CN205046541U - Composite foundation - Google Patents

Composite foundation Download PDF

Info

Publication number
CN205046541U
CN205046541U CN201520802673.9U CN201520802673U CN205046541U CN 205046541 U CN205046541 U CN 205046541U CN 201520802673 U CN201520802673 U CN 201520802673U CN 205046541 U CN205046541 U CN 205046541U
Authority
CN
China
Prior art keywords
layer
macadam
several
composite foundation
cfg
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520802673.9U
Other languages
Chinese (zh)
Inventor
王晓军
尚知宇
官璐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SUZHOU SINOMA CONSTRUCTION CO Ltd
Original Assignee
SUZHOU SINOMA CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SUZHOU SINOMA CONSTRUCTION CO Ltd filed Critical SUZHOU SINOMA CONSTRUCTION CO Ltd
Priority to CN201520802673.9U priority Critical patent/CN205046541U/en
Application granted granted Critical
Publication of CN205046541U publication Critical patent/CN205046541U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a composite foundation, including set up the foundation stabilization body, location in weak soil natural foundation lay in on the foundation stabilization body top add muscle mattress layer and set up in with the layer of filling on the muscle mattress layer, wherein, the foundation stabilization body is including a plurality of PHC tubular pile and the stake of a plurality of CFG, the range in turn of a plurality of PHC tubular pile and a plurality of CFG stake interval to form array structure, add muscle mattress layer and include from the last first metalling of down arranging in proper order, fine sand layer, a geogrid, second metalling, medium coarse sand layer, the 2nd geogrid, third metalling and concrete layer, and each the top of PHC tubular pile and each the top of CFG stake all wears to establish concrete layer, and plant in in the third metalling, this composite foundation not only can consolidate the ground, still reduces the construction degree of difficulty and engineering cost.

