CN205117498U - Multi -functional generating set of gas parallel machine - Google Patents

Multi -functional generating set of gas parallel machine Download PDF

Info

Publication number
CN205117498U
CN205117498U CN201520883868.0U CN201520883868U CN205117498U CN 205117498 U CN205117498 U CN 205117498U CN 201520883868 U CN201520883868 U CN 201520883868U CN 205117498 U CN205117498 U CN 205117498U
Authority
CN
China
Prior art keywords
parallel operation
room
isolating switch
rest area
gas turbine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520883868.0U
Other languages
Chinese (zh)
Inventor
施崇槐
郑义豪
王刚
范兴方
邹敏
吴波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Amico Fuel Gas Technology Co Ltd
Original Assignee
Chengdu Amico Fuel Gas Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Amico Fuel Gas Technology Co Ltd filed Critical Chengdu Amico Fuel Gas Technology Co Ltd
Priority to CN201520883868.0U priority Critical patent/CN205117498U/en
Application granted granted Critical
Publication of CN205117498U publication Critical patent/CN205117498U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Other Air-Conditioning Systems (AREA)

Abstract

The utility model provides a multi -functional generating set of gas parallel machine, organize in a gas turbine generator of silence case one end group and the 2nd gas turbine generator including silence case and parallel arrangement, one side of gas turbine generator group and the 2nd gas turbine generator group is provided with the access path, and the access path has control box and air conditioner through the wall connection rest area that gives sound insulation, rest area's top parallel arrangement, and rest area's opposite side is provided with the operating area, and the opposite side of operating area is provided with parallel machine and switches over the room to the avris that the machine switches the room is connected with the cable conductor through the district of working a telephone switchboard, the utility model discloses the computer lab is switched with parallel machine in gas turbine generator group owing to integrateed, has saved the space, has practiced thrift preparation and cost of transportation, electrical apparatus protection level IP65, the security is high, and inside personnel's activity space is big, and the travelling comfort is good, adopt modular circuit control, the reliability is high, and the fault point is few, and the response is fast, unit automated control degree is high, on -site supervision, debugging, simple operation.

Description

A kind of combustion gas parallel operation multifunctional generating unit
Technical field
The utility model relates to a kind of generator set, particularly a kind of combustion gas parallel operation multifunctional generating unit.
Background technique
Generator set refers to the power generating equipment that mechanical energy or other renewable energy sources can be transformed into electric energy.Common generator set is driven by steam turbine, water turbine or internal-combustion engine (motor such as petrol engine, diesel engine) usually, and renewable new energy comprise nuclear energy, wind energy, solar energy, biomass energy, ocean energy etc.Because the capacity of diesel generating set is comparatively large, can parallel operation operation and the continued power time long, also can independent operating, not with area power grid paired running, be not subject to the impact of electric network fault, reliability is higher.Especially commonly use under civil power is not very reliable situation to certain areas, using diesel generating set as standby power supply, the effect of emergency power supply can be played, again by the reasonably optimizing of low service system, some loads important at ordinary times being used when having a power failure, being therefore widely used in engineering.
Along with the diversification of the generator set market demand, in oil drilling industry, diesel generation and fuel gas generation are used alternatingly the constantly soaring of frequency, for reasonably using the generator set of these two kinds of different fuel media, use is switched in real time under just needing different environment and condition, when could namely ensure to produce, give full play of again the respective advantage of two type generator set, but existing generator set is difficult to the real-time switching that effectively realizes between two generators.
Model utility content
The technical problems to be solved in the utility model overcomes existing defect, a kind of combustion gas parallel operation multifunctional generating unit is provided, solve the multiple stage parallel operation problem of jet dynamic control, and the switching using function of diesel generating set and jet dynamic control, effectively can solve the problem in background technique.
In order to solve the problems of the technologies described above, the utility model provides following technological scheme:
The utility model provides a kind of combustion gas parallel operation multifunctional generating unit, comprise silencing case and be set in parallel in the first jet dynamic control and second jet dynamic control of described silencing case one end, the side of described first jet dynamic control and described second jet dynamic control is provided with access path, described access path connects rest area by noise barrier, the top of described rest area is arranged with control box and air-conditioning in parallel, the opposite side of described rest area is provided with control panel, the opposite side of described control panel is provided with parallel operation and switches room, the avris that described parallel operation switches room is connected with elastic cable paper by Wiring area.
As a kind of optimal technical scheme of the present utility model, described parallel operation switches room and comprises circuit breaker, the first isolating switch, the second isolating switch, the 3rd isolating switch and transformer, and described circuit breaker connects described first isolating switch, described second isolating switch and described 3rd isolating switch respectively.
As a kind of optimal technical scheme of the present utility model, heat radiation, ventilation flue are left in the bottom that described parallel operation switches room, adopt copper bar to connect between each element in inside in described parallel operation switching room.
As a kind of optimal technical scheme of the present utility model, the surface of described noise barrier is provided with viewing window, and the ground of described access path, described rest area and described control panel is all equipped with insulation antiskid glue cushion.
As a kind of optimal technical scheme of the present utility model, described parallel operation is switched room and is connected with described air-conditioning by pipeline.
The beneficial effect that compared with prior art the utility model reaches is:
1, owing to being integrated with jet dynamic control and parallel operation switches machine room, save space, saved making and cost of transportation;
2, electrical equipment security level IP65, Security is high, and internal staff's activity space is large, and travelling comfort is good;
3, adopt modular circuit to control, reliability is high, and fault point is few, and responsiveness is fast;
4, unit automation controlling extent is high, on-site supervision, debugging, simple operation.
Accompanying drawing explanation
Accompanying drawing is used to provide further understanding of the present utility model, and forms a part for specification, is used from explanation the utility model, does not form restriction of the present utility model with embodiment one of the present utility model.
In the accompanying drawings:
Fig. 1 is the main TV structure schematic diagram of the utility model;
Fig. 2 is that the utility model parallel operation switches room element structure schematic diagram;
Number in the figure: 1, silencing case; 2, the first jet dynamic control; 3, the second jet dynamic control; 4, noise barrier; 5, control box; 6, air-conditioning; 7, parallel operation switches room; 8, Wiring area; 9, elastic cable paper; 10, access path; 11, rest area; 12, control panel; 13, circuit breaker; 14, the first isolating switch; 15, the second isolating switch; 16, the 3rd isolating switch.
Embodiment
Below in conjunction with accompanying drawing, preferred embodiment of the present utility model is described, should be appreciated that preferred embodiment described herein is only for instruction and explanation of the utility model, and be not used in restriction the utility model.
Embodiment: as shown in Figure 1-2, the utility model provides a kind of combustion gas parallel operation multifunctional generating unit, comprise silencing case 1 and be set in parallel in first jet dynamic control 2 and second jet dynamic control 3 of silencing case 1 one end, the side of the first jet dynamic control 2 and the second jet dynamic control 3 is provided with access path 10, access path 10 connects rest area 11 by noise barrier 4, the top of rest area 11 is arranged with control box 5 and air-conditioning 6 in parallel, the opposite side of rest area 11 is provided with control panel 12, the opposite side of control panel 12 is provided with parallel operation and switches room 7, the avris that parallel operation switches room 7 is connected with elastic cable paper 9 by Wiring area 8.
Further, parallel operation switches room 7 and comprises circuit breaker 13, first isolating switch 14, second isolating switch 15, the 3rd isolating switch 16 and transformer, and circuit breaker 13 connects the first isolating switch 14, second isolating switch 15 and the 3rd isolating switch 16 respectively.Heat radiation, ventilation flue are left in the bottom that parallel operation switches room 7, adopt copper bar to connect between each element in inside in parallel operation switching room 7.The surface of noise barrier 4 is provided with viewing window, and the ground of access path 10, rest area 11 and control panel 12 is all equipped with insulation antiskid glue cushion, and Security is high, and internal staff's activity space is large, and travelling comfort is good.Parallel operation is switched room 7 and is connected with air-conditioning 6 by pipeline, is mainly used in the heat radiation refrigeration that parallel operation switches machine room 7.
Embodiment 1: shown in institute Fig. 1, and combustion gas parallel operation multifunctional generating unit is integrated in silencing case 1, and casing front end part lays two jet dynamic control as auxiliary power generation, leaves maintenance passageway 10; Box back switches machine room 7 by personnel rest area 11, control panel 12 and control box 5, air-conditioning 6, parallel operation, Wiring area 8 forms, front and back part is separated by noise barrier 4, noise barrier 4 leaves viewing window, personnel activity region paving insulation antiskid glue cushion, unit elastic cable paper is all from casing 1 rear end line, and the air-conditioning 6 in left side is mainly used in the heat radiation refrigeration that parallel operation switches machine room 7.
Embodiment 2: shown in institute Fig. 2, the electric elements that parallel operation switches machine room 7 is made up of circuit breaker 13, isolating switch, transformer etc., jet dynamic control 2 is connected by circuit breaker 13 lower end inlet wire, and diesel generating set is connected by isolating switch lower end left incoming line, last by the outlet of isolating switch upper end to load equipment, copper bar is adopted to connect between each element, copper bar arranges specification, rationally, bottom half leaves heat radiation, ventilation flue, personnel only need disconnecting switch operation handle knob, can realize the switching function of jet dynamic control and diesel generator.
The utility model, owing to being integrated with jet dynamic control and parallel operation switches machine room 7, saving space, has saved making and cost of transportation; Electrical equipment security level IP65, Security is high, and internal staff's activity space is large, and travelling comfort is good; Employing modular circuit controls, and reliability is high, and fault point is few, and responsiveness is fast; Unit automation controlling extent is high, on-site supervision, debugging, simple operation.
Last it is noted that the foregoing is only preferred embodiment of the present utility model, be not limited to the utility model, although be described in detail the utility model with reference to previous embodiment, for a person skilled in the art, it still can be modified to the technological scheme described in foregoing embodiments, or carries out equivalent replacement to wherein portion of techniques feature.All within spirit of the present utility model and principle, any amendment done, equivalent replacement, improvement etc., all should be included within protection domain of the present utility model.

Claims (5)

1. a combustion gas parallel operation multifunctional generating unit, comprise silencing case (1) and be set in parallel in the first jet dynamic control (2) and second jet dynamic control (3) of described silencing case (1) one end, it is characterized in that, the side of described first jet dynamic control (2) and described second jet dynamic control (3) is provided with access path (10), described access path (10) connects rest area (11) by noise barrier (4), the top of described rest area (11) is arranged with control box (5) and air-conditioning (6) in parallel, the opposite side of described rest area (11) is provided with control panel (12), the opposite side of described control panel (12) is provided with parallel operation and switches room (7), the avris that described parallel operation switches room (7) is connected with elastic cable paper (9) by Wiring area (8).
2. a kind of combustion gas parallel operation multifunctional generating unit according to claim 1, it is characterized in that, described parallel operation switches room (7) and comprises circuit breaker (13), the first isolating switch (14), the second isolating switch (15), the 3rd isolating switch (16) and transformer, and described circuit breaker (13) connects described first isolating switch (14), described second isolating switch (15) and described 3rd isolating switch (16) respectively.
3. a kind of combustion gas parallel operation multifunctional generating unit according to claim 2, is characterized in that, heat radiation, ventilation flue are left in the bottom that described parallel operation switches room (7), adopts copper bar to connect between each element in inside of described parallel operation switching room (7).
4. a kind of combustion gas parallel operation multifunctional generating unit according to claim 1, it is characterized in that, the surface of described noise barrier (4) is provided with viewing window, and the ground of described access path (10), described rest area (11) and described control panel (12) is all equipped with insulation antiskid glue cushion.
5. a kind of combustion gas parallel operation multifunctional generating unit according to claim 3, is characterized in that, described parallel operation is switched room (7) and is connected with described air-conditioning (6) by pipeline.
CN201520883868.0U 2015-11-09 2015-11-09 Multi -functional generating set of gas parallel machine Active CN205117498U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520883868.0U CN205117498U (en) 2015-11-09 2015-11-09 Multi -functional generating set of gas parallel machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520883868.0U CN205117498U (en) 2015-11-09 2015-11-09 Multi -functional generating set of gas parallel machine

Publications (1)

Publication Number Publication Date
CN205117498U true CN205117498U (en) 2016-03-30

Family

ID=55573114

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520883868.0U Active CN205117498U (en) 2015-11-09 2015-11-09 Multi -functional generating set of gas parallel machine

Country Status (1)

Country Link
CN (1) CN205117498U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106545407A (en) * 2016-12-19 2017-03-29 四川宏华电气有限责任公司 A kind of gas power station for oil electric drilling machine
CN110957849A (en) * 2018-09-26 2020-04-03 天津博威动力设备有限公司 Container type diesel engine set walking channel structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106545407A (en) * 2016-12-19 2017-03-29 四川宏华电气有限责任公司 A kind of gas power station for oil electric drilling machine
CN106545407B (en) * 2016-12-19 2019-12-31 四川宏华电气有限责任公司 Gas power station for petroleum electric drilling machine
CN110957849A (en) * 2018-09-26 2020-04-03 天津博威动力设备有限公司 Container type diesel engine set walking channel structure

Similar Documents

Publication Publication Date Title
CN103746389B (en) Wind-powered electricity generation 500kV based on reactive voltage characteristic collects Substation Reactive-power Compensation collocation method
CA2537971A1 (en) Power-station installation
CN205117498U (en) Multi -functional generating set of gas parallel machine
CN203521982U (en) Intelligent box type direct current traction transformer station
CN104993408B (en) Offshore boosting station
CN203201657U (en) Container power station
CN211046216U (en) Electric drive power integrated system of drilling system
CN202925950U (en) Thermal power plant main power house and integrated power house of additional building
CN207377658U (en) A kind of combustion gas of Novel filtration structure and machine generating set
CN106545407B (en) Gas power station for petroleum electric drilling machine
CN207454114U (en) A kind of integrated security intelligent control box for jet dynamic control
CN112018890B (en) Modularized prefabricated cabin type 110kV photovoltaic collection station for high-altitude areas
CN103580452A (en) Chained SVG power cabinet
CN210074787U (en) High-power converter circuit topological structure for offshore wind power
CN209742442U (en) Urban and rural integrated incineration power generation main plant for biomass and household garbage
CN208986677U (en) A kind of high pressure online UPS device
CN102082496A (en) Converter cabinet for wind power generation
CN208190041U (en) A kind of electronic engineering machinery power distribution cabinet
CN206972316U (en) A kind of space-saving type distributed energy resource system
CN207573087U (en) A kind of harbour bank electricity monitoring system
CN209313243U (en) A kind of compact bank electricity container
CN204552181U (en) A kind of mountain area wind energy turbine set booster stations " T " character form structure
CN211474245U (en) Novel prevent wind husky gas parallel operation generating set of structure
CN202530792U (en) Distributed roof energy station structure
CN205248801U (en) A distribution system that is used for slot type solar thermal energy electricity generation thermal -arrest field

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant