CN104891337B - A kind of driving light rail trolley method for rapidly mounting - Google Patents

A kind of driving light rail trolley method for rapidly mounting Download PDF

Info

Publication number
CN104891337B
CN104891337B CN201510190961.8A CN201510190961A CN104891337B CN 104891337 B CN104891337 B CN 104891337B CN 201510190961 A CN201510190961 A CN 201510190961A CN 104891337 B CN104891337 B CN 104891337B
Authority
CN
China
Prior art keywords
driving
light rail
trolley
rail trolley
hanging belt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510190961.8A
Other languages
Chinese (zh)
Other versions
CN104891337A (en
Inventor
江龙
孙亮
舒荣东
杨明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201510190961.8A priority Critical patent/CN104891337B/en
Publication of CN104891337A publication Critical patent/CN104891337A/en
Application granted granted Critical
Publication of CN104891337B publication Critical patent/CN104891337B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/12Arrangements of means for transmitting pneumatic, hydraulic, or electric power to movable parts of devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Carriers, Traveling Bodies, And Overhead Traveling Cranes (AREA)
  • Machines For Laying And Maintaining Railways (AREA)

Abstract

The invention discloses a kind of driving light rail trolley method for rapidly mounting, lay driving temporary source cable according to the load of the complete driving of installation and debugging, it is ensured that driving can run normally;Driving is utilized to be hoisted to below infield by light rail trolley to be installed;Being fixed on one end of hanging belt on the little hook of driving, the other end of hanging belt is put to touching ground, adjusts the height of driving ditch, make driving ditch not affect lifting and the installation of light rail trolley in lifting operation before hanging belt is fixing;Setting up job platform at travelling crane current collector maintenance cage near the side of trolley conductor bracket, described job platform is set up can not grazing crane beam and trolley conductor bracket.The invention have the advantage that quickening driving light rail trolley Fast Installation construction speed, safe and reliable, influence factor is few, high financial profit.

