CN205243474U CN201520945572.7U CN201520945572U CN205243474U CN 205243474 U CN205243474 U CN 205243474U CN 201520945572 U CN201520945572 U CN 201520945572U CN 205243474 U CN205243474 U CN 205243474U
Authority
CN
China
Prior art keywords
well
sleeve pipe
accumulator
target
oil gas
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520945572.7U
Other languages
Chinese (zh)
Inventor
闫丽丽
李敢
顾小勇
刘承杰
赵智玮
李娜
王桂英
吕芳蕾
朱瑛辉
吕玮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Petroleum and Chemical Corp
Sinopec Research Institute of Petroleum Engineering Shengli Co
Original Assignee
China Petroleum and Chemical Corp
Sinopec Research Institute of Petroleum Engineering Shengli Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Petroleum and Chemical Corp, Sinopec Research Institute of Petroleum Engineering Shengli Co filed Critical China Petroleum and Chemical Corp
Priority to CN201520945572.7U priority Critical patent/CN205243474U/en
Application granted granted Critical
Publication of CN205243474U publication Critical patent/CN205243474U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Other Liquid Machine Or Engine Such As Wave Power Use (AREA)

Abstract

The utility model discloses an oil gas well electricity generation energy storage equipment, including orientation plane butt joint well, target well, sleeve pipe, accumulator, orientation plane butt joint well includes vertical section, deflecting section and horizontal segment in proper order, horizontal segment and target shaft bottom portion butt joint intercommunication form the whole well that generates electricity, are equipped with the sleeve pipe in the whole well that generates electricity, piezoelectric vibrator is installed to the sheathed tube inner wall, the accumulator lies in the outer ground of well and is connected with the sleeve pipe electricity. Connect a power manager between sleeve pipe in the target well and the accumulator, a real -time supervision device is still connected to the accumulator, monitors the electric energy storage condition. The target well adopts the combination of different hole diameters and is equipped with the sleeve pipe in different footpaths, the piston of packing into respectively in the sleeve pipe in difference footpath, series generator and steam turbine in proper order between the sleeve pipe in power manager and different footpaths. The utility model discloses reduce electric energy energy storage development cost, realize abandonment resource reuse, vitalize assets, improve investment efficiency return rate.

Description

Oil gas water well generating energy-storage device
Technical field
The utility model relates to the electric energy development technique of abandoned well, specifically oil gas water well generating energy-storage device.
Background technology
At present, the supply of CNPC's resource is very in short supply, and international oil price drops sharply or continued downturn in long-time, rightEconomic development and the people's lives of China are exerted heavy pressures on. Meanwhile, Chinese and even many oil fields in the world moistureRate has met or exceeded 90%, and these oil fields have not been traditional oil fields strictly, but " paddy field ". AsThe economic benefit what improves these oil fields is a very important problem. A large amount of uses of fossil energy cause global atmosphereThe concentration of middle carbon dioxide constantly raises, and greenhouse effects constantly aggravate, and how makes human residential environment be subject to serious threatAddressing this problem is the significant challenge facing at present. In addition, oil field is autophage substantial oil in process of production,Oil company is main energy supplier (oil and natural gas), is also big power consumer.
Following world energy sources general layout is still unintelligible, but from worldwide trend, to controlling wanting of energy consumption and environmental pollutionAsking will be more and more stricter. The proportion that utilizes of new forms of energy still can be increasing in the long run, and this also gives in oil price dropThe oil consumption country benefiting sounds the alarm, and does not expand simply the scale of traditional mode of production pattern, and loosens economic structureAdjustment and the exploitation to new energy technology.
Wind-powered electricity generation, the intrinsic intermittent problems of solar electrical energy generation self are this heels of Ah noise made in coughing or vomiting's coloured glaze of new forms of energy development. Along with new energyThe continuation of source generating scale expands, and it is more urgent that this problem seems. Energy storage more than needed is got up, with energy peak periodDischarging, is to solve the intermittent emphasis of new forms of energy again.
Utility model content
The purpose of this utility model is to provide oil gas water well generating energy-storage device, can greatly reduce electric energy accumulation of energy and be developed toThis, realize waste resource recycling, vitalizes assets, improves efficiency of investment return rate.
In order to reach above-mentioned purpose, the utility model has adopted following technical scheme, oil gas water well generating energy-storage device, bagDraw together directed horizontal butt shaft, target well, sleeve pipe, accumulator, the horizontal butt shaft of described orientation comprises successively vertical section, makesTiltedly section and horizontal segment, described horizontal segment and target bottom are docked and connected, and form entirety generating well, in entirety generating wellSleeve pipe is housed, and the inwall of described sleeve pipe is provided with piezoelectric vibrator, and described accumulator is positioned at the outer ground of well and is electrically connected with sleeve pipe.
Between sleeve pipe in described target well and accumulator, connect a power supervisor, described accumulator also connects a realityTime monitoring device, monitoring electric energy storage situation.
Described target well adopts different hole diameters to combine and be equipped with the sleeve pipe of Different Diameter, in the sleeve pipe of Different Diameter, is respectively charged into workPlug, series generator and steam turbine successively between described power supervisor and the sleeve pipe of Different Diameter.
The well head of the horizontal butt shaft of described orientation and target well is installed fluid drive apparatus.
While carrying fluid, sleeve pipe is carried out to anticorrosion, scale control treatments.
Compared to prior art, the utlity model has following beneficial effect:
Basis of the present utility model is that petroleum industry also adopts drilling well and cased hole completion mode containing in underground oil, skySo out, these wells can become abandoned oil gas-water well into electric energy exploitation new way to the resource exploitation such as gas, but these wells in the pastNew purposes has been ignored by people due to the boundary of industry, utilizes these wells for reducing energy storage equipment development cost, realizesWaste resource recycling, vitalizes assets, and the return rate of increasing investment returns is all helpful, obviously saves investment, economic effectBenefit significantly.
Selecting to meet in geology, technique close down well, the abandoned well of power-generation energy-storage exploitation condition slightly does technological transformation and can becomeThe new tool that accumulation of energy utilizes, for saving investment, developing oil exploitation industry new growth engines, realizes scientific and technological progressMeaning very great.
All kinds ofly close down, leave unused, discarded produce oil gas-water well is distributed in each corner in oil field, manyly can turn waste into wealth,Use for reference for the exploitation of other new forms of energy provide thinking, by this project implementation, changed original fire coal, fuel oil,The system general layout of combustion gas power supply, has reduced management, charges for disposing pollutants use, has saved fuel cost, reaches energy efficiency, efficiencyThe object of multiplication.
Brief description of the drawings
Fig. 1 is the structural representation of oil gas water well generating energy-storage device the first embodiment of the present utility model;
Fig. 2 is the structural representation of oil gas water well generating energy-storage device the second embodiment of the present utility model;
Fig. 3 is the structural representation of the third embodiment of oil gas water well generating energy-storage device of the present utility model.
Detailed description of the invention
Relevant detailed description of the present utility model and technology contents, coordinate brief description of the drawings as follows, but accompanying drawing only provides referenceWith the use of explanation, be not used for the utility model to be limited.
Shown in Fig. 1-3, oil gas water well generating energy-storage device, comprise directed horizontal butt shaft, target well, sleeve pipe 3,Accumulator 5, the horizontal butt shaft of described orientation comprises vertical section, inclination section and horizontal segment, described horizontal segment and target well successivelyBottom is docked and connected, and forms entirety generating well, in entirety generating well, sleeve pipe is housed, and the inwall of described sleeve pipe is provided with pressureElectric tachometer indicator 9, described accumulator 5 is positioned at the outer ground of well and is electrically connected with sleeve pipe. Sleeve pipe in described target well and accumulator itBetween connect a power supervisor 4, described accumulator also connects a real-time monitoring device 6, monitoring electric energy storage situation.
Described target well adopts different hole diameters to combine and be equipped with the sleeve pipe of Different Diameter, in the sleeve pipe of Different Diameter, is respectively charged into workPlug 10, series generator 12 and steam turbine 11 successively between described power supervisor and the sleeve pipe of Different Diameter. Described orientationThe well head of horizontal butt shaft and target well is installed fluid drive apparatus. While carrying fluid, sleeve pipe is carried out to anticorrosion, scale control treatments.
Embodiment 1: as shown in Figure 1, ground 1, fluid 2, sleeve pipe 3, power supervisor 4, accumulator 5, real-timeMonitoring device 6, plugged zone 7, former oil-gas Layer or water layer 8, piezoelectric vibrator 9.
The steps include:
(1) calculate under the prerequisite meeting the demands at accumulation of energy energy, as former well depth can not reach depth requirements, drilling well addsDeeply, as former well depth reaches requirement, can directly carry out following steps;
(2) adopt physics or the former oil recovery of the eternal shutoff of chemical method, gas production, position, water harvesting layer, i.e. former oil-gas Layer or water layer 8;
(3) utilize the directed horizontal butt shaft of a bite in suitable distance, directed horizontal butt shaft comprise successively vertical section,Inclination section and horizontal segment, described horizontal segment and target bottom are docked and connected. Or utilize another horizontal orientation well, levelThe horizontal segment of directional well adopts other stratum renovation techniques and each targets such as fracturing technique while arriving target area, target well shaft bottomBottom is docked and connected;
(4) the good sleeve pipe 3 with piezoelectric vibrator 9 homenergic conversion equipments of pretreatment under different well sections place;
(5) use physics, chemical method thoroughly to clean foreign-matter contamination in well, pit shaft is processed;
(6), according to the requirement of user's energy consumption, can carry out above-mentioned operation to individual well or grid-connected cluster well, to meet different usingThe demand at family;
(7) in well, inject fluid 2, a large amount of gravitional force and the mechanical energy that in process fluid flow, produce turn by energyChanging device 9 produces electric energy, and electric energy becomes the output of regular electric energy through power supervisor 4 and deposits in accumulator 5 and make for peopleWith, and monitor energy storage situation by real-time monitoring device 6.
Wherein, be not limited to the dielectric materials such as water, solution, air by the fluid of pit shaft, piezoelectric vibrator homenergic conversion dressThe installation of putting and arrangement are also not only confined in embodiment of the present utility model.
Ground matched process technology: carry when fluid pipeline corrosion protection, scale control treatments; As electrical power storage amount does not reach userWhen requirement, can adopt other mode makeup energy such as ground thermal cycle.
Embodiment 2:
As shown in Figure 2, ground 1, fluid 2, sleeve pipe 3, power supervisor 4, accumulator 5, real-time monitoring device 6,Plugged zone 7, former oil-gas Layer or water layer 8, piezoelectric vibrator 9, piston 10, steam turbine 11, generator 12.
Concrete grammar implementation step is as follows:
(1) calculate under the prerequisite meeting the demands at accumulation of energy energy, as former well depth can not reach depth requirements, drilling well addsDeeply, as former well depth reaches requirement, can directly carry out following steps;
(2) adopt physics or the former oil recovery of the eternal shutoff of chemical method, gas production, position, water harvesting layer, i.e. former oil-gas Layer or water layer 8;
(3) utilize the directed horizontal butt shaft of a bite in suitable distance, directed horizontal butt shaft comprise successively vertical section,Inclination section and horizontal segment, described horizontal segment and each target bottom are docked and connected. Or utilize another horizontal orientation well,When the horizontal segment of horizontal orientation well arrives target area, target well shaft bottom and target bottom be docked and connected;
(4) the good sleeve pipe 3 with piezoelectric vibrator 9 homenergic conversion equipments of pretreatment under different well sections place;
(5), according to the requirement of user's energy consumption, can carry out above-mentioned operation to individual well or grid-connected cluster well, to meet different usingThe demand at family;
(6) in well, inject fluid 2, a large amount of gravitional force and the mechanical energy that in process fluid flow, produce turn by energyChanging device produces electric energy, and electric energy becomes the output of regular electric energy through power supervisor 3, and to deposit in accumulator 4 for people to use.
(7) according to the combination of different hole diameters, while utilizing fluid from small-well-diameter pit shaft pump to large footpath well shaft, in the well of large footpathPiston 10 moves, and pushing turbine 11 actings make generator 12 ladder generatings.
(8) converge simultaneously and utilize electric energy that piezoelectric vibrator produces to become the output of regular electric energy through power supervisor 4 to depositFor producing and life, and monitor energy storage situation by real-time monitoring device 6 in accumulator 5.
Ground matched process technology: ground steam turbine power generation working system, electrical power storage system; Carry when fluid pipelineAnticorrosion, scale control treatments; As electrical power storage amount does not reach user while requiring, can adopt other modes such as ground thermal cycle to supplement energyAmount.
Other are the same.
Embodiment 3:
As shown in Figure 3, ground 1, fluid 2, sleeve pipe 3, power supervisor 4, accumulator 5, real-time monitoring device 6,Plugged zone 7, former oil-gas Layer or water layer 8, piezoelectric vibrator 9, piston 10, steam turbine 11, generator 12, subsidy 13,Window sidetracking 14; Deepened section 15, horizontal Butt Section 16.
Concrete grammar implementation step is as follows:
(1) damaged, be out of shape as former well completion casing 3, can carry out casing swage, subsidy 13, or window sidetracking 14,As former well depth can not reach depth requirements, drilling well is deepened to deepened section 15, as former well depth reaches requirement, can directly enterRow following steps;
(2) adopt physics or the former oil-gas Layer of the eternal shutoff of chemical method or water layer 8;
(3) utilize the directed horizontal butt shaft of a bite in suitable distance, directed horizontal butt shaft comprise successively vertical section,Inclination section and horizontal segment, described horizontal segment and target bottom are docked and connected. Or utilize another horizontal orientation well, levelWhen the horizontal segment of directional well arrives target area, target shaft bottom and target bottom be docked and connected;
(4) 16 times pretreatment of deepened section 15 and horizontal Butt Section good with piezoelectric vibrator 9 homenergic conversion equipmentsSleeve pipe 3;
(5), according to the requirement of user's energy consumption, can carry out above-mentioned operation to individual well or grid-connected cluster well, to meet different usingThe demand at family;
(6) in well, inject fluid 2, a large amount of gravitional force and the mechanical energy that in flow process, produce fill by power conversionThe raw electric energy of buying property,
(7) according to the variation of different hole diameters, while utilizing fluid 2 from small-well-diameter pit shaft pump to large footpath well shaft, large footpath wellMiddle piston 10 moves, and pushing turbine 11 actings are generated electricity generator 12.
(8) converge simultaneously and utilize electric energy that piezoelectric vibrator produces to become the output of regular electric energy through power supervisor 4 to depositFor producing and life, and monitor energy storage situation by real-time monitoring device 6 in accumulator 5.
Ground matched process technology: ground steam turbine power generation working system, electrical power storage system; Carry when fluid pipelineAnticorrosion, scale control treatments; As electrical power storage amount does not reach user while requiring, can adopt other modes such as ground thermal cycle to supplement energyAmount.
Above different embodiment may be used alone, can also be used in combination.
The foregoing is only preferred embodiment of the present utility model, non-in order to limit the scope of the claims of the present utility model, otherUse the equivalence of patent spirit of the present utility model to change, all should all belong to the scope of the claims of the present utility model.

Claims (5)

1. oil gas water well generating energy-storage device, comprise directed horizontal butt shaft, target well, sleeve pipe, accumulator, the horizontal butt shaft of described orientation comprises vertical section, inclination section and horizontal segment successively, described horizontal segment and target bottom are docked and connected, form entirety generating well, in entirety generating well, sleeve pipe is housed, the inwall of described sleeve pipe is provided with piezoelectric vibrator, and described accumulator is positioned at the outer ground of well and is electrically connected with sleeve pipe.
2. oil gas water well generating energy-storage device according to claim 1, is characterized in that, connects a power supervisor between the sleeve pipe in described target well and accumulator, and described accumulator also connects a real-time monitoring device, monitoring electric energy storage situation.
3. oil gas water well generating energy-storage device according to claim 2, it is characterized in that, described target well adopts different hole diameters to combine and be equipped with the sleeve pipe of Different Diameter, in the sleeve pipe of Different Diameter, be respectively charged into piston, series generator and steam turbine successively between described power supervisor and the sleeve pipe of Different Diameter.
4. oil gas water well generating energy-storage device according to claim 1, is characterized in that, the well head of the horizontal butt shaft of described orientation and target well is installed fluid drive apparatus.
5. oil gas water well generating energy-storage device according to claim 4, is characterized in that, while carrying fluid, sleeve pipe is carried out to anticorrosion, scale control treatments.
CN201520945572.7U 2015-11-24 2015-11-24 Oil gas well electricity generation energy storage equipment Expired - Fee Related CN205243474U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520945572.7U CN205243474U (en) 2015-11-24 2015-11-24 Oil gas well electricity generation energy storage equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520945572.7U CN205243474U (en) 2015-11-24 2015-11-24 Oil gas well electricity generation energy storage equipment

Publications (1)

Publication Number Publication Date
CN205243474U true CN205243474U (en) 2016-05-18

Family

ID=55942554

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520945572.7U Expired - Fee Related CN205243474U (en) 2015-11-24 2015-11-24 Oil gas well electricity generation energy storage equipment

Country Status (1)

Country Link
CN (1) CN205243474U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106761565A (en) * 2015-11-24 2017-05-31 中国石油化工股份有限公司 Oil gas water well generating energy-storage device and method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106761565A (en) * 2015-11-24 2017-05-31 中国石油化工股份有限公司 Oil gas water well generating energy-storage device and method
CN106761565B (en) * 2015-11-24 2024-03-01 中国石油化工股份有限公司 Oil-gas-water well power generation energy storage device and method

Similar Documents

Publication Publication Date Title
Tanaka et al. Tomakomai CCS demonstration project of Japan, CO2 injection in process
CN105041271B (en) A kind of buck exploiting ocean natural gas hydrates method and sub-sea production systems
US8677752B2 (en) Power generation system
CN101666286B (en) System for integrally exploiting marine energy resource
CN106437497B (en) Hydraulic pressure demolition fracturing builds the hot dry rock method that manually heat is stored up
WO2012137068A3 (en) Mobile, modular, electrically powered system for use in fracturing underground formations
US20210024290A1 (en) System and method for compressed air energy storage
US20160108752A1 (en) Kinetic energy transfer system and methods
CN105422055A (en) System and method for collaborative development of natural gas, water-soluble gas and natural gas hydrate
Sullivan et al. Life-cycle analysis results for geothermal systems in comparison to other power systems: Part II.
CN205243474U (en) Oil gas well electricity generation energy storage equipment
Frank et al. Life cycle analysis of geothermal power generation with supercritical carbon dioxide
Kim et al. Probabilistic decline curve analysis for forecasting estimated ultimate recovery in shale gas play
SODIKI et al. Solar-powered groundwater pumping systems for Nigerian water sheds
CN106761565A (en) Oil gas water well generating energy-storage device and method
Chenari et al. Wave energy systems: An overview of different wave energy converters and recommendation for future improvements
Khan et al. The Geysers geothermal field, an injection success story
CN1071836C (en) Matching technique for changing production well into geothermal exploitation well
CN101662242A (en) Power supply device of solar photovoltaic generating system applied on land oil production machine
CN114016975A (en) Wind power generation method related to exploiting seabed surface exposed combustible ice mineral deposit methane generation device
CN102913403A (en) New process for utilization and energy transformation of deep geothermal resources
CN108533231B (en) Methane generation generating device for seabed combustible ice mineral deposit fragments
CN201479054U (en) Power supply device applied to onshore oil production machine of solar photovoltaic power generation system
CN215979339U (en) Hot dry rock fracturing scanning integrated device
CN204402446U (en) A kind of underground petroleum quarrying apparatus based on solar power source

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160518

Termination date: 20191124

CF01 Termination of patent right due to non-payment of annual fee