Description

Composite foundation
Technical field
The utility model relates to technical field of building construction, specifically provides a kind of composite foundation.
Background technology
In engineering practice, people have invented composite foundation, by basement process, improve the stress performance of natural ground, make it reach designing requirement.Currently used CFG pile composite foundation is the basement process form of the most conventional use, described CFG pile composite foundation structure refers to and arrange several CFG stakes in weak soil natural ground, then on the top of these several CFG stakes, be equipped with mattress layer (commonly using as macadam), last setting on mattress layer again fills layer, well can improve the stress performance of natural ground.
But due in practice of construction process, the Soft Soil Layer distribution of construction area, the equal factor of uneven thickness and water content, traditional, single CFG pile composite foundation processing form then well can not be applicable to the construction environment of more complicated, not only reach the technique effect of expection, also greatly can increase technical difficulty and the engineering cost of construction.
Therefore, how can either realize consolidated subsoil, reduce difficulty of construction and engineering cost again, become the technical problem that those skilled in the art need solution badly.
Summary of the invention
In order to overcome above-mentioned defect, the utility model provides a kind of composite foundation, and this composite foundation can not only consolidated subsoil, also reduction difficulty of construction and engineering cost.
The utility model in order to the technical scheme solving its technical problem and adopt is: a kind of composite foundation, comprise the ground stabilization body be arranged in weak soil natural ground, locate the reinforcement mattress layer that is layed on described ground stabilization body top and be arranged at and described reinforcement mattress layer fills layer, wherein, described ground stabilization body comprises several PHC pile tubes and several CFG stakes, the arrangement that several PHC pile tubes described and several CFG stake intervals replace, to form array structure;
Described reinforcement mattress layer comprises the first macadam, fine sand layer, the first geo-grid, the second macadam, medium-sand seam, the second geo-grid, the 3rd macadam and the layer of concrete arranged successively from top to bottom, and the top of PHC pile tube described in each and the top of CFG stake described in each are all fed through described layer of concrete, and be inserted in described 3rd macadam.
As further improvement of the utility model, the top of PHC pile tube described in several and the top of CFG stake described in several flush;
And the bottom of the bottom of PHC pile tube described in several and CFG stake described in several is also respectively equipped with the second fine sand layer respectively.
As further improvement of the utility model, the height of described PHC pile tube is greater than the height of described CFG stake.
As further improvement of the utility model, described in each, CFG stake inside is respectively embedded with reinforcing cage respectively.
As further improvement of the utility model, the thickness of described reinforcement mattress layer is 30 ~ 50cm.
As further improvement of the utility model, the particle diameter of described first macadam medium stone is greater than the particle diameter of described second macadam and the 3rd macadam medium stone.
The beneficial effects of the utility model are: compared to prior art, this composite foundation has the following advantages: 1. described ground stabilization body adopts the form that PHC pile tube and CFG stake combination are arranged, make full use of the characteristic of PHC pile tube and CFG stake self, not only effectively reduce foundation deformation, consolidated subsoil; Also reduce difficulty of construction, save engineering cost, efficient energy-saving.2. described reinforcement mattress layer can divide in fact the flexible cushion layer be made up of the first macadam, fine sand layer, the first geo-grid, the second macadam, medium-sand seam, the second geo-grid and the 3rd macadam and the rigidity mattress layer be made up of layer of concrete, wherein, flexible cushion layer can make composite foundation have the effect of buffering absorbing preferably, ensure that ground stabilization body is indeformable and reduce ground and produce crack, sedimentation etc., strengthen the steadiness of ground entirety; Rigidity mattress layer then can make ground stabilization body become to be integrated, and makes the supporting capacity of ground stabilization body be able to better performance; In addition, the water passage that rigidity mattress layer can also be formed in closing flexible mattress layer, avoids ponding to penetrate in ground stabilization body.
Accompanying drawing explanation
Fig. 1 is the cross-sectional view of composite foundation described in the utility model.
By reference to the accompanying drawings, make the following instructions:
1---ground stabilization body 10---PHC pile tube
11---CFG stake 2---reinforcement mattress layer
20---first macadam 21---fine sand layer
22---first geo-grid 23---second macadam
24---medium-sand seam 25---second geo-grid
26---the 3rd macadam 27---layer of concrete
3---fill layer
Detailed description of the invention
Referring to figure, preferred embodiment of the present utility model is described in detail.
A kind of composite foundation described in the utility model, comprise the ground stabilization body 1 be arranged in weak soil natural ground, locate the reinforcement mattress layer 2 that is layed on described ground stabilization body 1 top and be arranged at and described reinforcement mattress layer 2 fills layer 3, wherein, described ground stabilization body comprises several PHC pile tube 10 and several CFG stakes 11, the arrangement that several PHC pile tubes 10 described and several CFG stake 11 intervals replace, to form array structure;
Described reinforcement mattress layer 2 comprises the first macadam 20, fine sand layer 21, first geo-grid 22, second macadam 23, medium-sand seam 24, second geo-grid 25, the 3rd macadam 26 and the layer of concrete 27 arranged successively from top to bottom, and the top of PHC pile tube 10 described in each and the top of CFG stake 11 described in each are all fed through described layer of concrete 27, and be inserted in described 3rd macadam 26.
Preferably, the top of PHC pile tube 10 described in several and the top of CFG stake 11 described in several flush;
And the bottom of PHC pile tube 10 described in several and the bottom of CFG stake 11 described in several are also respectively equipped with the second fine sand layer respectively, using as substrate bearing stratum.
Preferably, the height of described PHC pile tube 10 is greater than the height of described CFG stake 11.
Preferably, described in each, CFG stake 11 inside is respectively embedded with reinforcing cage respectively.
Preferably, the thickness of described reinforcement mattress layer 2 is 30 ~ 50cm.
Preferably, the particle diameter of described first macadam 20 medium stone is greater than the particle diameter of described second macadam 23 and the 3rd macadam 26 medium stone.
Compared to prior art, composite foundation described in the utility model has the following advantages: 1. described ground stabilization body adopts the form that PHC pile tube and CFG stake combination are arranged, make full use of the characteristic of PHC pile tube and CFG stake self, not only effectively reduce foundation deformation, consolidated subsoil; Also reduce difficulty of construction, save engineering cost, efficient energy-saving.2. described reinforcement mattress layer can divide in fact the flexible cushion layer be made up of the first macadam, fine sand layer, the first geo-grid, the second macadam, medium-sand seam, the second geo-grid and the 3rd macadam and the rigidity mattress layer be made up of layer of concrete, wherein, flexible cushion layer can make composite foundation have the effect of buffering absorbing preferably, ensure that ground stabilization body is indeformable and reduce ground and produce crack, sedimentation etc., strengthen the steadiness of ground entirety; Rigidity mattress layer then can make ground stabilization body become to be integrated, and makes the supporting capacity of ground stabilization body be able to better performance; In addition, the water passage that rigidity mattress layer can also be formed in closing flexible mattress layer, avoids ponding to penetrate in ground stabilization body.

Claims (6)

