CN205169257U - Emplacement fender work or material rest - Google Patents

Emplacement fender work or material rest Download PDF

Info

Publication number
CN205169257U
CN205169257U CN201520865289.3U CN201520865289U CN205169257U CN 205169257 U CN205169257 U CN 205169257U CN 201520865289 U CN201520865289 U CN 201520865289U CN 205169257 U CN205169257 U CN 205169257U
Authority
CN
China
Prior art keywords
column
hook
material frame
stand
chain
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520865289.3U
Other languages
Chinese (zh)
Inventor
张京泉
马洪涛
王传振
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xiezhuang Coal Mine Xinwen Mining Industry Group Co Ltd
Original Assignee
Xiezhuang Coal Mine Xinwen Mining Industry Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xiezhuang Coal Mine Xinwen Mining Industry Group Co Ltd filed Critical Xiezhuang Coal Mine Xinwen Mining Industry Group Co Ltd
Priority to CN201520865289.3U priority Critical patent/CN205169257U/en
Application granted granted Critical
Publication of CN205169257U publication Critical patent/CN205169257U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses an emplacement fender work or material rest, including the two sets of materials frame body that uses in pairs, every group material frame body includes the floorbar, first stand and second stand, the setting of first stand and second stand symmetry is at the both ends of floorbar upper surface, the spaced was equipped with a plurality of first supports hook on its direction of height was followed to first stand, the spaced was equipped with a plurality of seconds support hook on its direction of height was followed to the second stand, first support hook and second hold in the palm the position one -to -one of hook, and corresponding two first support hooks hold in the palm with the second and still prop up a support removable crossbeam between the hook, the top of second stand still is equipped with a chain, the chain is connected with the lateral wall in tunnel, and still be equipped with a head rod between the upper portion of two first stands of two sets of materials framves body. The utility model discloses make putting of tool materials realize the emplacement management, reached the purpose of scour protection. Simultaneously, it is detachable through setting the crossbeam to, also made things convenient for the access of tool materials.

Description

A kind of fixation chemoprevention rushes material frame
Technical field
The utility model relates to material frame technical field, particularly relates to a kind of fixation chemoprevention and rushes material frame.
Background technology
Along with the increase of coal mining depth, the possibility that bump occurs increases, its hazard rating is also on the rise, therefore, need to take fixation according to erosion control administrative provisions to roadway support and tool material, and fixationization management to be carried out in boring head stock ground, total matter frame to be joined in stock ground, guarantee that material does not land.
Utility model content
The utility model mainly solves technical matters existing in prior art, thus provides one can carry out the management of erosion control fixationization and access fixation chemoprevention easily rushing material frame to tool material.
Above-mentioned technical matters of the present utility model is mainly solved by following technical proposals:
The fixation chemoprevention that the utility model provides rushes material frame, comprise the two groups of material frame bodies used in pairs, often organize described material frame body and comprise bottom girder, first column and the second column, the two ends upper surface being arranged on described bottom girder of described first column and the second column symmetry, described first column is provided with multiple first hook along interval in its short transverse, described second column is provided with multiple second hook along interval in its short transverse, the position one_to_one corresponding of described first hook and the second hook, and go back the removable crossbeam of rest one between corresponding two described first hooks and the second hook, the top of the second column is also provided with a chain, described chain is connected with the sidewall in tunnel, and be also provided with a head rod between the top of two the first columns of material frame body described in two groups.
Further, the top often organizing described second column of described material frame body is equipped with an anchor pole, and the two ends of described anchor pole are exposed, and described chain is located in one end of described anchor pole, and it is connected with described second column by a jam nut.
Further, one second pipe link is also provided with between the top of two the second columns of material frame body described in two groups.
Further, multiple described first hook is evenly distributed along in the short transverse of described first column, and multiple described second hook is evenly distributed along in the short transverse of described second column.
Further, described head rod and the second pipe link first column described with two and two the second columns are removable is connected respectively.
The beneficial effects of the utility model are: by being emitted on the corresponding crossbeam of two groups of material frame bodies by tool material successively layering, and utilize chain to be connected with the sidewall in tunnel, make putting of tool material achieve fixationization management, reach the object of erosion control.Meanwhile, detachable by crossbeam is arranged to, also facilitate the access of tool material.
Accompanying drawing explanation
In order to be illustrated more clearly in the utility model embodiment or technical scheme of the prior art, be briefly described to the accompanying drawing used required in embodiment or description of the prior art below, apparently, accompanying drawing in the following describes is only embodiments more of the present utility model, for those of ordinary skill in the art, under the prerequisite not paying creative work, other accompanying drawing can also be obtained according to these accompanying drawings.
Fig. 1 is the structural representation that fixation chemoprevention of the present utility model rushes material frame.
Detailed description of the invention
Below in conjunction with accompanying drawing, preferred embodiment of the present utility model is described in detail, to make advantage of the present utility model and feature can be easier to be readily appreciated by one skilled in the art, thus more explicit defining is made to protection domain of the present utility model.
Consult shown in Fig. 1, fixation chemoprevention of the present utility model rushes material frame, comprise the two groups of material frame bodies 1 used in pairs, often organize material frame body 1 and comprise bottom girder 2, first column 3 and the second column 4, the two ends upper surface being arranged on bottom girder 2 of the first column 3 and the second column 4 symmetry, first column 3 is provided with multiple first hook 5 along interval in its short transverse, second column 4 is provided with multiple second hook 6 along interval in its short transverse, the position one_to_one corresponding of the first hook 5 and the second hook 6, and go back the removable crossbeam 7 of rest one between corresponding two the first hooks 5 and the second hook 6, the top of the second column 4 is also provided with a chain 8, chain 8 is connected with the sidewall in tunnel, and be also provided with a head rod 9 between the top of two of two groups of material frame bodies 1 the first columns 3.The utility model by being emitted on tool material successively layering on the corresponding crossbeam 7 of two groups of material frame bodies 1, and utilizes chain 8 to be connected with the sidewall in tunnel, makes putting of tool material achieve fixationization and manage, reaches the object of erosion control.Meanwhile, by being arranged to detachable by crossbeam 7, the access of tool material is also facilitated.Wherein, tool material comprises anchor pole, metal rhombus net and single track hanging beam etc.
Concrete, the top often organizing the second column 4 of material frame body 1 is equipped with an anchor pole 10, and the two ends of anchor pole 10 are exposed, and chain 8 is located in one end of anchor pole 10, and it is connected with the second column 4 by a jam nut 11.Such setting can easily be changed chain 8, improves its safety.
In the utility model, when placing the materials such as metal rhombus net, in order to improve the stability of structure, between the top of two the second columns 4 of storage rack two groups of material frame bodies 1, be also provided with one second pipe link 12.Wherein, head rod 9 and the second pipe link 12 can adopt the anchor pole of φ 22mm to be made.And in order to change the distance between two groups of material frame bodies 1, the instrument material of different length can be applicable to, head rod 9 and the second pipe link 12 are respectively with two the first columns 3 with two the second columns 4 are removable is connected.
Preferably, multiple first hook 5 is evenly distributed along in the short transverse of the first column 3, and multiple second hook 6 is evenly distributed along in the short transverse of the second column 4.Make the stacking space size on every layer of crossbeam identical like this, not only increase appearance, and make the stress equalization of material frame, improve its stability.
Above, be only detailed description of the invention of the present utility model, but protection domain of the present utility model is not limited thereto, any change of expecting without creative work or replacement, all should be encompassed within protection domain of the present utility model.Therefore, the protection domain that protection domain of the present utility model should limit with claims is as the criterion.

Claims (5)

1. a fixation chemoprevention rushes material frame, comprise the two groups of material frame bodies (1) used in pairs, it is characterized in that: often organize described material frame body (1) and comprise bottom girder (2), first column (3) and the second column (4), the two ends upper surface being arranged on described bottom girder (2) of described first column (3) and the second column (4) symmetry, described first column (3) is provided with multiple first hook (5) along interval in its short transverse, described second column (4) is provided with multiple second hook (6) along interval in its short transverse, the position one_to_one corresponding of described first hook (5) and the second hook (6), and go back the removable crossbeam of rest one (7) between corresponding two described first hooks (5) and the second hook (6), the top of the second column (4) is also provided with a chain (8), described chain (8) is connected with the sidewall in tunnel, and be also provided with a head rod (9) between the top of two the first columns (3) of material frame body (1) described in two groups.
2. fixation chemoprevention as claimed in claim 1 rushes material frame, it is characterized in that: the top often organizing described second column (4) of described material frame body (1) is equipped with an anchor pole (10), the two ends of described anchor pole (10) are exposed, described chain (8) is located in one end of described anchor pole (10), and it is connected with described second column (4) by a jam nut (11).
3. fixation chemoprevention as claimed in claim 2 rushes material frame, it is characterized in that: be also provided with one second pipe link (12) between the top of two the second columns (4) of material frame body (1) described in two groups.
4. fixation chemoprevention as claimed in claim 3 rushes material frame, it is characterized in that: multiple described first hook (5) is evenly distributed along in the short transverse of described first column (3), multiple described second hook (6) is evenly distributed along in the short transverse of described second column (4).
5. fixation chemoprevention as claimed in claim 4 rushes material frame, it is characterized in that: described head rod (9) and the second pipe link (12) first column (3) described with two and two the second columns (4) are removable is connected respectively.
CN201520865289.3U 2015-11-02 2015-11-02 Emplacement fender work or material rest Expired - Fee Related CN205169257U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520865289.3U CN205169257U (en) 2015-11-02 2015-11-02 Emplacement fender work or material rest

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520865289.3U CN205169257U (en) 2015-11-02 2015-11-02 Emplacement fender work or material rest

Publications (1)

Publication Number Publication Date
CN205169257U true CN205169257U (en) 2016-04-20

Family

ID=55733274

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520865289.3U Expired - Fee Related CN205169257U (en) 2015-11-02 2015-11-02 Emplacement fender work or material rest

Country Status (1)

Country Link
CN (1) CN205169257U (en)

Similar Documents

Publication Publication Date Title
CN104674854B (en) Ballasting system for detecting engineering pile foundation
MY185057A (en) A tire assembly and a method of building a support structure in a marine environment using tires
CN203986862U (en) A kind of bookshelf with hanging ladder
CN205169257U (en) Emplacement fender work or material rest
CN204916609U (en) Goods shelves with adjustable length
CN204703186U (en) A kind of pre-embedded bolt positioning installation apparatus
CN102748052A (en) Combined mining rail crossheading circulating forward type forepoling system
CN202595207U (en) Heat-treatment quenching clamp
CN105151691A (en) Carrier for LED street lamp pole
CN204563409U (en) A kind of single pole, two bar, high-low rod integral type gymnastic training device
CN204096084U (en) A kind of alighting gear on 15kg remotely pilotless pesticide applicator
CN203185326U (en) Tree-shaped pipe rack and stacking rack composed of tree-shaped pipe racks
CN206022931U (en) Adjustment type bin frame
CN103711126A (en) Righting structure for piling
CN205116749U (en) A track strutting arrangement that is used for large -span steel construction wholly to slide
CN204529148U (en) Cement electric pole press-rod apparatus
CN203094923U (en) Combine type goods shelf
CN203814300U (en) Supporting rack for high and large tree in landscape engineering
CN207007013U (en) Guider and Moving target drone
CN203008946U (en) Hydraulic support
CN203294293U (en) Drilling platform with five or more buoys
CN204402514U (en) A kind of roadway support structure
CN204310244U (en) Helicoid hydraulic motor laying rack
CN203320557U (en) Undersea tunnel steel frame structure
CN204749949U (en) Car cable rocker car

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160420

Termination date: 20171102

CF01 Termination of patent right due to non-payment of annual fee