CN205276850U - Scaffold for building and protect connection structure outward - Google Patents

Scaffold for building and protect connection structure outward Download PDF

Info

Publication number
CN205276850U
CN205276850U CN201521126018.2U CN201521126018U CN205276850U CN 205276850 U CN205276850 U CN 205276850U CN 201521126018 U CN201521126018 U CN 201521126018U CN 205276850 U CN205276850 U CN 205276850U
Authority
CN
China
Prior art keywords
steel pipe
scaffold
utility
model
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201521126018.2U
Other languages
Chinese (zh)
Inventor
单晓曙
曹江云
龚小东
涂晓
傅宇航
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongtian Northwest Construction Investment Group Co Ltd
Original Assignee
Zhongtian Northwest Construction Investment Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongtian Northwest Construction Investment Group Co Ltd filed Critical Zhongtian Northwest Construction Investment Group Co Ltd
Priority to CN201521126018.2U priority Critical patent/CN205276850U/en
Application granted granted Critical
Publication of CN205276850U publication Critical patent/CN205276850U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to a building protection technical field specifically discloses a scaffold for building and protect connection structure outward, which comprises a bracket, support both sides welding has and is used for stretching out the board with the scaffold steel pipe is connected, stretch out the board and a steel sheet passes through bolted connection, a steel sheet and a pipe welding, the other end of steel pipe passes through fastener and scaffold steel pipe fastening connection. The utility model has the advantages that, when the installation, the steel pipe passes through fastener interconnect with the scaffold steel pipe, connects reliably firmly, prevents to use for a long time the problem of protector landing, the other end of steel pipe through the bolt with stretch out the board and be connected, quick detachable, easy to assemble.

Description

A kind of scaffold for building and outer protection attachment structure
Technical field
This utility model relates to construction safety technical field, particularly relates to a kind of scaffold for building and outer protection attachment structure.
Background technology
In the preventer of building field; protection network is generally used for various construction site by prior art; particularly skyscraper; can whole enclosed construction; the person can be effectively prevented, the fall injury of object, inflammable; reduce noise contamination by dust; reach civilized construction, protect environment, the effect of beautifying city; traditional construction scene generally uses tightrope and is woven into soft protection network and protects; but this protection network matter is soft yielding, inflammable, when weight drops also through soft protection network; protection effect is limited, and outward appearance is unsightly.
Utility model content
The purpose of this utility model is to provide a kind of scaffold for building and outer protection attachment structure, connects reliable, convenient installation, good looking appearance.
To achieve these goals, this utility model have employed following technical scheme: a kind of scaffold for building and outer protection attachment structure, and including support, described support both sides are welded with stretches out plate for what be connected with scaffolding steel pipe; Described stretching out plate and a steel plate is bolted, described steel plate and a steel-pipe welding, the other end of described steel pipe is fastenedly connected by fastener and scaffolding steel pipe.
The beneficial effects of the utility model are in that: when mounted, and steel pipe and scaffolding steel pipe are connected with each other by fastener, this connected mode robust, it is prevented that the long-time problem using preventer landing; The other end of steel pipe is connected with stretching out plate by bolt, quick detachable, convenient installation; Preventer adopts expanded metal lath to instead of traditional soft protection network, optimizes protection effect, and be easily installed, difficult deformation, protection effect is good, resistance to does not persistently fire, good looking appearance.
Accompanying drawing explanation
In order to be illustrated more clearly that this utility model embodiment technical scheme, below the accompanying drawing used required during embodiment is described is briefly described, apparently, accompanying drawing in the following describes is only that this utility model is in order to be illustrated more clearly that this utility model embodiment or technical scheme of the prior art, below the accompanying drawing used required in p-embodiment or description of the prior art is briefly described, for those of ordinary skill in the art, under the premise not paying creative work, it is also possible to obtain other accompanying drawing according to these accompanying drawings.
Fig. 1 is structural representation of the present utility model;
Fig. 2 is the close-up schematic view stretching out plate and scaffolding steel pipe junction of the present utility model.
Detailed description of the invention
Below in conjunction with the accompanying drawing in this utility model embodiment, the technical scheme in this utility model embodiment is clearly and completely described, it is clear that described embodiment is only a part of embodiment of this utility model, rather than whole embodiments. Based on the embodiment in this utility model, the every other embodiment that those of ordinary skill in the art obtain under not making creative work premise, broadly fall into the scope of this utility model protection.
One scaffold for building as shown in Figure 1 and outer protection attachment structure, including support 2, described support 2 both sides are welded with stretches out plate 4 for what be connected with scaffolding steel pipe 6.
Described stretching out plate 4 and a steel plate is bolted, described steel plate and a steel pipe 5 weld, and the other end of described steel pipe 5 is fastenedly connected by fastener 7 and scaffolding steel pipe 6.
When mounted, expanded metal lath 1 Os Draconis 3 are fixed, form protection aspect, again by support 2 fixed protection aspect, being fixed by fastener 7 with scaffolding steel pipe 6 by steel pipe 5, it is connected with each other by fastener 7, this connected mode robust, it is prevented that the long-time problem using preventer landing. The other end of steel pipe 5 welds a block plate, and steel plate is connected with stretching out plate 4 by bolt, quick detachable, convenient installation.
The foregoing is only preferred embodiment of the present utility model; not in order to limit this utility model; all within spirit of the present utility model and principle, any amendment of making, equivalent replacement, improvement etc., should be included within protection domain of the present utility model.