1. a composite foundation, it is characterized in that: comprise the ground stabilization body (1) be arranged in weak soil natural ground, locate the reinforcement mattress layer (2) that is layed on described ground stabilization body (1) top and be arranged at and described reinforcement mattress layer (2) fills layer (3), wherein, described ground stabilization body comprises several PHC pile tubes (10) and several CFG stakes (11), the arrangement that several PHC pile tubes (10) described and several CFG stake (11) intervals replace, to form array structure;
Described reinforcement mattress layer (2) comprises the first macadam (20), fine sand layer (21), the first geo-grid (22), the second macadam (23), medium-sand seam (24), the second geo-grid (25), the 3rd macadam (26) and the layer of concrete (27) arranged successively from top to bottom, and the top of PHC pile tube (10) described in each and the top of CFG stake (11) described in each are all fed through described layer of concrete (27), and be inserted in described 3rd macadam (26).
2. composite foundation according to claim 1, is characterized in that: the top of PHC pile tube (10) described in several and the top of CFG stake (11) described in several flush;
And the bottom of the bottom of PHC pile tube (10) described in several and CFG stake (11) described in several is also respectively equipped with the second fine sand layer respectively.
3. composite foundation according to claim 1 and 2, is characterized in that: the height of described PHC pile tube (10) is greater than the height of described CFG stake (11).
4. composite foundation according to claim 1, is characterized in that: described in each, CFG stake (11) inside is respectively embedded with reinforcing cage respectively.
5. composite foundation according to claim 1, is characterized in that: the thickness of described reinforcement mattress layer (2) is 30 ~ 50cm.
6. composite foundation according to claim 1, is characterized in that: the particle diameter of described first macadam (20) medium stone is greater than the particle diameter of described second macadam (23) and the 3rd macadam (26) medium stone.
CN201520802673.9U 2015-10-16 2015-10-16 Composite foundation Active CN205046541U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520802673.9U CN205046541U (en) 2015-10-16 2015-10-16 Composite foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520802673.9U CN205046541U (en) 2015-10-16 2015-10-16 Composite foundation

Publications (1)

Publication Number Publication Date
CN205046541U true CN205046541U (en) 2016-02-24

Family

ID=55340138

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520802673.9U Active CN205046541U (en) 2015-10-16 2015-10-16 Composite foundation

Country Status (1)

Country Link
CN (1) CN205046541U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105780804A (en) * 2016-03-26 2016-07-20 山东华安铁塔有限公司 Extra-high voltage power transmission iron tower foundation applicable to hilly regions
CN107130579A (en) * 2017-05-17 2017-09-05 重庆教育建设(集团)有限公司 Without muscle spread foundation constructing device and the dual composite foundation construction method of hard and soft
CN110512590A (en) * 2019-07-11 2019-11-29 桂林理工大学 It is a kind of for preventing the construction method of bridge foundation differential settlement
CN111155508A (en) * 2020-02-20 2020-05-15 中国电建集团贵阳勘测设计研究院有限公司 Soft soil karst foundation reinforced structure

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105780804A (en) * 2016-03-26 2016-07-20 山东华安铁塔有限公司 Extra-high voltage power transmission iron tower foundation applicable to hilly regions
CN107130579A (en) * 2017-05-17 2017-09-05 重庆教育建设(集团)有限公司 Without muscle spread foundation constructing device and the dual composite foundation construction method of hard and soft
CN110512590A (en) * 2019-07-11 2019-11-29 桂林理工大学 It is a kind of for preventing the construction method of bridge foundation differential settlement
CN111155508A (en) * 2020-02-20 2020-05-15 中国电建集团贵阳勘测设计研究院有限公司 Soft soil karst foundation reinforced structure

Similar Documents

Publication Publication Date Title
CN205046541U (en) Composite foundation
CN103821160B (en) Soft soil foundation combined pile net structure
CN101024951A (en) Foundation processing method
CN101922146A (en) Method for performing foundation treatment by using permeable concrete pipe piles
CN202969393U (en) Ribbing load reduction structure of road high hill culvert
CN104060601B (en) The construction method of utilizing precast construction stake pile foundation to carry out ground processing
CN103437336A (en) PVC hole-pipe gravel pile and soft foundation processing method thereof
CN101424079A (en) Construction method of geotechnical grid reinforcement bed course and sandstone pile bidirectional reinforced composite foundation
CN206706806U (en) A kind of dual composite foundation of rigid and flexible pile
CN201530968U (en) High-speed railway liquefying soil foundation-roadbed seismic strengthening structure
CN101200888A (en) Construction method of composite foundation
CN205954638U (en) Half semi -rigid flexible supporting construction of deep basal pit lateral wall
CN203834512U (en) Combined type gravity retaining wall
CN205501982U (en) Slope soft foundation reinforcement structure
CN102454171A (en) Reinforced earth retaining wall
CN101793027A (en) Core-grouted static pressure anchor rod pile
CN204875834U (en) Liquefaction sand and soil structure
CN204151772U (en) A kind of rigid pile composite foundation
CN206173937U (en) Short plain concrete stake composite foundation of long tube stake
CN202108055U (en) Reinforcement cantilever type retaining wall structure
CN203782727U (en) Soft soil foundation combined pile mesh structure
CN205420939U (en) Roadbed structure of crowded native bored concrete pile stake net of bidirectional screw
CN210886796U (en) Subgrade is consolidated to weak soil
CN205676912U (en) A kind of composite foundation
CN208251014U (en) A kind of upright embankment structure of composite foundation base empty van

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant