movable pipe changes is had in movable pipe, soft matter rope is connected with steel wire in retaining plate exit, steel wire is provided with Steel Sleeve entering drill hole, and steel wire terminal is fixed on the device of falling wedge, and the device of falling wedge is fixed on drill hole.
Compared with the prior art, the beneficial effects of the utility model are:
The utility model discloses a kind of coal mine roadway pucking Monitoring equipment, size it is carved with on the left of retaining plate, movable pipe is connected to the top of retaining plate by rope, in movable pipe, soft matter rope is cemented on cross bar apparatus structure also through movable pipe middle pulley, soft matter rope is connected with steel wire in the exit of retaining plate, enter drill hole at steel wire and it is fixed with Steel Sleeve, steel wire terminal is fixed on the device of falling wedge, when tunnel roof and floor and two helps rock mass to produce distortion and produce displacement in tunnel, the extruding device of falling wedge makes the steel wire steel wire that moves up move up along Steel Sleeve, in movable pipe, soft matter rope slides along pulley, movable pipe is moved down, change numerical value is read according to the scale on the left of retaining plate, demonstrate the running parameter of tunnel pucking, through data preparation analysis, different geologic conditions can be drawn, lithological change situation.
Accompanying drawing explanation
Fig. 1 is the utility model coal mine roadway pucking Monitoring equipment structural representation;
Fig. 2 is movable pipe structural representation in the utility model coal mine roadway pucking Monitoring equipment;
Fig. 3 is cross bar device schematic diagram in the utility model coal mine roadway pucking Monitoring equipment;
Fig. 4 is size enlarged diagram in the utility model coal mine roadway pucking Monitoring equipment.
1 device of falling wedge in figure; 2 steel wires; 3 Steel Sleeves; 4 soft matter ropes; 5 lower sheave combinations; 6 top sheaves; 7 cross bar devices; 8 movable pipes; 9 ropes; 10 retaining plates; 11 retaining plate scales.
Embodiment
Below in conjunction with accompanying drawing, the utility model is described in detail.
Shown in figure 1 and Fig. 2, the utility model discloses a kind of coal mine roadway pucking Monitoring equipment, movable pipe is connected to by rope the top of retaining plate, in movable pipe, soft matter rope is fixed on pulley also to pass the pulley in movable pipe, it is connected with cross bar device at top end stay cord, cross bar device supports movable pipe, and steel wire is fixed on borehole bottom through the Steel Sleeve being fixed on drill hole with the device of falling wedge, connects soft matter rope and steel wire.
When tunnel roof and floor and two helps rock mass to produce distortion, the terrestrial stress extruding device of falling wedge that distortion produces, making the device of falling wedge drive steel wire to be moved, steel wire moves up under the effect of Steel Sleeve, and the junction of steel wire and soft matter rope becomes absent-mindedness, soft matter rope will slide along pulley, movable pipe is moved down, according to the scale on the left of retaining plate, reads the parameter value of change, through data preparation analysis, it is possible to draw different geologic conditions, lithological change situation.
On Steel Sleeve, casting cement makes it the movement of steel wire to be had an impact, and the plank that can scribe elected as by retaining plate, and movable pipe elects the iron pipe of certain mass as, and retaining plate is placed in vertical position and is fixed wtih.

Claims (6)

1. a coal mine roadway pucking Monitoring equipment, it is characterized in that: be fixedly installed in the retaining plate bottom tunnel, scale is carved on the left of retaining plate, retaining plate top is connected with movable pipe by rope, having in movable pipe for the soft matter rope that movable pipe changes, soft matter rope is connected with steel wire in retaining plate exit, and steel wire is provided with Steel Sleeve entering drill hole, steel wire terminal is fixed on the device of falling wedge, and the device of falling wedge is fixed on drill hole.
2. coal mine roadway pucking Monitoring equipment according to claim 1, it is characterised in that, pulley is installed in movable pipe, soft matter rope is walked around pulley and is produced pulling force.
3. coal mine roadway pucking Monitoring equipment according to claim 1, it is characterised in that, retaining plate has movable cross bar apparatus structure by rope and movable pipe junction, for supporting movable pipe.
4. coal mine roadway pucking Monitoring equipment according to claim 1, it is characterised in that, steel wire is provided with Steel Sleeve entering drill hole, and steel wire tube is fixed on tunnel drill hole.
5. coal mine roadway pucking Monitoring equipment according to claim 1, it is characterised in that, the device of falling wedge is the anchorage head of hangnail tube pile structure, and is fixed on bore portion.
6. coal mine roadway pucking Monitoring equipment according to claim 1, it is characterised in that, to carve scale on the left of retaining plate be 1 millimeter is unit of length, be 0.5 millimeter at Special Areas is unit of length.
CN201620016766.3U 2016-01-05 2016-01-05 Monitoring instrument for heaving floor of coal mine tunnel Expired - Fee Related CN205277499U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620016766.3U CN205277499U (en) 2016-01-05 2016-01-05 Monitoring instrument for heaving floor of coal mine tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620016766.3U CN205277499U (en) 2016-01-05 2016-01-05 Monitoring instrument for heaving floor of coal mine tunnel

Publications (1)

Publication Number Publication Date
CN205277499U true CN205277499U (en) 2016-06-01

Family

ID=56062082

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620016766.3U Expired - Fee Related CN205277499U (en) 2016-01-05 2016-01-05 Monitoring instrument for heaving floor of coal mine tunnel

Country Status (1)

Country Link
CN (1) CN205277499U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107643063A (en) * 2017-10-19 2018-01-30 安徽理工大学 A kind of noiseless automonitor of lane surface displacement
CN107893655A (en) * 2017-11-21 2018-04-10 贵州大学 One kind drilling deformation monitoring device and monitoring method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107643063A (en) * 2017-10-19 2018-01-30 安徽理工大学 A kind of noiseless automonitor of lane surface displacement
CN107893655A (en) * 2017-11-21 2018-04-10 贵州大学 One kind drilling deformation monitoring device and monitoring method

Similar Documents

Publication Publication Date Title
CN111456723B (en) One-hole dual-purpose method for overburden three-zone detection and rock stratum movement monitoring
CN205277499U (en) Monitoring instrument for heaving floor of coal mine tunnel
CN206367981U (en) It is a kind of to facilitate the hanging beam mechanism that separating component is lifted in shield auger
CN203550930U (en) Slope deep displacement measuring device
CN103291210B (en) Gate-type double-tower gear-driven drilling machine
CN203687823U (en) Mining telescopic measuring rod
CN203672374U (en) Sag-free hydrometric cableway
CN205823149U (en) A kind of portable all-hydraulic engineering investigation rig
CN205242467U (en) Foundation pit deformation monitoring device
CN214793886U (en) Geological survey device of fetching earth
CN205117224U (en) Well rig crane
CN213627564U (en) Auxiliary moving device for drilling radar antenna
CN202925545U (en) Guide sleeve special for steel reinforcement cage
CN109632167B (en) Device and method for monitoring rock mass stress in open pit goaf
CN201296633Y (en) Device for moving entire petroleum gas-drilling rig with small displacement
CN220378198U (en) Rock drilling device for measuring drilling depth by using sensor
CN108361026B (en) Drilling measuring device
CN106050125A (en) Portable full hydraulic engineering investigation drilling rig
CN207315220U (en) A kind of sampling and testing drilling machine for railway engineering survey and construction
CN216142781U (en) Coal mine roof rock stratum deformation monitoring device
CN205713953U (en) A kind of building Special drill machine
CN218150781U (en) Telescopic tower device of well drilling machine
CN214943984U (en) Small-bore drilling equipment that groundwater hydrology research used
CN210375762U (en) Coal geological drilling sampling device
CN204627456U (en) Borer drill rod hanging apparatus

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160601