Modular steel construction factory building Download PDFInfo
- Publication number
- CN205000690U CN205000690U CN201520784055.6U CN201520784055U CN205000690U CN 205000690 U CN205000690 U CN 205000690U CN 201520784055 U CN201520784055 U CN 201520784055U CN 205000690 U CN205000690 U CN 205000690U
- Authority
- CN
- China
- Prior art keywords
- projection
- roof
- steel construction
- steel
- chassis
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Joining Of Building Structures In Genera (AREA)
Abstract
The utility model discloses a modular steel construction factory building, roof and wall body including the steel construction, the wall body is formed by stand and the combination of various steel sheet, stand and various steel sheet up end are provided with the projection, it has the round hole upward to open on the projection, the lower part on the roof of steel construction is provided with the upper groove, be provided with the fixed orifices in the upper groove, the epirelief stake pocket advances in the upper groove, the round hole corresponds with the fixed orifices each other, go up the round hole and pass through bolt fastening locking with the fixed orifices, the terminal surface is provided with down the projection under stand and the various steel sheet, the wall body lower extreme is fixed on the chassis on ground, be provided with the low groove on the chassis, the projection block is in the low groove down, the roof upper surface of steel construction is provided with the flashing board. The utility model discloses being closed by roof, wall body and the chassis assembly of steel construction and forming, simple structure is convenient for manufacture and the installation, and the cost has significantly reduced.
Description
Technical field
The utility model relates to building technical field, particularly relates to a kind of combined steel structure workshop.
Background technology
Existing industrial premises has civil structure, brick mix structure, also the various ways such as steel work are had, but existing steel-structure factory building has that construction costs is low, short construction period and the feature such as shockproof properties is good and be widely adopted, but existing steel-structure factory building is primarily of girder steel and support column composition, girder steel and support column are fixed connection by fixture, and roof is connected with by some connectors above girder steel, the mill construction of this steel work is complicated, be not easy to install and manufacture, also improve the cost of the manufacturing.
Utility model content
For the deficiencies in the prior art, the utility model provides a kind of combined steel structure workshop.
To achieve these goals, technical solution adopted in the utility model is:
A kind of combined steel structure workshop, comprise roof and the body of wall of steel work, described body of wall is combined by column and color steel, column and color steel upper surface are provided with projection, upper projection has circular hole, the bottom on the roof of steel work is provided with upper groove, fixing hole is provided with in upper groove, upper projection injects in upper groove, circular hole and fixing hole are mutually corresponding, upper circular hole and fixing hole are bolted locking, column and color steel lower surface are provided with lower projection, body of wall lower end is fixed on the chassis on ground, chassis is provided with low groove, lower projection is fastened in low groove.
The roof upper surface of described steel work is provided with flashing plate.
The beneficial effects of the utility model: compared with prior art, the utility model is combined by the roof of steel work, body of wall and chassis, and structure is simple, is convenient to manufacture and install, and greatly reduces cost.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
Detailed description of the invention
As shown in Figure 1, a kind of combined steel structure workshop, comprise roof 1 and the body of wall 2 of steel work, described body of wall 2 is combined by column and color steel, column and color steel upper surface are provided with projection, upper projection has circular hole, the bottom on the roof 1 of steel work is provided with upper groove, fixing hole is provided with in upper groove, upper projection injects in upper groove, circular hole and fixing hole are mutually corresponding, upper circular hole and fixing hole are bolted locking, column and color steel lower surface are provided with lower projection, body of wall lower end is fixed on the chassis 3 on ground, chassis 3 is provided with low groove, lower projection is fastened in low groove, roof 1 upper surface of described steel work is provided with flashing plate.
The beneficial effects of the utility model: compared with prior art, the utility model is combined by the roof of steel work, body of wall and chassis, and structure is simple, is convenient to manufacture and install, and greatly reduces cost.
Claims (2)
1. a combined steel structure workshop, comprise roof and the body of wall of steel work, it is characterized in that, described body of wall is combined by column and color steel, column and color steel upper surface are provided with projection, upper projection has circular hole, the bottom on the roof of steel work is provided with upper groove, fixing hole is provided with in upper groove, upper projection injects in upper groove, circular hole and fixing hole are mutually corresponding, upper circular hole and fixing hole are bolted locking, column and color steel lower surface are provided with lower projection, body of wall lower end is fixed on the chassis on ground, chassis is provided with low groove, lower projection is fastened in low groove.
2. a kind of combined steel structure workshop as claimed in claim 1, is characterized in that, the roof upper surface of described steel work is provided with flashing plate.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520784055.6U CN205000690U (en) | 2015-10-10 | 2015-10-10 | Modular steel construction factory building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520784055.6U CN205000690U (en) | 2015-10-10 | 2015-10-10 | Modular steel construction factory building |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205000690U true CN205000690U (en) | 2016-01-27 |
Family
ID=55157586
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520784055.6U Expired - Fee Related CN205000690U (en) | 2015-10-10 | 2015-10-10 | Modular steel construction factory building |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205000690U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106894561A (en) * | 2017-04-18 | 2017-06-27 | 中船第九设计研究院工程有限公司 | A kind of detachable steel structure Roof |
CN112593624A (en) * | 2020-12-29 | 2021-04-02 | 高洋 | Assembly type steel structure integrated green building and installation method thereof |
CN113216629A (en) * | 2021-05-19 | 2021-08-06 | 重庆大时代建筑设计有限公司 | Assembly type building construction method |
CN113513080A (en) * | 2021-06-24 | 2021-10-19 | 中国电建集团贵阳勘测设计研究院有限公司 | Integrated assembled steel construction environmental protection building |
-
2015
- 2015-10-10 CN CN201520784055.6U patent/CN205000690U/en not_active Expired - Fee Related
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106894561A (en) * | 2017-04-18 | 2017-06-27 | 中船第九设计研究院工程有限公司 | A kind of detachable steel structure Roof |
CN112593624A (en) * | 2020-12-29 | 2021-04-02 | 高洋 | Assembly type steel structure integrated green building and installation method thereof |
CN113216629A (en) * | 2021-05-19 | 2021-08-06 | 重庆大时代建筑设计有限公司 | Assembly type building construction method |
CN113216629B (en) * | 2021-05-19 | 2022-03-08 | 重庆大时代建筑设计有限公司 | Assembly type building construction method |
CN113513080A (en) * | 2021-06-24 | 2021-10-19 | 中国电建集团贵阳勘测设计研究院有限公司 | Integrated assembled steel construction environmental protection building |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205000690U (en) | Modular steel construction factory building | |
CN201865195U (en) | Novel movable board house | |
CN203022422U (en) | Enclosure with prefabricated structure | |
CN204959995U (en) | Modular structure of room roof beam | |
CN204081067U (en) | A kind of novel building supporting frame with steel structure | |
CN203889956U (en) | Rod-attached-to-wall connecting piece device for tower crane mounting | |
CN206279666U (en) | A kind of aluminium alloy curtain wall connector | |
KR101374162B1 (en) | Endorsement rafters, and a method for manufacturing the same | |
CN202248429U (en) | Open type aluminum board curtain wall system assembled by small units | |
CN204185122U (en) | A kind of crane girder LB board connecting structure of weather proof seepage | |
CN205024953U (en) | Novel side fascia | |
CN203840262U (en) | A solar cell panel fixing support base | |
CN205369599U (en) | Horizontal bed board waterproof node of steel structure industrial workshop wall | |
CN205276487U (en) | Connection structure of light steel prefabricated exterior wall and major structure with adjustable it is three -dimensional | |
CN204983140U (en) | Removal glass steel base reinforced structure for house | |
CN204959980U (en) | Simple to operate's floor connection structure | |
CN203846792U (en) | Power plant wall reinforced structure | |
CN203334716U (en) | Column base accessory for plastic-wood pavilion | |
CN202227607U (en) | Novel gutter structure in steel plate | |
CN203834818U (en) | Roof board and wallboard system | |
CN205063035U (en) | Node structure is fixed to gatepost fossil fragments | |
CN204826295U (en) | Outer wall body supporting member | |
CN201665966U (en) | Railing with hidden-assembled stand columns | |
CN205476293U (en) | Floor installation mechanism | |
CN204185970U (en) | A kind of Novel partition plate |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160127 Termination date: 20181010 |