CN204975846U - Ram quick -witted basic cantilever crane group by force to frock - Google Patents
Ram quick -witted basic cantilever crane group by force to frock Download PDFInfo
- Publication number
- CN204975846U CN204975846U CN201520666128.1U CN201520666128U CN204975846U CN 204975846 U CN204975846 U CN 204975846U CN 201520666128 U CN201520666128 U CN 201520666128U CN 204975846 U CN204975846 U CN 204975846U
- Authority
- CN
- China
- Prior art keywords
- underframe
- frock
- bearing pin
- hook
- cantilever crane
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Jib Cranes (AREA)
Abstract
The utility model discloses a ram quick -witted basic cantilever crane group by force to frock, including chassis, vertical installation spacing stand and the at least two piece crossbeams of horizontal installation at the chassis upper surface in chassis one side, the height of spacing stand reduces from a left side to the right side for the chassis in proper order, spacing stand top installation level round pin axle, the axis direction of round pin axle is the same with chassis length direction, sell epaxial fixed mounting and hold in the palm the hook, through using the crossbeam, spacing stand and three chord member location of asking the hook as basic cantilever crane, can through behind the position of definite three chord members and measurement angle and the position that obtains the web member, and with an other chord member and fixed web member welding, accomplish the assembly welding of basic cantilever crane, through using this frock, can effectively improve assembly welding efficiency, improve the interchangeability of basic cantilever crane, the strong machine that rams maintains cost is reduced, improve basic cantilever crane straightness accuracy, wholly assemble diagonal and angle, the reduction is to the reliance of workman's technical ability, improve the assembly welding precision.
Description
Technical field
The utility model relates to dynamic compaction machinery mounting technology field, particularly relates to a kind of dynamic compaction machinery basis jib group to frock.
Background technology
Along with Industrial Engineering maximizes and the development of hugeization, at equipment manufacturing, project installation aspect, lifted load is allowed to require progressively to improve to crane, crane or dynamic compaction machinery all utilize swing arm as supporting construction, but, along with the raising of lifted load, also more and more higher to swing arm requirement of strength, swing arm own wt also progressively improves, limit the raising of crane or dynamic compaction machinery lifted load to a certain extent, for this reason, some cranes maximized and dynamic compaction machinery all start to adopt steel truss type boom structure, on the one hand, steel truss structure is under the prerequisite that can meet support strength, sole mass declines greatly, in addition on the one hand, steel truss subsection setup, weight can be played according to difference and carry out length adjustment, expand the scope of application of crane, meet the requirement of equipment manufacturing and the maximization of project installation aspect and huge equalization.
The basic jib of general steel truss type swing arm comprises the web member that four rhizospheres become the chord member of truncated rectangular pyramids shape and are fixedly welded between four chord members, in concrete installation process, substantially the right mode of artificial group is adopted to weld at present, this kind of mode exists in the middle of making that jib linearity is overproof, overall package diagonal is overproof, angle is incorrect, group is inclined, can not exchange, production efficiency is low, the shortcomings such as high are required to craftsmanship, and the group affecting connector is scrapped causing time serious, causes waste of raw materials.
Utility model content
Technical problem to be solved in the utility model is to provide a kind of dynamic compaction machinery basis jib group to frock, by using crossbeam, the three strings bar location of jib based on spacing column and hook, and the end position of two chord members being positioned at bottom can be determined according to the crossbeam at underframe two ends, namely the angle and position measuring and obtain web member is can be passed through after determining the position of three strings bar, and an other chord member is welded with fixing web member, complete the assembly welding of basic jib, by using this frock, can effectively improve assembly welding efficiency, improve the interchangeability of basic jib, reduce dynamic compaction machinery maintenance cost, improve basic jib linearity, overall package diagonal and angle, reduce the dependence to craftsmanship, improve assembly welding precision.
For solving the problems of the technologies described above, technical solution adopted in the utility model is: a kind of dynamic compaction machinery basis jib group is to frock, comprise at least two crossbeams that underframe, the spacing column of row being vertically arranged on underframe side and level are arranged on chassis top surface, the height of described spacing column reduces from left to right successively relative to underframe, horizontal bearing pin is installed on described spacing column top, the axis direction of bearing pin is identical with length over end sills direction, and described bearing pin fixedly mounts hook.
The quantity of described spacing column is identical with the quantity of crossbeam, and described crossbeam adopts channel-section steel, with welding of underframe and its length direction is vertical with length over end sills direction bottom it.
Described spacing column adopts channel-section steel to be vertically welded on above underframe, and channel-section steel upper end level wears bearing pin, and the split pin of bearing pin one end is fixed, its other one end fixed installation hook.
Described hook comprises shank and hook portion, and described shank is screw rod, and screw portion is arranged through the through hole of bearing pin one end, and overlaps nut with the supporting installation two of screw rod, and two cover nuts lay respectively at bearing pin both sides, and described hook portion is the arc shaped hook of a side opening.
The beneficial effect adopting technique scheme to produce is: by using crossbeam, the three strings bar location of jib based on spacing column and hook, and the end position of two chord members being positioned at bottom can be determined according to the crossbeam at underframe two ends, namely the angle and position measuring and obtain web member is can be passed through after determining the position of three strings bar, and an other chord member is welded with fixing web member, complete the assembly welding of basic jib, by using this frock, can effectively improve assembly welding efficiency, improve the interchangeability of basic jib, reduce dynamic compaction machinery maintenance cost, improve basic jib linearity, overall package diagonal and angle, reduce the dependence to craftsmanship, improve assembly welding precision.
Accompanying drawing explanation
Fig. 1 is the utility model front view;
Fig. 2 is the top view of Fig. 1;
Fig. 3 is hook mounting structure schematic diagram;
Fig. 4 is the utility model using state schematic diagram;
In the accompanying drawings: 1, underframe; 2, crossbeam; 3, spacing column; 4, bearing pin; 5, hook; 6, basic jib.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, the utility model is described in further detail.
The utility model discloses a kind of dynamic compaction machinery basis jib group as shown in Figure 1-2 to frock, comprise at least two crossbeams 2 that underframe 1, the spacing column 3 of row being vertically arranged on underframe 1 side and level are arranged on underframe 1 upper surface, the height of described spacing column 3 reduces from left to right successively relative to underframe 1, horizontal bearing pin 4 is installed on described spacing column 3 top, the axis direction of bearing pin 4 is identical with underframe 1 length direction, and described bearing pin 4 fixedly mounts hook 5; The quantity of described spacing column 3 is identical with the quantity of crossbeam 2, and described crossbeam 2 adopts channel-section steel, welds and its length direction is vertical with underframe 1 length direction bottom it with underframe 1; Described spacing column 3 adopts channel-section steel to be vertically welded on above underframe 1, and channel-section steel upper end level wears bearing pin 4, and bearing pin 4 one end split pin is fixed, its other one end fixed installation hook 5; Described hook 5 comprises shank and hook portion, and described shank is screw rod, and screw portion is arranged through the through hole of bearing pin 4 one end, and overlaps nut with the supporting installation two of screw rod, and two cover nuts lay respectively at bearing pin 4 both sides, and described hook portion is the arc shaped hook of a side opening.
In embody rule process, the utility model is by using crossbeam, the three strings bar location of jib based on spacing column and hook, and the end position of two chord members being positioned at bottom can be determined according to the crossbeam at underframe two ends, namely the angle and position measuring and obtain web member is can be passed through after determining the position of three strings bar, and an other chord member is welded with fixing web member, complete the assembly welding of basic jib, by using this frock, can effectively improve assembly welding efficiency, improve the interchangeability of basic jib, reduce dynamic compaction machinery maintenance cost, improve basic jib linearity, overall package diagonal and angle, reduce the dependence to craftsmanship, improve assembly welding precision.
Claims (4)
1. a dynamic compaction machinery basis jib group is to frock, it is characterized in that: comprise at least two crossbeams (2) that underframe (1), the spacing column of the row (3) being vertically arranged on underframe (1) side and level are arranged on underframe (1) upper surface, the height of described spacing column (3) reduces from left to right successively relative to underframe (1), horizontal bearing pin (4) is installed on described spacing column (3) top, the axis direction of bearing pin (4) is identical with underframe (1) length direction, described bearing pin (4) fixedly mounts hook (5).
2. dynamic compaction machinery basis according to claim 1 jib group is to frock, it is characterized in that: the quantity of described spacing column (3) is identical with the quantity of crossbeam (2), described crossbeam (2) employing channel-section steel, welds with underframe (1) bottom it and its length direction is vertical with underframe (1) length direction.
3. dynamic compaction machinery basis according to claim 2 jib group is to frock, it is characterized in that: described spacing column (3) adopts channel-section steel to be vertically welded on underframe (1) top, channel-section steel upper end level wears bearing pin (4), bearing pin (4) one end split pin is fixed, its other one end fixed installation hook (5).
4. dynamic compaction machinery basis according to claim 3 jib group is to frock, it is characterized in that: described hook (5) comprises shank and hook portion, described shank is screw rod, screw portion is arranged through the through hole of bearing pin (4) one end, and overlap nut with the supporting installation two of screw rod, two cover nuts lay respectively at bearing pin (4) both sides, and described hook portion is the arc shaped hook of a side opening.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520666128.1U CN204975846U (en) | 2015-08-31 | 2015-08-31 | Ram quick -witted basic cantilever crane group by force to frock |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520666128.1U CN204975846U (en) | 2015-08-31 | 2015-08-31 | Ram quick -witted basic cantilever crane group by force to frock |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204975846U true CN204975846U (en) | 2016-01-20 |
Family
ID=55110264
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520666128.1U Active CN204975846U (en) | 2015-08-31 | 2015-08-31 | Ram quick -witted basic cantilever crane group by force to frock |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204975846U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105033554A (en) * | 2015-08-31 | 2015-11-11 | 南车石家庄车辆有限公司 | Basic arm rack assembly tooling of dynamic compactor |
-
2015
- 2015-08-31 CN CN201520666128.1U patent/CN204975846U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105033554A (en) * | 2015-08-31 | 2015-11-11 | 南车石家庄车辆有限公司 | Basic arm rack assembly tooling of dynamic compactor |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202509404U (en) | High-pier single-column capping beam framework construction support system | |
CN201089696Y (en) | Spar boom of explosion-proof suspension crane | |
CN106702906A (en) | Pre-pressing device for hanging baskets and pre-pressing method thereof | |
CN204975847U (en) | Middle cantilever crane group is to frock tip location support | |
CN201738597U (en) | Sectional steel and steel pipe combined type support system of beam with high and large cross section | |
CN105369745A (en) | Bridge support exchanging and lifting reaction frame | |
CN204975846U (en) | Ram quick -witted basic cantilever crane group by force to frock | |
CN207534312U (en) | A kind of shaped steel assembly assist device | |
CN102310177A (en) | Device for controlling downwarping of intermediate tank | |
CN102877657B (en) | Large-span H-shaped plane composite structure beam string upper-air cable replacement construction method | |
CN204975845U (en) | Ram cantilever crane group of set -top portion by force to frock | |
CN205116146U (en) | Strong middle cantilever crane group of machine of ramming is to frock | |
CN206581682U (en) | A kind of interim transition structure in jacking framed bridge steel column for contacting net basis | |
CN105033554A (en) | Basic arm rack assembly tooling of dynamic compactor | |
CN202577158U (en) | Hyperbolic cable tower cross beam adjusting bracket | |
CN105033556B (en) | Arm support group is to frock at the top of dynamic compaction machinery | |
CN212128878U (en) | Cylindrical pier capping beam construction bracket based on pin rod method | |
CN210621745U (en) | Foundation bolt fixing frame assembly | |
CN205046924U (en) | Wind power generation tower with can flexible down tube of a stretch -draw | |
CN203220783U (en) | Scraper blade device of mud scraper | |
CN202994492U (en) | T-shaped bridge static loading test rack | |
CN203653074U (en) | Quick-assembled combined cross beam for portal crane | |
CN105033553A (en) | End positioning support for middle arm frame pairing tool | |
CN202081385U (en) | Adjustable main truss hanging basket | |
CN104278848B (en) | A kind of Bailey beam dismounting tractor-trailer |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C56 | Change in the name or address of the patentee | ||
CP03 | Change of name, title or address |
Address after: 051430 Shijiazhuang Province, Luancheng City, Shijiazhuang province equipment Industrial Park, Yu Xiang street, No. 168 Patentee after: CRRC SHIJIAZHUANG CO., LTD. Address before: 050000 Shijiazhuang Province, Luancheng City, Shijiazhuang province equipment Industrial Park, Yu Xiang street, No. 168 Patentee before: CSR SHIJIAZHUANG ROLLING STOCK WORKS |