CN204996184U - Can improve secondary sedimentation tank system that organic waste water goes out quality of water volume - Google Patents

Can improve secondary sedimentation tank system that organic waste water goes out quality of water volume Download PDF

Info

Publication number
CN204996184U
CN204996184U CN201520701858.0U CN201520701858U CN204996184U CN 204996184 U CN204996184 U CN 204996184U CN 201520701858 U CN201520701858 U CN 201520701858U CN 204996184 U CN204996184 U CN 204996184U
Authority
CN
China
Prior art keywords
sedimentation tank
mud
secondary sedimentation
tank
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520701858.0U
Other languages
Chinese (zh)
Inventor
廖亮
张捷
刘亮
蓝裕进
陆宏杰
胡百九
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingtian Material Technology Co Ltd
China National Electric Apparatus Research Institute Co Ltd
Original Assignee
China National Electric Apparatus Research Institute Co Ltd
Guangzhou Kinte Industrial Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China National Electric Apparatus Research Institute Co Ltd, Guangzhou Kinte Industrial Co Ltd filed Critical China National Electric Apparatus Research Institute Co Ltd
Priority to CN201520701858.0U priority Critical patent/CN204996184U/en
Application granted granted Critical
Publication of CN204996184U publication Critical patent/CN204996184U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Separation Of Suspended Particles By Flocculating Agents (AREA)

Abstract

The utility model discloses an one (b) plants can improve secondary sedimentation tank system that organic waste water goes out quality of water volume, including coagulating basin, secondary sedimentation tank and play water catch basin, coagulating basin, secondary sedimentation tank and play water catch basin connect gradually along water flow direction, its characterized in that, secondary sedimentation tank is advection formula sedimentation tank, has the sludge discharging groove of checkdam along pond width setting on its head pool wall, sets up out the mill weir on the afterbody pool wall, and a plurality of sludge hoppers are established to the bottom of the pool, the sludge hopper sets in a row and is covered with the bottom of the pool along the width and the length in pond, and independent mud pipe is all established to every sludge hopper, and the top in pond sets up the walking mud scraper for catch up with the mud scum on the surface of water to sludge discharging groove, make the mud scum keep away from out the mill weir, thereby improve a quality of water volume.

Description

A kind of secondary precipitation cell system improving organic wastewater effluent characteristics
Technical field
The utility model relates to oneplant the secondary precipitation cell system that can improve organic wastewater effluent characteristics.
Background technology
Containing in organic industrial wastewater and organic wastewater treatment process, especially esterification waste water treatment process, organic wastewater first carries out coagulating kinetics again through biochemical treatment.But esterification waste water produces a lot of mud scum after biochemical treatment, after entering coagulation reaction tank, even if interpolation coagulant and flocculant are also difficult to eliminate, thus often have more mud scum in the water of pond.Too much mud scum can be unfavorable for that coagulating affects follow-up sedimentation effect, in order to improve follow-up sedimentation effect, needs the mud scum removing the coagulating basin water surface, to improve follow-up sedimentation effect.Although the mud generated through coagulating can be deposited at the bottom of pond in secondary sedimentation tank major part, also there is many mud to become mud scum and waft and float on the surface.Remove these mud scums floated on the surface that waft if collected not in time, will disperse to drift through mud scum after a period of time and in water, follow water outlet flow away, cause effluent characteristics to be deteriorated, make the COD (COD of water outlet cr), BOD (BOD on the five 5), the content of suspension (SS), total nitrogen (TN) and total phosphorus (TP) all can increase.In order to ensure that standard water discharge often needs to remove the mud scum of the water surface.Current many dependence manually salvages mud scum, not only wastes time and energy, and artificial easily mud scum is broken up when salvaging mud scum to drift in water, to follow water outlet flow away and cause effluent characteristics to be deteriorated.
Conventional rectangular sedimentation tank, only at settling zone head design one mud-removing bucket and extraction mud pipe, arranges driving type mud scraper in pond, and the mud bottom the cleaning shoe expulsion settling zone utilizing driving type mud scraper is in bucket.But, the mud major part that organic wastewater produces through biochemical treatment is anabolite, entered the density of the mud of coagulating postprecipitation bottom settling zone only slightly larger than the density of water, if utilize the cleaning shoe of driving type mud scraper to expel these mud, mud easily floats and causes water muddy, is unfavorable for water purification.In addition, for the mud scum on the water surface, conventional rectangular sedimentation tank utilize more the scum board of driving type mud scraper along the flow direction of water by mud scum expulsion to the scum silica frost groove of pond afterbody, be unfavorable for being separated of water and mud scum like this, affect effluent characteristics.
For these reasons, exploitation is needed onekind effectively to remove mud and mud scum that organic industrial sewage produces after coagulating treatment to improve the secondary precipitation cell system of effluent characteristics.
Utility model content
The purpose of this utility model is to provide oneplant the secondary precipitation cell system that can improve organic wastewater effluent characteristics.
The purpose of this utility model is achieved through the following technical solutions: oneplant the secondary precipitation cell system that can improve organic wastewater effluent characteristics, comprise coagulating basin, secondary sedimentation tank and water outlet collecting-tank, described coagulating basin, secondary sedimentation tank is connected along water (flow) direction successively with water outlet collecting-tank, described secondary sedimentation tank is rectangular sedimentation tank, its head pool wall is arranged the mud drainage slot with checkdam along pond width, afterbody pool wall sets out mill weir, multiple sludge hopper is established at the bottom of pond, described sludge hopper sets in a row along the width in pond and length and is covered with at the bottom of pond, each sludge hopper all establishes independently discharge pipeline, the top in pond arranges walking mud scraper, for the mud scum on the water surface is rushed to mud drainage slot, make mud scum away from effluent weir, be conducive to being separated of mud scum and water.
The utility model arranges mud drainage slot in the head of the secondary sedimentation tank side that namely intakes, and is expelled the mud scum on the water surface in mud drainage slot, make mud scum away from effluent weir, avoid mud scum to enter effluent weir with current, flow in water outlet collecting-tank by walking mud scraper.Arrange in the bottom of secondary sedimentation tank and arrange in a row bucket more and be covered with at the bottom of whole pond, sludge settling is in each sludge hopper, pool bottom sludge is collected without the need to arranging mud scraper, as long as each sludge hopper carries out spoil disposal operation one by one, a density mud slightly larger than water just can be avoided to float, and in pond, the water of clear water zone keeps clarification.Due to above two designs, water is effectively separated with mud and mud scum, improves effluent characteristics.
Further, described effluent weir is downflow weir, and arrange a hole, row's submerged weir bottom it, weir arranges filter screen above hole, effectively tackles mud scum.The aperture of the mesh of described filter screen is 1 ~ 2mm.For improving mud scum interception result, described filter screen arranges 2-5 layer.
Described secondary sedimentation tank is rectangle, and its length direction is water (flow) direction, and length-width ratio is 2 ~ 6 ︰ 1.The plane of described sludge hopper is square or rectangular.Described secondary sedimentation tank discharge pipeline entrance center point distance pond at the bottom of 0.1 ~ 0.2 meter.
Described coagulating basin comprises distribution reservoir, coagulant drug-adding device and flocculant chemicals dosing plant, in described distribution reservoir, water inlet arranges the reaction bucket arranged along pond width, the dam lower than pool inner water face that this reaction bucket has, in bucket, mixer is set, the agent outlet of described coagulant drug-adding device and flocculant chemicals dosing plant struggles against with reaction and is connected, first waste water after biochemical treatment enter in reaction bucket and coagulant and flocculant react overflow again and enter in distribution reservoir, any side of described distribution reservoir except water inlet side arranges the deslagging bucket with checkdam, the top of the checkdam of described deslagging bucket exceeds the water surface 0.1 ~ 0.2 meter.
In described reaction bucket, the flow-stopping plate parallel with reacting the dam that struggles against is set, space in reaction bucket is separated into inhalant region and exhalant region, wherein, space between described flow-stopping plate and water inlet is inhalant region, space between flow-stopping plate and dam is exhalant region, there is spacing thus be communicated with inhalant region and exhalant region bottom described flow-stopping plate and reaction struggle against, described mixer is placed in inhalant region, described coagulant drug-adding device is connected with inhalant region with the agent outlet of flocculant chemicals dosing plant, first waste water after biochemical treatment enter in inhalant region to react with coagulant and flocculant and enter exhalant region and then overflow again in distribution reservoir.
Discharge pipeline is established, at the bottom of the central point of the entrance of described discharge pipeline distance pond 0.1 ~ 0.2 meter bottom described distribution reservoir.
Described water outlet collecting-tank is provided with drainpipe, and pipe is provided with suction pump or outlet conduit valve.
The utility model also comprises sludge concentration tank, and the deslagging bucket of described distribution reservoir is all connected with sludge concentration tank with each discharge pipeline with the mud drainage slot of discharge pipeline, described secondary sedimentation tank, and mud scum and mud discharging are so far carried out concentration.
The utility model can do following improvement: described coagulating basin, secondary sedimentation tank, water outlet collecting-tank and the adjacent setting of sludge concentration tank, connected by porose rectification wall between described coagulating basin and secondary sedimentation tank, described mud drainage slot is arranged on the side wall upper part that porose rectification wall is positioned at secondary sedimentation tank, described water outlet collecting-tank is positioned at the afterbody of secondary sedimentation tank and is connected with secondary sedimentation tank by the partition wall being provided with effluent weir, described sludge concentration tank is positioned at the homonymy of coagulating basin and secondary sedimentation tank and shares body of wall with coagulating basin and secondary sedimentation tank, the floss hole that the deslagging bucket of described coagulating basin is then arranged on the body of wall that is connected with sludge concentration tank is communicated with sludge concentration tank, can from flowing in sludge concentration tank after mud scum enters deslagging bucket, the notch of the mud drainage slot of described secondary sedimentation tank is opened on the body of wall that is connected with sludge concentration tank, from flowing into sludge concentration tank after in pond, mud scum enters mud drainage slot.
Described porose rectification wall is provided with the several rectification hole of a row along secondary sedimentation tank width distribution, the central point of each rectification hole is positioned at the position of at the bottom of distance pond 0.6 ~ 1.2 meter, as the water distribution area of distribution reservoir and secondary sedimentation tank, each rectification hole to be the length of side be square hole of 0.1 ~ 0.2 meter, pitch of holes is 0.2 ~ 0.4 meter.Such setting not only water distribution is effective, can also alleviate the impact of current, is conducive to the sludge settling in secondary sedimentation tank.
the beneficial effects of the utility model are:
1. the head of secondary sedimentation tank of the present utility model arranges mud drainage slot, being driven toward head by the afterbody of mud scum from pond, making it away from afterbody effluent weir, avoiding mud scum to enter in water outlet collecting-tank with current when arranging mud scum.Multiple sludge hopper is established to set in a row along the width in pond and length and be covered with at the bottom of pond at the bottom of pond, sludge settling is in each sludge hopper, pool bottom sludge is collected without the need to arranging mud scraper, each sludge hopper carries out spoil disposal operation one by one, a density mud slightly larger than water is avoided to float, water is effectively separated with mud and mud scum, and in pond, the water of clear water zone keeps clarification, improves effluent characteristics.
2. the effluent weir of secondary sedimentation tank of the present utility model adopts downflow weir, and bottom arranges a hole, row's submerged weir, hole, weir is also arranged 2-5 metafiltration net, improves the interception result of mud scum.
3. distribution reservoir of the present utility model arranges mud-removing bucket, and only the mud scum on the water surface need be driven in deslagging bucket, mud scum can flow automatically and drain, without the need to artificial salvaging, time saving and energy saving.
4. the rectification wall between coagulating basin of the present utility model and secondary sedimentation tank is porose rectification wall, rectification hole centre bore is positioned at the position of at the bottom of distance pond 0.6 ~ 1.2 meter, not only water distribution is effective, also alleviates the impact of current, is conducive to the precipitation of mud in secondary sedimentation tank.
5. secondary precipitation cell system of the present utility model rational in infrastructure simple, effectively interception mud scum improves the water quality of process water outlet, spoil disposal is simple to operate, time saving and energy saving.
Accompanying drawing explanation
Fig. 1 is the top view of the utility model secondary precipitation cell system;
Fig. 2 is that the 1-1 of Fig. 1 is to sectional view;
Fig. 3 is the 1-1 profile of Fig. 1;
Fig. 4 is the 2-2 sectional view of Fig. 1;
Fig. 5 is the 3-3 sectional view of Fig. 1;
Fig. 6 is the 4-4 sectional view of Fig. 1;
In figure: 1. reaction bucket, 2. mixer, 3. discharge pipeline, 4. sludge hopper, 5. downflow weir hole, 6. water outlet collecting-tank, 7. drainpipe, 8. sludge concentration tank, 9. walking mud scraper, 10. mud drainage slot, 11. deslagging buckets, the checkdam of 12. deslagging buckets, 13. distribution reservoirs, rectification hole on 14. porose rectification walls, the walking track of 15. walking mud scrapers, the flap motor of 16. walking mud scrapers, the movable motor of 17. walking mud scrapers, the vulcanite scraper slag plate of 18. walking mud scrapers, 19. porose rectification walls, 20. secondary sedimentation tanks, the checkdam of 21. mud drainage slots, the flow-stopping plate of 22. reaction buckets, the dam of 23. reaction buckets, 24. effluent weirs.
Accompanying drawing does not illustrate operating platform and safety barrier.Pipeline merely illustrates pre-buried pipe section, and other parts pipeline does not illustrate.
Detailed description of the invention
Embodiment in is by reference to the accompanying drawings further described by the utility model below:
The secondary precipitation cell system of improved effluent characteristics is as shown in figures 1 to 6 an embodiment of the present utility model, comprises coagulating basin, secondary sedimentation tank 20, water outlet collecting-tank 6 and sludge concentration tank 8, and these four ponds can independently be arranged.And in order to save the area, coagulating basin, secondary sedimentation tank 20, water outlet collecting-tank 6 and the adjacent setting of sludge concentration tank 8 in the present embodiment.Wherein, coagulating basin, secondary sedimentation tank 20 are connected along water (flow) direction successively with water outlet collecting-tank 6.Connected by porose rectification wall 19 between coagulating basin and secondary sedimentation tank 20, water outlet collecting-tank 6 is positioned at the afterbody of secondary sedimentation tank 20 and is connected with secondary sedimentation tank 20 by the partition wall being provided with effluent weir.Sludge concentration tank 8 is positioned at the homonymy of coagulating basin and secondary sedimentation tank 20 and shares body of wall with coagulating basin and secondary sedimentation tank 20.
Secondary sedimentation tank 20 is rectangular sedimentation tank, and be rectangle pond body, its length direction is water (flow) direction, and length-width ratio is 2 ~ 6 ︰ 1.Porose rectification wall 19 is positioned at secondary sedimentation tank 20 head, its side wall upper part being positioned at secondary sedimentation tank 20 arranges the mud drainage slot 10 with checkdam 21 along pond width, the floss hole of mud drainage slot 10 is opened on the body of wall that is connected with sludge concentration tank 8, from flowing into sludge concentration tank 8 after in pond, mud scum enters mud drainage slot 10.The afterbody partition wall of secondary sedimentation tank 20 sets out mill weir 24, and this effluent weir 24 is downflow weir, and arrange row's submerged downflow weir hole 5 bottom it, weir arranges filter screen above hole, effectively to tackle mud scum.The aperture of sieve meshes is 1 ~ 2mm.For improving mud scum interception result, filter screen arranges 2-5 layer.Establish multiple sludge hopper 4 at the bottom of pond, its plane is rectangle.All sludge hoppers 4 set in a row along the width in pond and length and are covered with at the bottom of pond, and each sludge hopper 4 all establishes independently discharge pipeline 3, and the central point of discharge pipeline 3 entrance is arranged at the position of at the bottom of distance pond 0.1 ~ 0.2 meter.The top in pond arranges walking mud scraper 9, for the mud scum on the water surface is rushed to mud drainage slot 10, makes mud scum away from effluent weir, is conducive to being separated of mud scum and water.Walking mud scraper 9 comprises Slag Scraping Device, walking track 15 and electric controller, walking track 15 is arranged on the both sides lip on body length direction, pond, Slag Scraping Device is across pond body and two ends are slidably mounted on the walking track 15 of body both sides, pond respectively, and electric controller then controls Slag Scraping Device walking.Slag Scraping Device comprises support, is arranged on the pulley at support two ends, movable motor 17, flap motor 16 and vulcanite scraper slag plate 18, and the pulley at support two ends is arranged on the walking track 15 of body both sides, pond.Movable motor 17, flap motor 16 and vulcanite scraper slag plate 18 are rack-mount, and movable motor 17 is responsible for the advance of Slag Scraping Device or the walking of retrogressing, and flap motor 16 is responsible for vulcanite scraper slag plate 18 to reverse to hold high when Slag Scraping Device retreats, make it higher than the water surface.
Coagulating basin comprises distribution reservoir 13, coagulant drug-adding device and flocculant chemicals dosing plant.Distribution reservoir 13 is connected by porose rectification wall 19 with secondary sedimentation tank 20, and distribution reservoir 13 is less than secondary sedimentation tank 20, and its long limit is the broadside of secondary sedimentation tank 20.Porose rectification wall 19 is provided with the several rectification hole 14 of a row along secondary sedimentation tank width distribution, and the central point in hole is positioned at the position of at the bottom of distance pond 0.6 ~ 1.2 meter, as the water distribution area of distribution reservoir 13 and secondary sedimentation tank 20.Each rectification hole 14 to be length of sides be square hole of 0.1 ~ 0.2 meter, pitch of holes is 0.2 ~ 0.4 meter, and such setting not only water distribution is effective, can also alleviate the impact to current, is conducive to the sludge settling in secondary sedimentation tank 20.The pool wall that distribution reservoir 13 is relative with porose rectification wall 19 establishes water inlet, for connecting water inlet pipe in that side away from sludge concentration tank 8.With water inlet side, the reaction bucket 1 arranged along pond width is set, the dam 23 lower than pool inner water face that this reaction bucket 1 has in pond, in bucket, the flow-stopping plate 22 parallel with dam 23 is set, space in reaction bucket 1 is separated into inhalant region and exhalant region.Wherein, the space between flow-stopping plate 22 and water inlet is inhalant region, and the space between flow-stopping plate and dam is exhalant region, and flow-stopping plate 22 has spacing with bottom reaction bucket 1 thus is communicated with inhalant region and exhalant region.Arrange mixer 2 in inhalant region, coagulant drug-adding device is connected with inhalant region with the agent outlet of flocculant chemicals dosing plant.First waste water after biochemical treatment enter in inhalant region to react with coagulant and flocculant and enter exhalant region and then overflow again in distribution reservoir 13.Distribution reservoir 13 also arranges the deslagging bucket 11 with checkdam 12, and this deslagging bucket 11 is arranged on and shares on body of wall with sludge concentration tank 8, shares on body of wall and establishes breach as floss hole, make the longitudinal section of deslagging bucket 11 for " ".Extend to axial plane in distribution reservoir 13 bottom deslagging bucket 11, the top of the checkdam 12 of deslagging bucket 11 exceeds the water surface 0.1 ~ 0.2 meter, and the floss hole of deslagging bucket 11 is opened on shared body of wall, can from flowing in sludge condensation after mud scum enters deslagging bucket 11.Discharge pipeline 3 is established, at the bottom of the central point of the entrance of discharge pipeline 3 distance pond 0.1 ~ 0.2 meter bottom distribution reservoir 13.
The drainpipe 7 of water outlet collecting-tank 6 is provided with suction pump or outlet conduit valve.
method for treating water:
While the waste water after biochemical treatment enters the reaction bucket 1 of coagulating basin, start mixer 2, coagulant medicine system adds appropriate coagulant simultaneously, flocculant medicine system adds appropriate flocculant simultaneously, waste water outflow in reaction bucket 1 after coagulating enters distribution reservoir 13, then the buffering area of secondary sedimentation tank 20 is entered through porose rectification wall 19, then arrive settling zone and carry out mud-water separation, pass downflow weir hole 5 and screen pack after arriving secondary sedimentation tank 20 afterbody, then overflow in water outlet collecting-tank 6.
Mud major part after settling zone carries out mud-water separation can be deposited to the sludge hopper 4 at the bottom of pond, and part floccule becomes mud scum and wafts and float on the surface.Carry out the eliminating mud scum operation of 1-2 time every day.Get rid of the operation of mud scum: the water level being promoted secondary sedimentation tank 20 by the suction pump or outlet conduit valve controlling water outlet collecting-tank 6, when the checkdam of water level a little more than deslagging bucket 11 and mud drainage slot 10, mud scum first on artificial expulsion distribution reservoir 13 water surface is to deslagging bucket 11, and mud scum is from flowing in sludge concentration tank 8.After treating the mud scum expulsion on distribution reservoir 13 water surface, start slag-scraper 9, slag-scraper 9 is advanced toward the direction of secondary sedimentation tank 20 head expulsion mud scum, simultaneously by artificial by the expulsion of the mud scum of secondary sedimentation tank 20 to mud drainage slot 10, mud scum enters sludge concentration tank 8 from flowing to floss hole.Closing Slag Scraping Device when slag-scraper 9 arrives mud scum mud drainage slot 10 side, continuing by manually mud scum being expelled into mud drainage slot 10.After completing the operation of first round expulsion mud scum, start slag-scraper 9 and make the afterbody retreating to thereafter secondary sedimentation tank 20.Expulsion work repeatedly can be carried out according to actual needs in succession, until water surface mud scum is got rid of clean.After being expelled by the mud scum of secondary sedimentation tank 20, start the mud of the sludge hopper 4 of discharge at the bottom of pond one by one.Before operation, first check and will guarantee that first is wanted discharge pipeline 3 valve of the sludge hopper 4 of spoil disposal to be in open mode, then starts slush pump, extracting the mud in discharge sludge hopper 4.After often exhausting the mud of a bucket, first open discharge pipeline 3 valve of next sludge hopper 4, then discharge pipeline 3 valve is closed in pass, namely will guarantee have discharge pipeline 3 valve to be in open mode in mud discharging process.After mud discharging completes, the suction pump recovering water outlet collecting-tank 6, to automatic starting state, opens outlet conduit valve, to drain the water of water outlet collecting-tank 6 in good time.Spoil disposal operation General Requirements day shift and the middle class in a kindergarten are respectively taken out mud one and are taken turns, and expel the operation of mud scum must front, after taking out the operating in of mud, can extend hydraulic detention time like this, improve the water quality of water outlet.
The utility model is not limited to above-mentioned detailed description of the invention; according to foregoing; according to ordinary technical knowledge and the customary means of this area; do not departing under the utility model above-mentioned basic fundamental thought prerequisite; the utility model can also make the equivalent modifications of other various ways, replacement or change, all drops among protection domain of the present utility model.

Claims (9)

1. one kind can be improved the secondary precipitation cell system of organic wastewater effluent characteristics, comprise coagulating basin, secondary sedimentation tank and water outlet collecting-tank, described coagulating basin, secondary sedimentation tank is connected along water (flow) direction successively with water outlet collecting-tank, it is characterized in that, described secondary sedimentation tank is rectangular sedimentation tank, its head pool wall is arranged the mud drainage slot with checkdam along pond width, afterbody pool wall sets out mill weir, multiple sludge hopper is established at the bottom of pond, described sludge hopper sets in a row along the width in pond and length and is covered with at the bottom of pond, each sludge hopper all establishes independently discharge pipeline, the top in pond arranges walking mud scraper, for the mud scum on the water surface is rushed to mud drainage slot, make mud scum away from effluent weir.
2. the secondary precipitation cell system improving organic wastewater effluent characteristics according to claim 1, it is characterized in that, described effluent weir is downflow weir, and arrange a hole, row's submerged weir bottom it, weir arranges filter screen above hole.
3. the secondary precipitation cell system improving organic wastewater effluent characteristics according to claim 1, it is characterized in that, described coagulating basin comprises distribution reservoir, coagulant drug-adding device and flocculant chemicals dosing plant, in described distribution reservoir, water inlet arranges the reaction bucket arranged along pond width, the dam lower than pool inner water face that this reaction bucket has, in bucket, mixer is set, the agent outlet of described coagulant drug-adding device and flocculant chemicals dosing plant struggles against with reaction and is connected, first waste water after biochemical treatment enter in reaction bucket and coagulant and flocculant react overflow again and enter in distribution reservoir, any side of described distribution reservoir except water inlet side arranges the deslagging bucket with checkdam.
4. the secondary precipitation cell system improving organic wastewater effluent characteristics according to claim 3, it is characterized in that, in described reaction bucket, the flow-stopping plate parallel with reacting the dam that struggles against is set, space in reaction bucket is separated into inhalant region and exhalant region, wherein, space between described flow-stopping plate and water inlet is inhalant region, space between flow-stopping plate and dam is exhalant region, there is spacing thus be communicated with inhalant region and exhalant region bottom described flow-stopping plate and reaction struggle against, described mixer is placed in inhalant region, described coagulant drug-adding device is connected with inhalant region with the agent outlet of flocculant chemicals dosing plant, first waste water after biochemical treatment enter in inhalant region to react with coagulant and flocculant and enter exhalant region and then overflow again in distribution reservoir.
5. the secondary precipitation cell system of the improved organic wastewater effluent characteristics according to claim 3 or 4, it is characterized in that, also comprise sludge concentration tank, the deslagging bucket of described distribution reservoir is all connected with sludge concentration tank with each discharge pipeline with the mud drainage slot of discharge pipeline, described secondary sedimentation tank, and mud scum and mud discharging are so far carried out concentration.
6. the secondary precipitation cell system improving organic wastewater effluent characteristics according to claim 5, it is characterized in that, described coagulating basin, secondary sedimentation tank, water outlet collecting-tank and the adjacent setting of sludge concentration tank, connected by porose rectification wall between described coagulating basin and secondary sedimentation tank, described mud drainage slot is arranged on the side wall upper part that porose rectification wall is positioned at secondary sedimentation tank, described water outlet collecting-tank is positioned at the afterbody of secondary sedimentation tank and is connected with secondary sedimentation tank by the partition wall being provided with effluent weir, described sludge concentration tank is positioned at the homonymy of coagulating basin and secondary sedimentation tank and shares body of wall with coagulating basin and secondary sedimentation tank, the floss hole that the deslagging bucket of described coagulating basin is then arranged on the body of wall that is connected with sludge concentration tank is communicated with sludge concentration tank, from flowing in sludge concentration tank after mud scum enters deslagging bucket, the notch of the mud drainage slot of described secondary sedimentation tank is opened on the body of wall that is connected with sludge concentration tank, from flowing into sludge concentration tank after in pond, mud scum enters mud drainage slot.
7. the secondary precipitation cell system improving organic wastewater effluent characteristics according to claim 6, it is characterized in that, described porose rectification wall is provided with the several rectification hole of a row along secondary sedimentation tank width distribution, the central point of rectification hole is positioned at the position of at the bottom of distance pond 0.6 ~ 1.2 meter, as the water distribution area of distribution reservoir and secondary sedimentation tank, each rectification hole to be the length of side be square hole of 0.1 ~ 0.2 meter, pitch of holes is 0.2 ~ 0.4 meter.
8. the secondary precipitation cell system improving organic wastewater effluent characteristics according to claim 6, is characterized in that, establish discharge pipeline bottom described distribution reservoir, at the bottom of the central point of the entrance of described discharge pipeline distance pond 0.1 ~ 0.2 meter.
9. the secondary precipitation cell system improving organic wastewater effluent characteristics according to claim 6, is characterized in that, described water outlet collecting-tank is provided with drainpipe, and pipe is provided with suction pump or outlet conduit valve.
CN201520701858.0U 2015-09-11 2015-09-11 Can improve secondary sedimentation tank system that organic waste water goes out quality of water volume Active CN204996184U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520701858.0U CN204996184U (en) 2015-09-11 2015-09-11 Can improve secondary sedimentation tank system that organic waste water goes out quality of water volume

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520701858.0U CN204996184U (en) 2015-09-11 2015-09-11 Can improve secondary sedimentation tank system that organic waste water goes out quality of water volume

Publications (1)

Publication Number Publication Date
CN204996184U true CN204996184U (en) 2016-01-27

Family

ID=55153090

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520701858.0U Active CN204996184U (en) 2015-09-11 2015-09-11 Can improve secondary sedimentation tank system that organic waste water goes out quality of water volume

Country Status (1)

Country Link
CN (1) CN204996184U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105107241A (en) * 2015-09-11 2015-12-02 广州擎天材料科技有限公司 Secondary sedimentation tank system capable of improving organic wastewater effluent quality and processing method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105107241A (en) * 2015-09-11 2015-12-02 广州擎天材料科技有限公司 Secondary sedimentation tank system capable of improving organic wastewater effluent quality and processing method

Similar Documents

Publication Publication Date Title
CN105107241B (en) Secondary sedimentation tank system capable of improving organic wastewater effluent quality and processing method
CN201848131U (en) Table-flap type multi-stage mud-discharge settling tank applied to sewage treatment
CN105089133A (en) Automatic hydraulic-control initial rainwater diverting device
CN105129969B (en) Perimeter filter water outlet biochemical sedimentation basin
CN210481129U (en) Urban inland river sewage treatment system
CN103755085B (en) Device and method for removing algal bloom and purifying algae source in branch reservoir bay of channel reservoir
CN204996184U (en) Can improve secondary sedimentation tank system that organic waste water goes out quality of water volume
CN203878648U (en) Multifunctional rainwater collecting system
CN201971694U (en) Flotation-sedimentation tank with sideward flow inclined plate
CN203269678U (en) Sewage treatment device
CN205170615U (en) District sanitary sewage treatment system
CN209853876U (en) Integrated grease separation water purifier
CN113797606A (en) Rectangular peripheral inlet and outlet sedimentation tank with optimized water inlet and outlet and sludge discharge modes
CN203281084U (en) Anti-blocking precipitator
CN207031205U (en) A kind of sewage processing filtering device
JPH10277311A (en) Water treatment method, water collecting trough with scum passage, and water treatment facility using the same
CN108164038A (en) A kind of Water feeding treatment device and processing method
RU2137884C1 (en) System for carrying-away and purification of surface effluent
CN203803164U (en) Efficient mud-water separation precipitation system
KR102067998B1 (en) A scum collecting device capable of automatic water level tracking and scum collection using buoyancy
CN204447427U (en) A kind of rectangular sedimentation tank
CN208561942U (en) A kind of Water feeding treatment device
CN207877308U (en) A kind of highly integrated air-floating apparatus
RU2404137C1 (en) Cleaning installation of storm water sewage in urban terrain
CN2448822Y (en) Composite sewage treatment equipment

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 510860 Yufeng Road, Shiling Town, Huadu District, Guangzhou City, Guangdong Province

Co-patentee after: China Electrical Appliance Research Institute Co., Ltd.

Patentee after: Guangzhou Kinte Industrial Co., Ltd.

Address before: 510860 Yufeng Road, Shiling Town, Huadu District, Guangzhou City, Guangdong Province

Co-patentee before: China National Electric Apparatus Research Institute Co., Ltd.

Patentee before: Guangzhou Kinte Industrial Co., Ltd.

CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: No.5 Lisha East Road, Shatian Town, Dongguan City, Guangdong Province 523000

Co-patentee after: China Electrical Appliance Research Institute Co.,Ltd.

Patentee after: Qingtian Material Technology Co., Ltd

Address before: Shiling Town, Huadu District, Guangzhou City, Guangdong province 510860 Yufeng Road No. 16

Co-patentee before: China Electrical Appliance Research Institute Co.,Ltd.

Patentee before: GUANGZHOU KINTE INDUSTRIAL Co.,Ltd.