Claims (1)

1. a scaffold for building and outer protection attachment structure, it is characterised in that: including support (2), described support (2) both sides are welded with stretches out plate (4) for what be connected with scaffolding steel pipe (6);
The described plate (4) that stretches out is bolted with a steel plate, and described steel plate and a steel pipe (5) weld, and the other end of described steel pipe (5) is fastenedly connected by fastener (7) and scaffolding steel pipe (6).
CN201521126018.2U 2015-12-29 2015-12-29 Scaffold for building and protect connection structure outward Expired - Fee Related CN205276850U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201521126018.2U CN205276850U (en) 2015-12-29 2015-12-29 Scaffold for building and protect connection structure outward

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201521126018.2U CN205276850U (en) 2015-12-29 2015-12-29 Scaffold for building and protect connection structure outward

Publications (1)

Publication Number Publication Date
CN205276850U true CN205276850U (en) 2016-06-01

Family

ID=56061434

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201521126018.2U Expired - Fee Related CN205276850U (en) 2015-12-29 2015-12-29 Scaffold for building and protect connection structure outward

Country Status (1)

Country Link
CN (1) CN205276850U (en)

Similar Documents

Publication Publication Date Title
CN205012627U (en) Assembly type structure outer wall protects stores pylon outward
CN206987412U (en) A kind of building curtain wall construction anti-fall device
CN204960269U (en) Integral pylon
CN201687251U (en) Anti-climbing net structure of truss iron tower
CN204627010U (en) A kind of outer guard net being applicable to climbing frame
CN203639011U (en) Safety climbing channel for sized tower crane for building engineering
CN204752026U (en) Tower crane escape way
CN205276847U (en) Safety device is assisted to scaffold
CN205276850U (en) Scaffold for building and protect connection structure outward
CN204326483U (en) A kind of construction safety scaffold
CN205742975U (en) A kind of direct plugging type scaffold
CN201835457U (en) Turning joint for staircase handrail
CN204609338U (en) External protection device of scaffold for building
CN203201164U (en) Tool type guard bar for construction site
CN209195056U (en) A kind of construction special protecting equipment
CN211143706U (en) Protective net clip
CN201635414U (en) Floor edge safety protection device
CN206530074U (en) A kind of building safety protection network
AU2012100959A4 (en) An innovative acoustic barrier
CN204703544U (en) A kind of safe and practical high rise elevator well construction guard system
CN202990447U (en) Constructional engineering tool type stair guard railing
CN205677221U (en) Concrete in marine environment attachment clears up portable frame apparatus
CN204199728U (en) Highrise building regularization horizontal protective device
CN203452369U (en) Tool type safeguard
CN205875685U (en) T steel scaffold frame pivot system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160601

Termination date: 20161229