- CN204983100U CN204983100U CN201520498472.4U CN201520498472U CN204983100U CN 204983100 U CN204983100 U CN 204983100U CN 201520498472 U CN201520498472 U CN 201520498472U CN 204983100 U CN204983100 U CN 204983100U
- Authority
- CN
- China
- Prior art keywords
- well
- shaft
- pipeline
- inspection
- riverbed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000007689 inspection Methods 0.000 title claims abstract description 33
- 238000012423 maintenance Methods 0.000 abstract description 8
- 238000010276 construction Methods 0.000 abstract description 7
- 239000010865 sewage Substances 0.000 description 10
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 5
- 238000010586 diagram Methods 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000004140 cleaning Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000001514 detection method Methods 0.000 description 1
- 230000002349 favourable effect Effects 0.000 description 1
- 230000000737 periodic effect Effects 0.000 description 1
- 230000001105 regulatory effect Effects 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Landscapes
- Sewage (AREA)
Abstract
The utility model discloses an inspection well, inspection well include pit shaft (1) and with well room (2) of the lower extreme intercommunication of pit shaft (1), follow pipeline (3) of laying in the riverbed the well room is passed in (2). The pit shaft passes from the well is indoor with well room intercommunication, the pipeline of laying in the riverbed among the above -mentioned technical scheme to make things convenient for the maintenance of riverbed interior conduit. To the construction of whole section dirty pipeline, inspection well's position may produce the occupation of land of minute quantity, and other most occupations of land all are located the riverbed to both can reduce the occupation of land scope of pipeline laying, and also solve the pipeline in the riverbed and overhauld inconvenient problem, and be applicable to the river course and cut and take up an area of the restricted condition in the dirty engineering.
Description
Technical Field
The utility model relates to an underground drainage detection facility specifically relates to an inspection shaft.
Background
Inspection wells, commonly known as "inspection wells", are commonly located at junctions of drainage pipes, bends, pipe diameter or slope changes, drops, and linear pipe sections at intervals, and are drainage attachment structures for periodic inspection, cleaning, and dredging of pipes. The inspection well is mainly divided into a sewage (waste) water inspection well and a rainwater inspection well. Because the pipe sections between two adjacent wells are on the same straight line, inspection wells are required to be arranged at the positions of changing the section of the pipeline, changing the gradient, meeting and changing the elevation, and the inspection wells are required to be arranged on the overlong straight pipe sections in sections (the section spacing is regulated according to the diameter of the pipeline and the types of rain and sewage).
However, under the influence of too fast city construction, the original sewage outlets on the two banks of the river channel are often limited in occupied space position when sewage intercepting pipelines are laid in the later period, and the high removal and occupation cost is often generated when the river channel with more buildings on the two banks is particularly serious. In addition, the sewage intercepting pipelines laid in the riverway and the riverway side slope often have the defect of inconvenient maintenance because inspection wells cannot be built according to the standard.
In view of the above-mentioned shortcomings of the prior art, there is a need for a new type of manhole.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing an inspection shaft to there is the inconvenient problem of maintenance in the pipeline of laying in the river course in the solution.
In order to achieve the above object, the present invention provides an inspection well, which comprises a shaft and a well chamber communicated with the lower end of the shaft, wherein a pipeline laid in the river bed passes through the well chamber.
Preferably, the shaft is vertically disposed within a bank protection.
Preferably, the upper end of the shaft is provided with an inlet hole for access of service personnel, and the inlet hole is closed by a well cover.
Preferably, an inlet hole for access of a service person is formed in the upper end of the shaft, the inspection well further comprises an extension well which extends upwards from the upper end of the shaft and is communicated with the shaft, and the upper end of the extension well is sealed by the well cover.
Preferably, the extension well protrudes upward beyond an upper surface of the bank protection slope.
Preferably, the well chamber extends from a lower end of the wellbore into the river bed.
Preferably, the cross-section of the well chamber taken perpendicular to the direction of extension of the well chamber is rectangular, circular or domed rectangular.
Preferably, a sump is provided on the bottom surface of the well chamber.
Preferably, the sump is located below the wellbore.
In the technical scheme, the shaft is communicated with the well chamber, and the pipeline laid in the river bed passes through the well chamber, so that the pipeline in the river bed can be maintained conveniently. To the construction of whole sewage intercepting pipeline, the position of inspection shaft probably produces very little occupation of land, and other most take up an area of and all are located the riverbed to both can reduce the occupation of land scope of pipe laying, also solved the inconvenient problem of pipeline maintenance in the riverbed, be applicable to the river course and intercept the restricted condition of occupation of land in the engineering.
Other features and advantages of the present invention will be described in detail in the detailed description which follows.
Drawings
The accompanying drawings, which are included to provide a further understanding of the invention and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention and together with the description serve to explain the principles of the invention and not to limit the invention. In the drawings:
FIG. 1 is a schematic diagram of an embodiment of an inspection well configuration;
FIG. 2 is a schematic diagram of another embodiment of an inspection well.
Wherein,
1 shaft 2 well chamber
3 inlet hole of pipe 4
5 sump 6 river bank protection slope
7 well lid 8 extends well
Detailed Description
The following detailed description of the embodiments of the present invention will be made with reference to the accompanying drawings. It is to be understood that the description of the embodiments herein is for purposes of illustration and explanation only and is not intended to limit the invention.
The utility model provides an inspection well, this inspection well include pit shaft 1 and with the well chamber 2 of the lower extreme intercommunication of pit shaft 1, lay pipeline 3 in the riverbed and pass from well chamber 2. The shaft 1 is communicated with the well chamber 2, and a pipeline laid in the river bed penetrates through the well chamber 2, so that the pipeline in the river bed can be maintained conveniently. To the construction of whole sewage interception pipeline, the position of inspection shaft probably produces very little occupation of land, and other most occupation of land all are located the riverbed to both can reduce the occupation of land scope of pipe laying, also solved the inconvenient problem of pipeline maintenance in the riverbed, be applicable to the restricted condition of occupation of land among the river course sewage interception engineering.
Specifically, as shown in fig. 1 and 2, the shaft 1 is vertically disposed within the bank protection 6. An inlet hole 4 for the entry and exit of the inspection person is provided at the upper end of the shaft 1, and the inlet hole 4 is closed by a well lid 7. A service person can enter the manhole from the entry hole 4 on the bank and through the shaft 1 into the well chamber 2 to facilitate maintenance of the conduit in the bed. In another embodiment, the upper end of the shaft 1 is provided with an inlet hole 4 for access of service personnel, and the inspection well further comprises an extension well 8 extending upwards from the upper end of the shaft 1 and communicating with the shaft 1, and a well cover 7 closing the upper end of the extension well 8. The arrangement of the extension shaft 8 is determined according to the structure of the bank protection slope 6 and the depth of the upper end of the shaft 1. Also, the extension well 8 preferably protrudes upward beyond the upper surface of the bank protection 6 to facilitate maintenance of the inspection well.
Further, the well chamber 2 extends from the lower end of the shaft 1 into the river bed, thereby forming an "L" shaped structure. The cross-section of the well chamber 2 taken perpendicular to said extension direction of the well chamber is rectangular, circular or domed rectangular. The round top rectangle is a rectangle with the upper side replaced by an arc, namely a figure formed by connecting the arc and three straight line segments end to end. The pipeline 3 laid in the river bed passes through the well chamber 2, and maintainers can enter the well chamber 2 to overhaul the pipeline 3.
In addition, a water collecting pit 5 is arranged on the bottom surface of the well chamber 2, and accumulated water in the well chamber 2 can flow into the water collecting pit 5, so that accumulated water on the bottom surface of the well chamber 2 (especially the bottom surface close to the pipeline 3) is prevented, and the overhaul work of maintainers is facilitated. In particular, the sump 5 is located below the shaft 1, away from the pipes 3 laid in the river bed.
The pipeline 3 is a sewage intercepting pipeline which is laid in a riverbed along a river channel and is 2-3 m away from the side line of the river. To the construction of whole sewage intercepting pipeline, the position of inspection shaft probably produces very little occupation of land, and other most take up an area of and all are located the riverbed to both can reduce the occupation of land scope of pipe laying, also solved the inconvenient problem of pipeline maintenance in the riverbed, be applicable to the river course and intercept the restricted condition of occupation of land in the engineering. For example, the river course base current in northern area is less, and construction convenience adopts in the river course the utility model discloses an inspection shaft is favorable to city pipeline construction very much.
The preferred embodiments of the present invention have been described in detail with reference to the accompanying drawings, however, the present invention is not limited to the details of the above embodiments, and the technical concept of the present invention can be within the scope of the present invention to perform various simple modifications to the technical solution of the present invention, and these simple modifications all belong to the protection scope of the present invention.
It should be noted that the various features described in the above embodiments may be combined in any suitable manner without departing from the scope of the invention. In order to avoid unnecessary repetition, the present invention does not separately describe various possible combinations.
In addition, various embodiments of the present invention can be combined arbitrarily, and the disclosed content should be regarded as the present invention as long as it does not violate the idea of the present invention.
Claims (9)
1. The inspection well is characterized by comprising a shaft (1) and a well chamber (2) communicated with the lower end of the shaft (1), wherein a pipeline (3) laid in a river bed penetrates through the well chamber (2).
2. The manhole according to claim 1, wherein the shaft (1) is vertically arranged in a bank protection (6).
3. An inspection shaft according to claim 2, characterized in that the upper end of the shaft (1) is provided with an access opening (4) for access by service personnel, the access opening (4) being closed by a well cover (7).
4. An inspection shaft according to claim 2, characterized in that the upper end of the shaft (1) is provided with an inlet hole (4) for access by service personnel, and that the inspection shaft further comprises an extension shaft (8) extending upwardly from the upper end of the shaft (1) and communicating with the shaft (1), and that a well cover (7) closes the upper end of the extension shaft (8).
5. The manhole according to claim 4, wherein the extension shaft (8) protrudes upwards beyond the upper surface of the bank protection (6).
6. The manhole according to claim 2, wherein the well chamber (2) extends from the lower end of the shaft (1) into the river bed.
7. The manhole according to claim 6, wherein the cross section of the well (2) taken perpendicular to the extension direction of the well is rectangular, circular or domed rectangular.
8. The manhole according to any of claims 1 to 7, wherein a sump (5) is provided on the bottom surface of the well (2).
9. The manhole according to claim 8, wherein the sump (5) is located below the shaft (1).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520498472.4U CN204983100U (en) | 2015-07-10 | 2015-07-10 | Inspection well |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520498472.4U CN204983100U (en) | 2015-07-10 | 2015-07-10 | Inspection well |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204983100U true CN204983100U (en) | 2016-01-20 |
Family
ID=55117482
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520498472.4U Active CN204983100U (en) | 2015-07-10 | 2015-07-10 | Inspection well |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204983100U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106049542A (en) * | 2016-07-29 | 2016-10-26 | 上海市政工程设计研究总院(集团)有限公司 | Arrangement method for drainage inspection wells applied to comprehensive pipe rack |
CN106223448A (en) * | 2016-07-29 | 2016-12-14 | 上海市政工程设计研究总院(集团)有限公司 | A kind of method to set up being applied to the rain of pipe gallery, sewage inspection well |
CN109706970A (en) * | 2018-12-12 | 2019-05-03 | 金华电力设计院有限公司 | A kind of prefabricated square cable active well |
CN112554125A (en) * | 2020-12-11 | 2021-03-26 | 北京市水利规划设计研究院 | Water conservancy corridor subassembly and water conservancy facility |
-
2015
- 2015-07-10 CN CN201520498472.4U patent/CN204983100U/en active Active
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106049542A (en) * | 2016-07-29 | 2016-10-26 | 上海市政工程设计研究总院(集团)有限公司 | Arrangement method for drainage inspection wells applied to comprehensive pipe rack |
CN106223448A (en) * | 2016-07-29 | 2016-12-14 | 上海市政工程设计研究总院(集团)有限公司 | A kind of method to set up being applied to the rain of pipe gallery, sewage inspection well |
CN106223448B (en) * | 2016-07-29 | 2024-03-08 | 上海市政工程设计研究总院(集团)有限公司 | Setting method of rain and sewage inspection well applied to comprehensive pipe rack |
CN109706970A (en) * | 2018-12-12 | 2019-05-03 | 金华电力设计院有限公司 | A kind of prefabricated square cable active well |
CN112554125A (en) * | 2020-12-11 | 2021-03-26 | 北京市水利规划设计研究院 | Water conservancy corridor subassembly and water conservancy facility |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204983100U (en) | Inspection well | |
CN106836285B (en) | Building informatization-based underground pipe gallery monitoring waterproof structure | |
CN205688461U (en) | Pipe gallery section structure | |
CN211621640U (en) | Well water circulating system of foundation pit dewatering well | |
CN102587486A (en) | Hidden-buried sewage interception facility inside river bank | |
CN206971351U (en) | Miscellaneous inlet for stom water is cut on a kind of integral type road surface | |
CN107542152B (en) | A kind of pavement comprehensive pipe network drainage system | |
CN202767227U (en) | Retaining self-rinsing device for drainage inverted siphon | |
CN207260284U (en) | One kind shunting anti-blockage type road drainage pipeline | |
CN204001140U (en) | The one gradient formula transformer station raceway groove drainage system that catchments | |
CN110029721A (en) | A kind of combine with the pipe culvert of blowdown and first rain Regulation Function cuts dirty structure | |
CN216379363U (en) | System for directly intercepting sewage from rainwater outlet in river channel | |
CN106869236B (en) | Horizontal storage tank for sponge urban rainwater collection system and construction method of horizontal storage tank | |
CN103628562B (en) | A kind of retaining from flusher for draining inverted siphon | |
CN205369374U (en) | Rainwater cyclic utilization system | |
CN205134332U (en) | Municipal administration delivery pipeline hole groove supporting construction | |
CN210238709U (en) | Reduce drainage structure of utility tunnel sump pit quantity | |
CN205935150U (en) | Rain water pipe assembly | |
CN102587487B (en) | Inflow energy dissipation, exhaust and outflow multifunctional combined well with regulating storage pipe | |
CN209975299U (en) | Municipal administration is with quick drainage device in road surface | |
CN207130751U (en) | Water guide pipe network device for dredging underground water around underground building | |
CN207295964U (en) | A kind of horizontal prefabricated pumping plant of integration | |
KR101151090B1 (en) | Keeping treatment system for primary stage rainwater using the water-storage tank | |
CN207846474U (en) | A kind of conversion well for drawing comb evacuation rain sewage pipe for pipe gallery | |
CN207776075U (en) | The trapped well of transformer collection oil pit by through hole |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |