CN205035836U - Irrigation concrete elevation monitor under water - Google Patents

Irrigation concrete elevation monitor under water Download PDF

Info

Publication number
CN205035836U
CN205035836U CN201520750612.2U CN201520750612U CN205035836U CN 205035836 U CN205035836 U CN 205035836U CN 201520750612 U CN201520750612 U CN 201520750612U CN 205035836 U CN205035836 U CN 205035836U
Authority
CN
China
Prior art keywords
graded tube
concrete
pile
pull rod
under water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520750612.2U
Other languages
Chinese (zh)
Inventor
张龙
巩立青
翟瑞军
刘国栋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 3 Engineering Group Co Ltd
Transportation Engineering Branch of China Railway No 3 Engineering Group Co Ltd
Original Assignee
China Railway No 3 Engineering Group Co Ltd
Transportation Engineering Branch of China Railway No 3 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 3 Engineering Group Co Ltd, Transportation Engineering Branch of China Railway No 3 Engineering Group Co Ltd filed Critical China Railway No 3 Engineering Group Co Ltd
Priority to CN201520750612.2U priority Critical patent/CN205035836U/en
Application granted granted Critical
Publication of CN205035836U publication Critical patent/CN205035836U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Or Underwater Handling Of Building Materials (AREA)

Abstract

The utility model belongs to the technical field of drilled pile irrigation concrete construction under water, concretely relates to irrigation concrete elevation monitor under water. The utility model discloses a can in time, accurately monitor the height that fills that the pile foundation concrete filled the in -process, provide an irrigation concrete elevation monitor under water, including fixed bolster, graded tube with be equipped with the sample plate that gets of counter weight, graded tube vertical installation, install on the fixed bolster through horizontal fixed axle and through the locking of scale lock the upper end of graded tube, gets sample plate and install in the lower extreme of graded tube and reciprocate along with the graded tube. This monitor can be timely, accurate, the audio -visual pile bolck concrete that embodies fills developments, has effectively avoided surpassing and irritating because of filling the inaccurate concrete that causes of altitude control, leads to the pile head too big, waste time and energy during the chisel pile head, quality problems such as cost increasing, pile head quality -unqualified are consumed above set limit to the material, and economic benefits is obvious.

Description

Underwater concreting absolute altitude monitor
Technical field
The utility model belongs to the technical field of drilled pile underwater concrete construction, is specifically related to a kind of underwater concreting absolute altitude monitor.
Background technology
In pile foundation concrete perfusion work progress, if the high too high meeting of castinplace pile top mark causes concrete to waste, if perfusion absolute altitude deficiency, stake top can be caused off quality.Therefore, strictly must control concrete groundwater increment, then need to measure concrete influx height in filling process.Traditional measuring method adopts lining rope to measure filling concrete height, but when utilizing the method to measure, if measurement not in time or lining rope tup is overweight easily sinks in concrete, then can cause the super filling of concrete, cause pile crown excessive, waste time and energy during cutter pile crown, added cost; If tup kicks the beam and easily held up by upper strata laitance, can not determine bottom lining rope, whether tup sinks to concrete, workman can be misled if any mudstone and think it is concrete, cause measure inaccurate, the quality problems such as cause pile crown off quality.
For bridge engineering pile foundation construction, adopt the artificial lining rope that irregularly uses to measure filling concrete height during drilled pile construction underwater concreting before, for the stake of long 40 rice diameter 1.25 meters of a pile, perfusion pore-forming at least needs to measure more than 5 times with lining rope, qualified in order to ensure stake top mark eminence concrete quality as far as possible, during concrete perfusion, high will to exceed design stake top mark high 1.0 meters for top mark, easily cause pile crown excessive, cause costly waste and cut a hole pile crown time-consuming, take a lot of work, stake top quality is also difficult to control, and often causes and does over again.
Summary of the invention
The utility model, in order to monitor the influx height in pile foundation filling concrete process in time, exactly, provides a kind of underwater concreting absolute altitude monitor.
The utility model adopts following technical scheme:
A kind of underwater concreting absolute altitude monitor, comprise fixed support, graded tube and be provided with the sampling dish of counterweight, described graded tube is vertically installed, the upper end of graded tube to be installed on fixed support by horizontal fixed axis and by the locking of scale lock, sampling dish is installed on the lower end of graded tube and moves up and down with graded tube.
Described fixed support comprises back shaft, job platform and casing, and back shaft and job platform connection in T shape, the two ends of job platform are by casing supported, and described graded tube is connected to the side of job platform.
Described casing is semicircle globoidal structure.
Described sampling dish is cube structure, one of them side of side's body is active open, the keying of active open (8) is controlled by linkage pull rod, the junction of linkage pull rod lower end and active open is provided with spring, the epimere of linkage pull rod is arranged on horizontal fixed axis, and the upper end of linkage pull rod is provided with flexible handle.
The stage casing of described linkage pull rod is also provided with the loop chain be connected with graded tube together.
The utility model has following beneficial effect:
1, to utilize graded tube can embody stake top filling concrete in time, accurately, intuitively dynamic for this monitor, effectively prevent because influx height controls the super filling of the inaccurate concrete caused, cause pile crown excessive, waste time and energy during cutter pile crown, the quality problems such as added cost consumed above set limit by material, pile crown is off quality, recruitment quantity reduces original 1/3rd, concrete quantity consumed reduces 5 percent, and economic benefit is obvious.With the on average super design elevation 1.0 meters calculating of every pile base concrete influx height, consume above set limit concrete V=3.14*(1.25/2) 2* 1=1.22 cubic meter, the railway engineering Pile Foundations Design quantity of one 40 kilometers about 7000, concrete is wasted 8540 cubic metres (not comprising 1.5 meters, a footpath).
2, whether there are rubble and concrete sample by checking in sampling dish, can judge that whether stake top quality is qualified in time, effectively improve the construction quality on stake top.
Accompanying drawing explanation
Fig. 1 is structural front view of the present utility model;
Fig. 2 is structure top view of the present utility model;
In figure: 1-scale lock, 2-horizontal fixed axis, 3-job platform, 4-graded tube, 5-linkage pull rod, 6-spring, 7-casing, 8-active open, 9-sampling dish.
Detailed description of the invention
By reference to the accompanying drawings, detailed description of the invention of the present utility model is described further:
A kind of underwater concreting absolute altitude monitor as shown in Figure 1, 2, comprise fixed support, graded tube 4 and be provided with the sampling dish 9 of counterweight, described graded tube 4 is vertically installed, the upper end of graded tube 4 to be installed on fixed support by horizontal fixed axis 2 and by scale lock 1 locking, sampling dish 9 is installed on the lower end of graded tube 4 and moves up and down with graded tube 4.Described fixed support comprises back shaft, job platform 3 and casing 7, back shaft and job platform 3 connection in T shape, and the two ends of job platform 3 are supported by casing 7, and described graded tube 4 is connected to the side of job platform 3; Described casing 7 is semicircle globoidal structure, and the inner space of globoidal structure is for installing the device such as graded tube 4, sampling dish 9, and its structure itself serves supporting role.
As shown in Figure 1, described sampling dish 9 is cube structure, 3mm steel plate with holes is adopted to be made, physical dimension is 20*20*10cm, one of them side of side's body is active open 8, and the keying of active open 8 is controlled by linkage pull rod 5, and the junction of linkage pull rod 5 lower end and active open 8 is provided with spring 6, the epimere of linkage pull rod 5 is arranged on horizontal fixed axis 2, and the upper end of linkage pull rod 5 is provided with flexible handle.Linkage pull rod 5 adopts the steel pole of diameter 5mm, and the upper end of steel pole arranges installation by horizontal fixed axis 2, and centre is provided with one loop chain, plays the effect of stable linkage pull rod.The active open of linkage pull rod lower end link sampling dish, upper end link flexible handle, by the switch of hand control sampling dish side active open, handle lower end arranges spring, normal when using spring straining side door close, portable pull bar when needing to open.When monitoring filling concrete height to design height, by the active open on pull bar interlock sampling dish, open lateral opening, press down whole device 10cm, concrete is entered in sampling dish, and then closes active open by pull bar, propose whole device, check whether have rubble and concrete sample in sampling dish, judge that whether stake top quality is qualified.
Because the lock value=horizontal fixed axis absolute altitude-stake top mark of scale lock is high, by lock value and horizontal fixed axis absolute altitude then can convert draw actual measurement hit nail absolute altitude, namely after concrete arrives stake top mark height, touch sampling dish 9, then sampling dish promotes sampling dish along with concrete surface raises again, scale steel pipe upwards promotes, can visual inspection influx height, measured value and design load are contrasted.
Utilize detector described in the utility model, when solving underwater concreting, influx height controls the problems, particularly cost waste problem such as inaccuracy, top concrete be off quality, time-consuming.Therefore, compared with traditional metering system, this high monitor has simple to operate, time saving and energy saving, operating efficiency is high, the feature that improves workmanship, to reduce costs etc.

Claims (5)

1. a underwater concreting absolute altitude monitor, it is characterized in that: comprise fixed support, graded tube (4) and be provided with the sampling dish (9) of counterweight, described graded tube (4) is vertically installed, the upper end of graded tube (4) to be installed on fixed support by horizontal fixed axis (2) and by scale lock (1) locking, sampling dish (9) is installed on the lower end of graded tube (4) and moves up and down with graded tube (4).
2. underwater concreting absolute altitude monitor according to claim 1, it is characterized in that: described fixed support comprises back shaft, job platform (3) and casing (7), back shaft and job platform (3) connection in T shape, the two ends of job platform (3) are supported by casing (7), and described graded tube (4) is connected to the side of job platform (3).
3. underwater concreting absolute altitude monitor according to claim 2, is characterized in that: described casing (7) is semicircle globoidal structure.
4. underwater concreting absolute altitude monitor according to claim 1, it is characterized in that: described sampling dish (9) is cube structure, one of them side of side's body is active open (8), the keying of active open (8) is controlled by linkage pull rod (5), the junction of linkage pull rod (5) lower end and active open (8) is provided with spring (6), the epimere of linkage pull rod (5) is arranged on horizontal fixed axis (2), and the upper end of linkage pull rod (5) is provided with flexible handle.
5. underwater concreting absolute altitude monitor according to claim 4, is characterized in that: the stage casing of described linkage pull rod (5) is also provided with the loop chain be connected with graded tube (4) together.
CN201520750612.2U 2015-09-25 2015-09-25 Irrigation concrete elevation monitor under water Active CN205035836U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520750612.2U CN205035836U (en) 2015-09-25 2015-09-25 Irrigation concrete elevation monitor under water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520750612.2U CN205035836U (en) 2015-09-25 2015-09-25 Irrigation concrete elevation monitor under water

Publications (1)

Publication Number Publication Date
CN205035836U true CN205035836U (en) 2016-02-17

Family

ID=55294748

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520750612.2U Active CN205035836U (en) 2015-09-25 2015-09-25 Irrigation concrete elevation monitor under water

Country Status (1)

Country Link
CN (1) CN205035836U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107255656A (en) * 2017-06-30 2017-10-17 中北大学 The superfilled device of detection concrete that electronics and mechanical detection are integrated in one

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107255656A (en) * 2017-06-30 2017-10-17 中北大学 The superfilled device of detection concrete that electronics and mechanical detection are integrated in one
CN107255656B (en) * 2017-06-30 2023-10-20 中北大学 Concrete detection and overflow device integrating electronic and mechanical detection

Similar Documents

Publication Publication Date Title
CN101832993B (en) Semi-module test box for dynamic compaction reinforced foundation model test
CN101865739B (en) Pre-tightening force dynamic monitoring system for pre-stressed anchor bar strengthening project
CN102704459B (en) Test device of indoor model for reinforcing soft soil foundation by dynamic compaction
CN201666857U (en) Large-scale rockfill confining creep deformation compression instrument
CN205561851U (en) Detect hang down straightness's instrument of form setting
CN108007800A (en) A kind of model test apparatus and test method for circulating the sedimentation of the dynamic load soil body
CN108955495B (en) Tunnel suspension column flange angle measuring tool and angle measuring method
CN105158110A (en) Small size lysimeter suitable for different groundwater depths
CN103470041B (en) The cast-in-place concrete beam template steel pipe support precompressed construction method that adopts loose sand to load
CN107461150A (en) A kind of piling machine for bridge construction
CN107503384A (en) Assembled underground continuous wall penetrating resistance test device
CN202547721U (en) Water regimen monitoring early warning system
CN202194122U (en) Pile top concrete pouring controlling, sampling and warning device
CN205035836U (en) Irrigation concrete elevation monitor under water
CN201520977U (en) Drilling bored pile underwater pouring concrete pile top elevation controller
CN205262472U (en) Novel counter -slope measuring apparatu
CN106013267B (en) A kind of vertical anti-pulling concrete model stake and its method of construction and application
CN117144942A (en) Slope engineering reinforcement state sensing protection monitoring method and system
CN103437385B (en) A kind of transmission iron tower tilt rectification
CN201561729U (en) Concrete pole buried depth measuring device
CN204163120U (en) Excavation of foundation pit space enclosing structure top deformation monitoring device
CN208172969U (en) A kind of high slope surface deformation monitoring and warning system
CN206339363U (en) A kind of simple underground structure Analysis of Buoyancy model test apparatus
CN202865837U (en) Reinforcement core filling structure of prestressed concrete pipe pile
CN206208430U (en) A kind of tension measuring device and system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant