Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520556314.XU
Other languages
Chinese (zh)
Inventor
马文凯
王祥
张龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN JINGLONG ENGINEERING MACHINERY CO LTD
Original Assignee
TIANJIN JINGLONG ENGINEERING MACHINERY CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN JINGLONG ENGINEERING MACHINERY CO LTD filed Critical TIANJIN JINGLONG ENGINEERING MACHINERY CO LTD
Priority to CN201520556314.XU priority Critical patent/CN204958051U/en
Application granted granted Critical
Publication of CN204958051U publication Critical patent/CN204958051U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Electric Cable Installation (AREA)

Abstract

The utility model provides a construction lift, including guide rail frame, cable trolley frame and the cable trolley case that the symmetry set up, the cable trolley case sets up the intermediate position at the cable trolley frame, and the both ends of cable trolley frame are respectively through pulley and guide rail frame sliding connection, the bottom and the side of cable trolley case are provided with a plurality of solidus ears, wear to be equipped with the cable rope in the solidus ear, the top of every guide rail frame is provided with all that B turns to the fixed pulley and A turns to the fixed pulley, cable rope passes every solidus ear, and the both ends of cable rope pass two every B on the guide rails frame respectively in proper order and turn to fixed pulley and A and turn to to be connected with behind the fixed pulley and receive the line roller, receives the setting of line roller on rail brackets. Construction lift simple structure easily operate, through two synchronous motors work of controller control, adopt and receive the line roller and receive and release the up -and -down motion that the cable trolley case was controlled to the cable conductor, increased a guide rail frame, the both ends of putting up cable trolley all provide the support of sliding, have improved the support degree.

Description

A kind of building hoist
Technical field
The utility model belongs to building hoist field, especially relates to a kind of building hoist.
Background technology
Existing building hoist adopts single-rail frame, but in the operational process of building construction hoist, cable trolley is easily subject to the reason of construction operating mode, as impacts such as strong wind, heavy rain or building wastes, causes cable trolley fluctuation of service.
Summary of the invention
In view of this, the utility model is intended to propose a kind of building hoist, to improve the operation stability of cable trolley.
For achieving the above object, the technical solution of the utility model is achieved in that
A kind of building hoist, comprise symmetrically arranged guide rail bracket, cable trolley frame and cable trolley case, described cable trolley case is fixedly installed on the midway location of cable trolley frame, and the two ends of described cable trolley frame are respectively by pulley and guide rail bracket sliding block joint; The bottom of described cable trolley case and side are provided with multiple solidus ear, are equipped with cable rope in described solidus ear; The top of each described guide rail bracket is provided with B and turns to fixed pulley and A to turn to fixed pulley; Described cable rope is through each solidus ear, and the two ends of cable rope are connected with take-up roller after turning to fixed pulley and A to turn to fixed pulley through each B on two guide rail brackets successively respectively, and described take-up roller is arranged on guide rail bracket.
Further, two described A turn to fixed pulley all to arrange towards near the direction of centre plane, and two B turn to fixed pulley all to arrange towards the direction away from centre plane.
Further, two described take-up rollers respectively provide power by a motor, and two motors are connected with controller by electrical connection, control two motor in synchrony work by controller.
Relative to prior art, building hoist structure described in the utility model is simple to operation, controls two motor in synchrony work by controller, adopts take-up roller taking up and laying cable conductors to manipulate the up-and-down movement of cable trolley case; And by the firm cable trolley case of multiple solidus ear, substantially increase the degree of operating steadily of cable trolley case; Add a guide rail bracket, all provide sliding support to the two ends of cable trolley frame, improve support degree.
Accompanying drawing explanation
The accompanying drawing forming a part of the present utility model is used to provide further understanding of the present utility model, and schematic description and description of the present utility model, for explaining the utility model, is not formed improper restriction of the present utility model.In the accompanying drawings:
Fig. 1 is the structural representation described in the utility model embodiment.
Description of reference numerals:
1-guide rail bracket, 2-A turns to fixed pulley, and 3-B turns to fixed pulley, 4-cable rope, 5-pulley, 6-take-up roller, 7-cable trolley frame, 8-cable trolley case, 9-solidus ear.
Detailed description of the invention
It should be noted that, when not conflicting, the embodiment in the utility model and the feature in embodiment can combine mutually.
Below with reference to the accompanying drawings and describe the utility model in detail in conjunction with the embodiments.
A kind of building hoist as shown in Figure 1, comprise symmetrically arranged guide rail bracket 1, cable trolley frame 7 and cable trolley case 8, described cable trolley case 8 is fixedly installed on the midway location of cable trolley frame 7, and the two ends of described cable trolley frame 7 are respectively by pulley 5 and guide rail bracket 1 sliding block joint; The bottom of described cable trolley case 8 and side are provided with multiple solidus ear 9, are equipped with cable rope 4 in described solidus ear 9; The top of each described guide rail bracket 1 is provided with B and turns to fixed pulley 3 and A to turn to fixed pulley 2; Described cable rope 4 is through each solidus ear 9, and the two ends of cable rope 4 are connected with take-up roller 6 after turning to fixed pulley 3 and A to turn to fixed pulley 2 through each B on two guide rail brackets 1 successively respectively, and described take-up roller 6 is arranged on guide rail bracket 1.
Two described A turn to fixed pulley 2 all to arrange towards near the direction of centre plane, and two B turn to fixed pulley 3 all to arrange towards the direction away from centre plane.
Two described take-up rollers 6 respectively provide power by a motor, and two motors are connected with controller by electrical connection, control two motor in synchrony work by controller, adopt take-up roller taking up and laying cable conductors to manipulate the up-and-down movement of cable trolley case.
The foregoing is only preferred embodiment of the present utility model; not in order to limit the utility model; all within spirit of the present utility model and principle, any amendment done, equivalent replacement, improvement etc., all should be included within protection domain of the present utility model.

Claims (3)

1. a building hoist, it is characterized in that: comprise symmetrically arranged guide rail bracket (1), cable trolley frame (7) and cable trolley case (8), described cable trolley case (8) is fixedly installed on the midway location of cable trolley frame (7), and the two ends of described cable trolley frame (7) are respectively by pulley (5) and guide rail bracket (1) sliding block joint; The bottom of described cable trolley case (8) and side are provided with multiple solidus ear (9), are equipped with cable rope (4) in described solidus ear (9); The top of each described guide rail bracket (1) is provided with B and turns to fixed pulley (3) and A to turn to fixed pulley (2); Described cable rope (4) is through each solidus ear (9), and the two ends of cable rope (4) are connected with take-up roller (6) after turning to fixed pulley (3) and A to turn to fixed pulley (2) through the B on two guide rail brackets (1) successively, described take-up roller (6) is arranged on guide rail bracket (1).
2. building hoist according to claim 1, it is characterized in that: two described A turn to fixed pulley (2) all to arrange towards near the direction of centre plane, two B turn to fixed pulley (3) all to arrange towards the direction away from centre plane.
3. building hoist according to claim 1, is characterized in that: two described take-up rollers (6) respectively provide power by a motor, and two motors are connected with controller by electrical connection.
CN201520556314.XU 2015-07-28 2015-07-28 Construction lift Expired - Fee Related CN204958051U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520556314.XU CN204958051U (en) 2015-07-28 2015-07-28 Construction lift

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520556314.XU CN204958051U (en) 2015-07-28 2015-07-28 Construction lift

Publications (1)

Publication Number Publication Date
CN204958051U true CN204958051U (en) 2016-01-13

Family

ID=55053131

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520556314.XU Expired - Fee Related CN204958051U (en) 2015-07-28 2015-07-28 Construction lift

Country Status (1)

Country Link
CN (1) CN204958051U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114364627A (en) * 2019-09-17 2022-04-15 株式会社日立制作所 Lifter for construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114364627A (en) * 2019-09-17 2022-04-15 株式会社日立制作所 Lifter for construction

Similar Documents

Publication Publication Date Title
CN103058065A (en) Novel sliding-type gantry crane and use thereof
CN104891337B (en) A kind of driving light rail trolley method for rapidly mounting
CN202755635U (en) Movable-type basket support
CN204958051U (en) Construction lift
CN203373022U (en) Self-lifting type cableway transportation device
CN202848860U (en) Special sling for flexible busbar installation
CN108910719B (en) Light wallboard hanging machine
CN202880699U (en) Bias-rail girder bridge crane
CN102969676A (en) Cable laying device adopting guiding type control of fixed pulleys
CN205575403U (en) Mono beam overhead crane
CN202785371U (en) Novel simple girder bridge type crane
CN103035368A (en) 10kV transformer frame
CN103274310A (en) Self-lifting type cableway transporting device
CN202465078U (en) Hoisting mechanism of crane
CN203845639U (en) Machine-room-less elevator with counterweight device and tractor rear-mounted
CN105776034A (en) Explosion-poof bridge crane
CN201729606U (en) Movable rope bearing device of tower crane
CN203205744U (en) Lifting type circuit breaker transfer trolley
CN201914847U (en) Lifting table for moving guide rod
CN205653060U (en) Explosion -protection bridge crane
CN201296606Y (en) Power supply structure for electrolysis shop centralization major service overhead traveling crane trolley line
CN212403224U (en) Electric hoist cable towing device
CN204198264U (en) Electric block drift angle lifting auxiliary device
CN204223999U (en) The running of elevator and control system
CN204847642U (en) Construction elevator stop device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160113

Termination date: 20200728