Description

A kind of driving light rail trolley method for rapidly mounting
Technical field
The present invention relates to a kind of industrial equipment construction installation method, in particular, relate to a kind of driving light rail trolley method for rapidly mounting.
Background technology
In metallurgical industry Factory Building, driving plays lifts the effect that heavy sensation in the foot is light, and the lifting of main equipment, installation etc. all need to be completed by the cooperation of driving, and the travelling crane sliding touch wire providing electrical source of power to driving is of a great variety, wherein maximum with light rail trolley installation difficulty.Conventional light rail trolley installation method many cooperation with truck crane is installed as master, owing to light rail trolley installation process needing continuous moving automobile hang truck position, station, therefore working performance is relatively low, additionally mounted personnel need to install light rail trolley by self-control cage under crane beam, operation danger coefficient is big, there is potential safety hazard.
Summary of the invention
The present invention is directed to the deficiencies in the prior art, and a kind of work efficiency, saving expense of improving is provided, additionally it is possible to improve a kind of driving light rail trolley method for rapidly mounting of operational security.
A kind of driving light rail trolley method for rapidly mounting of the present invention, including following construction procedure:
Step 1 lays driving temporary source cable according to the load of the complete driving of installation and debugging, it is ensured that driving can run normally;Driving is utilized to be hoisted to below infield by light rail trolley to be installed;
One end of hanging belt is fixed on the little hook of driving by step 2, and the other end of hanging belt is put to touching ground, adjusts the height of driving ditch, make driving ditch not affect lifting and the installation of light rail trolley in lifting operation before hanging belt is fixing;
Step 3 sets up job platform at travelling crane current collector maintenance cage near the side of trolley conductor bracket, can not grazing crane beam and trolley conductor bracket when job platform is set up;
Step 4 adjusts the height limit switch of little hook of driving a vehicle, by piece light rail trolley of one end colligation of hanging belt, start little hook of driving a vehicle and rise button, little hook of driving a vehicle unclamps rising button after rising to light rail trolley setting height(from bottom), adjust the height limit switch of little hook of driving a vehicle, make light rail trolley stop after rising setting height(from bottom);
Driving dolly is stopped the side to trolley conductor bracket to be installed by step 5, adjusts driving dolly and makes the distance trolley conductor bracket 100~200mm of hanging belt end, disconnects driving dolly main circuit power;
Step 6 uses hanging belt by firm for light rail trolley colligation to be installed, driving is opened above light rail trolley to be installed, come to a complete stop after arriving installation site, disconnect travelling crane truck main circuit power, operating personnel enters job platform, starting little hook of driving a vehicle and rise button handling light rail to be installed trolley, stop after arriving installation site, operating personnel installs light rail trolley;
After step 7 light rail trolley installs, operating personnel leaves job platform, send travelling crane truck main circuit power, driving handling light rail trolley to run to next infield, disconnect travelling crane truck main circuit power, and operating personnel enters job platform operation;
Step 8 removes driving temporary source cable after all light rail trolleys install, and removes hanging belt and removes job platform.
Little hook of driving a vehicle in described step 2 is provided with cable drum.Fix connect with cord head hold-down bolt after one ends wound cable drum three circle of described hanging belt.The distance trolley conductor bracket 130~170mm of described hanging belt end.The distance trolley conductor bracket 150mm of described hanging belt end.
The invention has the beneficial effects as follows: (1) accelerating construction progress: before installation, light rail trolley to be installed can be carried to infield by driving, installation process middle rolling car can run freely, need compared with continuous moving automobile hangs truck position, station, working performance can be improved greatly with using in truck crane installation process.(2) safe and reliable: compared with routine work method, by setting up job platform outside travelling crane current collector maintenance cage, operating personnel can be not required to install light rail trolley by self-control cage under crane beam, improves the safety of operation.(3) high financial profit: use this method can save the lease expenses of truck crane, save Construction Cost.(4) influence factor is few: routine work method need to consider the truck position, station of truck crane, and truck crane is higher to the requirement on basis, owing to site environment is complicated, cross-operation between each operation, components etc. are put in a jumble, affect erect-position and the lifting of truck crane, use the impact that this method can avoid above unfavorable factor to install light rail trolley.
Accompanying drawing explanation
Fig. 1 the inventive method implementation process schematic diagram one;
Fig. 2 the inventive method implementation process schematic diagram two;
Fig. 3 is the A-A sectional view of Fig. 2
In figure: driving 1, light rail trolley 2, little hook 3 of driving a vehicle, hanging belt 4, travelling crane current collector maintenance cage 5, job platform 6, driving dolly 7, crane beam 8, trolley conductor bracket 9, travelling crane truck 10.
Detailed description of the invention
The invention will be further described below in conjunction with the accompanying drawings.
In the drawings, a kind of driving light rail trolley method for rapidly mounting of the present invention, including following construction procedure:
Step 1 lays driving temporary source cable according to the load of the complete driving 1 of installation and debugging, it is ensured that driving 1 can run normally;Driving 1 is utilized to be hoisted to below infield by light rail trolley 2 to be installed;
One end of hanging belt 4 is fixed on the little hook 3 of driving by step 2, and the other end of hanging belt 4 is put to touching ground, adjusts the height of driving ditch 3, make driving ditch 3 not affect lifting and the installation of light rail trolley 2 in lifting operation before hanging belt 4 is fixing;
Step 3 sets up job platform 6 at travelling crane current collector maintenance cage 5 near the side of trolley conductor bracket 9, can not grazing crane beam 8 and trolley conductor bracket 9 when job platform 6 is set up;
Step 4 adjusts the height limit switch of little hook 3 of driving a vehicle, by piece light rail trolley 2 of one end colligation of hanging belt 4, start little hook 3 of driving a vehicle and rise button, drive a vehicle after little hook 3 rises to light rail trolley 2 setting height(from bottom) and unclamp rising button, adjust the height limit switch of little hook 3 of driving a vehicle, make light rail trolley 2 stop after rising setting height(from bottom);
Driving dolly 7 is stopped the side to trolley conductor bracket 9 to be installed by step 5, adjusts driving dolly 7 and makes the distance trolley conductor bracket 150mm of hanging belt 4 end, disconnects driving dolly 7 main circuit power;
Step 6 uses hanging belt 4 by firm for light rail trolley 2 colligation to be installed, driving 1 is opened above light rail trolley 2 to be installed, come to a complete stop after arriving installation site, disconnect travelling crane truck 10 main circuit power, operating personnel enters job platform 6, starting little hook 3 of driving a vehicle and rise button handling light rail to be installed trolley 2, stop after arriving installation site, operating personnel installs light rail trolley 2;
After step 7 light rail trolley 2 installs, operating personnel leaves job platform 6, send travelling crane truck 10 main circuit power, and 1 handling light rail trolley 2 of driving a vehicle runs to next infield, disconnecting travelling crane truck 10 main circuit power, operating personnel enters job platform 6 operation;
Driving 1 temporary source cable removed by step 8 all light rails trolley 2 after installing, remove hanging belt 4 and remove job platform 6.
Little hook 3 of driving a vehicle in described step 2 is provided with cable drum, fixes connect with cord head hold-down bolt after one ends wound cable drum three circle of described hanging belt 4.

Claims (5)

1. a driving light rail trolley method for rapidly mounting, it is characterised in that include following construction procedure:
Step 1 lays driving temporary source cable according to the load of the complete driving (1) of installation and debugging, it is ensured that driving (1) can run normally;Driving (1) is utilized to be hoisted to below infield by light rail trolley (2) to be installed;
One end of hanging belt (4) is fixed in the little hook of driving (3) by step 2, the other end of hanging belt (4) is put to touching ground, adjust the height of little hook (3) of driving a vehicle before hanging belt (4) is fixing, make the little hook of driving (3) not affect lifting and the installation of light rail trolley (2) in lifting operation;
Step 3 sets up job platform (6) at travelling crane current collector maintenance cage (5) near the side of trolley conductor bracket (9), can not grazing crane beam (8) and trolley conductor bracket (9) when job platform (6) is set up;
Step 4 adjusts the height limit switch of little hook (3) of driving a vehicle, by piece light rail trolley (2) of one end colligation of hanging belt (4), start little hook (3) of driving a vehicle and rise button, drive a vehicle after little hook (3) rises to light rail trolley (2) setting height(from bottom) and unclamp rising button, adjust the height limit switch of little hook (3) of driving a vehicle, make light rail trolley (2) stop after rising setting height(from bottom);
Driving dolly (7) is stopped the side to trolley conductor bracket to be installed (9) by step 5, adjusts driving dolly (7) and makes the distance trolley conductor bracket (9) 100~200mm of hanging belt (4) end, disconnects driving dolly (7) main circuit power;
Step 6 uses hanging belt (4) by firm for light rail trolley (2) colligation to be installed, driving (1) is opened to light rail trolley (2) to be installed top, come to a complete stop after arriving installation site, disconnect travelling crane truck (10) main circuit power, operating personnel enters job platform (6), starting little hook (3) of driving a vehicle and rise button handling light rail to be installed trolley (2), stop after arriving installation site, operating personnel installs light rail trolley (2);
After step 7 light rail trolley (2) installs, operating personnel leaves job platform (6), connect travelling crane truck (10) main circuit power, driving (1) handling light rail trolley (2) runs to next infield, disconnecting travelling crane truck (10) main circuit power, operating personnel enters job platform (6) operation;
After step 8 all light rails trolley (2) installs, remove driving (1) temporary source cable, remove hanging belt (4) and remove job platform (6).
A kind of driving light rail trolley method for rapidly mounting the most according to claim 1, it is characterised in that little hook (3) of driving a vehicle in described step 2 is provided with cable drum.
A kind of driving light rail trolley method for rapidly mounting the most according to claim 1, it is characterised in that fix connect with cord head hold-down bolt after one ends wound cable drum three circle of described hanging belt (4).
A kind of driving light rail trolley method for rapidly mounting the most according to claim 1, it is characterised in that the distance trolley conductor bracket (9) 130~170mm of described hanging belt (4) end.
A kind of driving light rail trolley method for rapidly mounting the most according to claim 4, it is characterised in that distance trolley conductor bracket (9) 150mm of described hanging belt (4) end.
CN201510190961.8A 2015-04-22 2015-04-22 A kind of driving light rail trolley method for rapidly mounting Active CN104891337B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510190961.8A CN104891337B (en) 2015-04-22 2015-04-22 A kind of driving light rail trolley method for rapidly mounting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510190961.8A CN104891337B (en) 2015-04-22 2015-04-22 A kind of driving light rail trolley method for rapidly mounting

Publications (2)

Publication Number Publication Date
CN104891337A CN104891337A (en) 2015-09-09
CN104891337B true CN104891337B (en) 2016-09-14

Family

ID=54024385

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510190961.8A Active CN104891337B (en) 2015-04-22 2015-04-22 A kind of driving light rail trolley method for rapidly mounting

Country Status (1)

Country Link
CN (1) CN104891337B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107434211B (en) * 2016-05-26 2018-10-19 五冶集团上海有限公司 A kind of electric single-beam suspension crane trolley installation method
CN107098270B (en) * 2017-05-16 2019-04-05 陈晓斌 It is a kind of using power generation and the bridge cranes of small articles to be transported
CN109204345B (en) * 2017-06-30 2021-04-20 比亚迪股份有限公司 Track engineering vehicle
CN110783864B (en) * 2019-10-31 2021-06-01 上海宝冶集团有限公司 Cable cabling rack device under travelling crane beam
CN112374368B (en) * 2020-11-13 2022-05-10 中国十九冶集团有限公司 Positioning device and mounting method for trolley wire support

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101348213A (en) * 2007-07-17 2009-01-21 中国二十冶建设有限公司 Mounting method of crane sliding contact line in workshop
CN101633324A (en) * 2008-07-23 2010-01-27 沈阳铝镁设计研究院 Method and structure for supplying power to sliding contact lines of crown blocks intensively overhauled in electrolysis workshop
CN203077188U (en) * 2012-12-14 2013-07-24 中国二十冶集团有限公司 Device for adjusting space between driving sliding contact lines
CN103401125A (en) * 2013-08-14 2013-11-20 株洲天桥起重机股份有限公司 Piecewise sliding contact line power supply connection method and connection device thereof
CN104071696A (en) * 2014-07-07 2014-10-01 镇江市江岛电器制造有限公司 Mounting method for crane sliding contact line

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101348213A (en) * 2007-07-17 2009-01-21 中国二十冶建设有限公司 Mounting method of crane sliding contact line in workshop
CN101633324A (en) * 2008-07-23 2010-01-27 沈阳铝镁设计研究院 Method and structure for supplying power to sliding contact lines of crown blocks intensively overhauled in electrolysis workshop
CN203077188U (en) * 2012-12-14 2013-07-24 中国二十冶集团有限公司 Device for adjusting space between driving sliding contact lines
CN103401125A (en) * 2013-08-14 2013-11-20 株洲天桥起重机股份有限公司 Piecewise sliding contact line power supply connection method and connection device thereof
CN104071696A (en) * 2014-07-07 2014-10-01 镇江市江岛电器制造有限公司 Mounting method for crane sliding contact line

Also Published As

Publication number Publication date
CN104891337A (en) 2015-09-09

Similar Documents

Publication Publication Date Title
CN104891337B (en) A kind of driving light rail trolley method for rapidly mounting
CN203699606U (en) Lifter and iron tower
CN102616673A (en) Chimney electric baskets of power generation project
CN107226419A (en) A kind of synchronisation control means of the special double-hung driving of H profile steel reconditioning
CN107069562A (en) Replacing insulator under electrified method and load transfer device
CN105019664A (en) High-altitude slipping installation method for compartment-type electric room
CN102963817A (en) Tailing force-free large equipment hoisting vertical tail removal method
CN205764526U (en) For welding the dolly of clamping-rail trolley conductor bracket
CN205575403U (en) Mono beam overhead crane
CN204897247U (en) A hoist and mount bracket for moving motor rotor
CN104870358A (en) Maintenance method for a lift
CN105776034A (en) Explosion-poof bridge crane
CN201817208U (en) Simple lifting machine
CN103803420A (en) Overhead crane with electric hoist
CN101723252B (en) Overhead-traveling installation method of 400t overhead travelling crane replacement equipment
CN202880699U (en) Bias-rail girder bridge crane
CN103010965A (en) Special tool of 110kVGW4-type for hoisting switch blades and porcelain bottles
CN102344079A (en) Windmill service elevator
CN205407131U (en) Cable laying device
CN205653060U (en) Explosion -protection bridge crane
CN210438304U (en) Monorail crane with telescopic function
CN102718133A (en) Crane trolley
CN108335613A (en) A kind of electrical control system of crane apparatus for demonstrating and its application method
CN105905804A (en) Hybrid differential driving mechanism for controlling lifting of crane and transverse moving of trolley
CN204832481U (en) Special high -voltage transformer tandem formula check -up platform

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant