CN205187721U - Oil drilling derrick crouches and adorns spooling gear - Google Patents

Oil drilling derrick crouches and adorns spooling gear Download PDF

Info

Publication number
CN205187721U
CN205187721U CN201520993413.4U CN201520993413U CN205187721U CN 205187721 U CN205187721 U CN 205187721U CN 201520993413 U CN201520993413 U CN 201520993413U CN 205187721 U CN205187721 U CN 205187721U
Authority
CN
China
Prior art keywords
rope
crown sheave
wire rope
winding jib
comb
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520993413.4U
Other languages
Chinese (zh)
Inventor
朱波
曹常青
闫玉涛
魏相强
韩鑫宝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Lanzhou LS Group Co Ltd
Original Assignee
Lanzhou LS Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Lanzhou LS Group Co Ltd filed Critical Lanzhou LS Group Co Ltd
Priority to CN201520993413.4U priority Critical patent/CN205187721U/en
Application granted granted Critical
Publication of CN205187721U publication Critical patent/CN205187721U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Jib Cranes (AREA)

Abstract

The utility model relates to a petroleum equipment auxiliary machinery technical field discloses an oil drilling derrick crouches and adorns spooling gear, and this device is installed between crown sheave group and tourist bus assembly pulley, the below of crown sheave group is equipped with overhead traveling crane rest base board, respectively installs a comb -shaped rope winding jib on overhead traveling crane rest base board and crown sheave group pulley edge two the tangent sides, and the rope winding jib includes a set of broach and bottom plate, and the one end of broach is fixed on the bottom plate, and the other end of broach is fixed on overhead traveling crane rest base board. The utility model discloses an use of rope winding jib puts in order messenger, wire rope in the wire rope handling hole of the rope winding jib with the crown sheave is organized, the tourist bus assembly pulley is corresponding, and messenger, wire rope just can not take place the phenomenon of disorder cable rope woolding, have shortened the wire rope handling time, have improved wire rope handling efficiency, and labour saving and time saving has reduced the operation degree of difficulty, the potential safety hazard that has probably appeared when having avoided reason rope operation again.

Description

Oil-well rig boring tower sleeping dress rope guide
Technical field
The utility model relates to oil equipment accessory machinery technical field, specifically a kind of oil-well rig boring tower sleeping dress rope guide that can promote rotary line wire rope handling efficiency.
Background technology
The derrick of oil-well rig is after sleeping installing into, and rotary line is coiled between crown sheave group and tourist bus assembly pulley by one of topmost work exactly successively.Because rotary line is comparatively thick comparatively hard, needing when wire rope handling operation to tie up with thinner messenger the wire rope handling work first carrying out assembly pulley in the end of steel rope, after messenger wire rope handling completes, then by pulling messenger, steel rope being in place.When connecting rope, the assembly pulley of overhead traveling crane and tourist bus is distant, and messenger is comparatively thin longer and naturally droop by gravity, there will be mutual intersection, very easily the phenomenon of generation disorder cable rope woolding between messenger.Once there is the phenomenon of disorder cable rope woolding, just need to re-start reason rope, wire rope handling, snarly messenger is untied new building of laying equal stress on around on corresponding pulley.Waste time and energy, add the work difficulty of operating personnel.
Utility model content
The purpose of this utility model is to provide a kind of oil-well rig boring tower sleeping dress rope guide, with solve drilling derrick sleeping install into wear between rear crown sheave group and tourist bus assembly pulley around messenger, steel rope time easily there is disorder cable rope woolding phenomenon, the problem that wire rope handling operation is wasted time and energy.
For solving the problem, technical solution adopted in the utility model is:
A kind of oil-well rig boring tower sleeping dress rope guide, this device is arranged between crown sheave group and tourist bus assembly pulley, the below of described crown sheave group is provided with a day frame panel, it frame panel and tangent two sides of crown sheave group pulley edge are respectively provided with the rope winding jib of a pectination, rope winding jib comprises one group of comb and base plate, one end of comb is fixed on base plate, and the other end of comb is fixed on day frame panel, is partitioned into several eyelet hole between sky frame panel and base plate by comb.
Further improve as of the present utility model, the distance between adjacent two described comb is identical with the distance between two pulley grooves adjacent in described crown sheave group.
The utility model is when wire rope handling operation, and the one end at steel rope first tied up by messenger by operating personnel, then messenger is passed crown sheave, successively by the corresponding eyelet hole of rope winding jib, then penetrates corresponding tourist bus pulley; After deriving from tourist bus pulley, first by the corresponding eyelet hole of pectination rope winding jib, then be coiled on the corresponding pulley of overhead traveling crane, tractive messenger, penetrates steel rope in crown sheave and tourist bus pulley, completes the wire rope handling operation of steel cable.
The utility model is by the use of rope winding jib, messenger, steel rope are put in order between the comb of the corresponding rope winding jib of crown sheave group, tourist bus assembly pulley, the phenomenon of disorder cable rope woolding would not be there is in messenger, steel rope, shorten the wire rope handling time, improve wire rope handling efficiency, time saving and energy saving, reduce task difficulty; The potential safety hazard that may occur when avoiding reason rope operation again.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model;
Fig. 2 is lateral plan of the present utility model in Fig. 1;
Fig. 3 is the structural representation of rope winding jib in Fig. 1;
Fig. 4 is using state figure of the present utility model;
In figure: 1, crown sheave group, 2, rope winding jib, 3, sky frame panel, 4, messenger, 5, tourist bus assembly pulley, 6, comb, 7, base plate.
Detailed description of the invention
Below in conjunction with accompanying drawing, the utility model is described in further detail.
The sleeping dress of a kind of oil-well rig boring tower as shown in Figures 1 to 4 rope guide, this device is arranged between crown sheave group 1 and tourist bus assembly pulley 5, the below of crown sheave group 1 is provided with day frame panel 3, two sides that it frame panel 3 is tangent with crown sheave group 1 pulley edge are respectively provided with the rope winding jib 2 of a pectination, rope winding jib 2 comprises one group of comb 6 and base plate 7, one end of comb 6 is fixed on base plate 7, the other end of comb 6 is fixed on day frame panel 3, is partitioned into several eyelet hole between sky frame panel 3 and base plate 7 by comb 6.Distance between adjacent two comb 6 is identical with the distance between two pulley grooves adjacent in crown sheave group 1.
The utility model is when wire rope handling operation, and messenger 4 is first tied up the one end at steel rope by operating personnel, then messenger 4 is passed crown sheave group 1, successively by the corresponding eyelet hole of rope winding jib 2, then penetrates corresponding tourist bus assembly pulley 5; After deriving from tourist bus pulley, first by the eyelet hole of pectination rope winding jib 2 correspondence, then be coiled on the corresponding pulley of overhead traveling crane, tractive messenger 4, penetrates steel rope in crown sheave and tourist bus pulley, completes the wire rope handling operation of steel cable.
The utility model is by the use of rope winding jib, messenger, steel rope are put in order between the comb of the corresponding rope winding jib of crown sheave group, tourist bus assembly pulley, the phenomenon of disorder cable rope woolding would not be there is in messenger, steel rope, shorten the wire rope handling time, improve wire rope handling efficiency, time saving and energy saving, reduce task difficulty; The potential safety hazard that may occur when avoiding reason rope operation again.

Claims (2)

1. an oil-well rig boring tower sleeping dress rope guide, this device is arranged between crown sheave group (1) and tourist bus assembly pulley (5), it is characterized in that: the below of described crown sheave group (1) is provided with a day frame panel (3), two sides that it frame panel (3) is tangent with crown sheave group (1) pulley edge are respectively provided with the rope winding jib (2) of a pectination, rope winding jib (2) comprises one group of comb (6) and base plate (7), one end of comb (6) is fixed on base plate (7), the other end of comb (6) is fixed on a day frame panel (3), several eyelet hole is partitioned into by comb (6) between it frame panel (3) and base plate (7).
2. oil-well rig boring tower is sleeping according to claim 1 fills rope guide, it is characterized in that: the distance between adjacent two described comb (6) is identical with the distance between adjacent two pulley grooves in described crown sheave group (1).
CN201520993413.4U 2015-12-04 2015-12-04 Oil drilling derrick crouches and adorns spooling gear Active CN205187721U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520993413.4U CN205187721U (en) 2015-12-04 2015-12-04 Oil drilling derrick crouches and adorns spooling gear

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520993413.4U CN205187721U (en) 2015-12-04 2015-12-04 Oil drilling derrick crouches and adorns spooling gear

Publications (1)

Publication Number Publication Date
CN205187721U true CN205187721U (en) 2016-04-27

Family

ID=55780737

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520993413.4U Active CN205187721U (en) 2015-12-04 2015-12-04 Oil drilling derrick crouches and adorns spooling gear

Country Status (1)

Country Link
CN (1) CN205187721U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108002272A (en) * 2017-12-21 2018-05-08 中国石油集团川庆钻探工程有限公司 Pulling rope device for pulling well drilling steel wire rope and pulling method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108002272A (en) * 2017-12-21 2018-05-08 中国石油集团川庆钻探工程有限公司 Pulling rope device for pulling well drilling steel wire rope and pulling method thereof
CN108002272B (en) * 2017-12-21 2023-06-09 中国石油集团川庆钻探工程有限公司 Pulling rope device for pulling drilling steel wire rope and pulling method thereof

Similar Documents

Publication Publication Date Title
CN202064839U (en) Four-drill column double headframe for land drilling machine
CN205114916U (en) Two winch oil -well rigs play to rise system based on move fixed pulley train
CN204342334U (en) That a kind of oil-well rig is changed the large rope of drilling well leads large rope device
CN107651546A (en) The main replacing lifting ropes of multi-rope technique of vertical
CN205187721U (en) Oil drilling derrick crouches and adorns spooling gear
CN205709343U (en) The inverse dress special building hoist of moldeed depth foundation ditch
CN202108420U (en) Land headframe for duplex rig
CN202578561U (en) Safety anti-collision device for overhead travelling crane
CN103964284A (en) Non-production-stopping modifying method for hoisting system with multi-rope friction pulley for hoisting internal shaft
CN204732808U (en) A kind of cable testing bridge laying apparatu
CN202401981U (en) Drilling machine
CN103967503A (en) Production-stop-free transformation method for tower type interior shaft elevating system
CN204643680U (en) A kind of dustless electric cucurbit
CN202031502U (en) Double-travel hoisting system of drilling and workover rig
CN205558818U (en) A whole lift -type rig
CN203248599U (en) Counterweight self-detached structure of rotary drilling rig and rotary drilling rig
CN205133000U (en) Be applied to extra long device of hoist engine
CN208656387U (en) A kind of wirerope binding method drilling cable mounting mechanism
CN101881037A (en) Water pumping device for flushing well
CN201534741U (en) Lifting device of mine elevator
CN203345984U (en) Sinking winch
CN204189369U (en) A kind of heave compensation testing table
CN202300271U (en) Downhole catching fisher
CN206338037U (en) A kind of well workover self-balancing derrick
CN211198437U (en) Underground sensor pulley lifting device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant