CN204919379U - A removal scaffolding structure on water for bridge on water maintenance - Google Patents

A removal scaffolding structure on water for bridge on water maintenance Download PDF

Info

Publication number
CN204919379U
CN204919379U CN201520707190.0U CN201520707190U CN204919379U CN 204919379 U CN204919379 U CN 204919379U CN 201520707190 U CN201520707190 U CN 201520707190U CN 204919379 U CN204919379 U CN 204919379U
Authority
CN
China
Prior art keywords
flitch
plummer
section steel
connection wire
channel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520707190.0U
Other languages
Chinese (zh)
Inventor
宋海立
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai long strengthening Polytron Technologies Inc
Original Assignee
Shanghai Jiujian Reinforcement Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Jiujian Reinforcement Technology Co Ltd filed Critical Shanghai Jiujian Reinforcement Technology Co Ltd
Priority to CN201520707190.0U priority Critical patent/CN204919379U/en
Application granted granted Critical
Publication of CN204919379U publication Critical patent/CN204919379U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to a removal scaffolding structure on water for bridge on water maintenance, including a plurality of flitches, a plurality of cystosepiments, a plurality of connection lead screws, the channel -section steel plummer, trick frame bed frame by four flitch end -to -end connection form a rectangle, the top of trick frame bed frame is provided with the channel -section steel plummer, separate into a plurality of grooves of bearing by horizontal vertical crisscross flitch that distributes in the trick frame bed frame, it is provided with the cystosepiment to bear the inslot, crossing position all is provided with and is connected the lead screw between flitch and the flitch, connect the overlap department of running through flitch and flitch in the lead screw bottom, the lead screw that connecting filament peak of the staff portion stretched into the channel -section steel plummer inserts in the groove. The utility model discloses can float in removal scaffolding structure on water, its utilize the motor vessel pull, fixed, hold in the palm daytime to construction region, provide firm handy operation platform for the construction, forget about it the bank phytal zone evening, guarantee freighter at night is opened the navigation or air flight smoothly.

Description

For the Waterborne movable scaffolding structure of on-water bridge maintenance
Technical field
The utility model relates to a kind of scaffolding structure, is a kind of Waterborne movable scaffolding structure for on-water bridge maintenance specifically.
Background technology
Operation bridge is permanent large structure in way and structures, also be the important component part of Rail Highway driving facility and guarantee the key equipment that transportation safety is unimpeded, have complex structure, technical strong, build difficulty, cost difficulty, feature that cost is higher.Once damage, gently then speed limit off-load is heavy then cut off traffic.China railways bridge, differs and limitation in designing and constructing owing to building age different, technical standard, there is many problems.Along with the sustainable development that Chinese national economy is built, the continuous growth of railway transportation intensity, for adapting to the needs of train speed raising, heavy haul transport, bridge must have higher carrying, anti-disaster ability and safety reliability, also has higher requirement to bridge maintenance maintenance department.Therefore, carry out bridge maintenance maintenance work, for guaranteeing safety of railway traffic, promote the development of China's economic construction, tool is of great significance.
Bridge strengthening work has achieved a lot of progress in recent years, but we still face a lot of problem.Luoyang Yellow River Bridge is positioned at middle and lower reaches boundary, the Yellow River part, and south is closed highway with Luoyang-old city, Mengjin-Bai and is connected, and north is connected with the Meng County-Liu village-Jiyuan highway, is the important tie in contact north and south.Bridge total length 3428.934M, totally 67 holes, every hole clear span 50M, wherein about has 45 holes to be seated in torrential Huanghe water.First difficult point faced in reinforcing design is exactly the strengthen maintenance process of the bridge for high water level, and personnel's operational difficulty, the maintenance cost setting up bar construction is high, and the cycle is long.If set up scaffold in water, ship can be hindered normally to open the navigation or air flight, and poor stability, potential safety hazard are large.Run into more surging river, easily occur the situation of bar construction shakiness, most of bridge pier of bridge is positioned at the river course that The turbulent river crashes its way through, time have freighter to open the navigation or air flight.Horizontal plane has 9 meters more than bottom bridge, and water level, towards rising to fall at sunset, brings huge difficulty to construction under bridge.
Summary of the invention
For above-mentioned situation, the utility model provides a kind of Waterborne movable scaffolding structure for on-water bridge maintenance, can float on Waterborne movable scaffolding structure waterborne, and it utilizes power ship to draw, fixes, daytime, holder was to construction area, for construction provides firmly portable operating platform; Forget about it phytal zone, bank evening, ensure that night, freighter was opened the navigation or air flight smoothly.
To achieve these goals, the technical solution of the utility model is as follows:
A kind of Waterborne movable scaffolding structure for on-water bridge maintenance, comprise some flitches, some cystosepiments, some connection wire rods, channel-section steel plummer, the scaffold pedestal of rectangle is connected to form by four flitch head and the tail, the top of scaffold pedestal is provided with channel-section steel plummer, some bearing grooves are separated into by the flitch be laterally longitudinally interspersed in scaffold pedestal, cystosepiment is provided with in bearing groove, position crossing between flitch with flitch is provided with connection wire rod, the overlapping place of flitch and flitch is run through bottom connection wire rod, connection wire rod top is stretched in the screw mandrel access groove of channel-section steel plummer.
As preferred embodiment, the width of described flitch is 200 millimeters, and length is 4000 millimeters.
As preferred embodiment, the radius of described connection wire rod is 50 ~ 60 millimeters, and the length of connection wire rod is 400 ~ 500 millimeters, and connection wire rod bottom is equipped with set bolt.
As preferred embodiment, the length of described bearing groove 1100 ~ 1200 millimeters, width is 1000 ~ 1100 millimeters, the cystosepiment shape in bearing groove and bearing groove form fit.
As preferred embodiment, described channel-section steel plummer is provided with for anti-skidding steel wire net structure.
As preferred embodiment, be provided with external screw thread in the screw mandrel access groove of described channel-section steel plummer, external screw thread is threaded with the screw-internal thread fit at connection wire rod top.
The utility model has the advantages that: can float on Waterborne movable scaffolding structure waterborne, it utilizes power ship to draw, fixes, and daytime, holder was to construction area, for construction provides firmly portable operating platform; Forget about it phytal zone, bank evening, ensure that night, freighter was opened the navigation or air flight smoothly.
Accompanying drawing explanation
Fig. 1 is top view of the present utility model.
Fig. 2 is left view of the present utility model.
In the drawings: 1-flitch, 2-cystosepiment, 3-connection wire rod, 4-channel-section steel plummer, 5-scaffold pedestal, 6-bearing groove, 7-screw mandrel access groove, 8-set bolt, 9-steel wire net structure.
Detailed description of the invention
The technological means realized to make the utility model, creation characteristic, reaching object and effect is easy to understand, below in conjunction with concrete diagram, setting forth the utility model further.
See Fig. 1 ~ Fig. 2, a kind of Waterborne movable scaffolding structure for on-water bridge maintenance, comprise some flitches, some cystosepiments, some connection wire rods, channel-section steel plummer, the scaffold pedestal of rectangle is connected to form by four flitch head and the tail, the top of scaffold pedestal is provided with channel-section steel plummer, some bearing grooves are separated into by the flitch be laterally longitudinally interspersed in scaffold pedestal, cystosepiment is provided with in bearing groove, position crossing between flitch with flitch is provided with connection wire rod, the overlapping place of flitch and flitch is run through bottom connection wire rod, connection wire rod top is stretched in the screw mandrel access groove of channel-section steel plummer.
As preferred embodiment, the width of described flitch is 200 millimeters, and length is 4000 millimeters.
As preferred embodiment, the radius of described connection wire rod is 50 ~ 60 millimeters, and the length of connection wire rod is 400 ~ 500 millimeters, and connection wire rod bottom is equipped with set bolt.
As preferred embodiment, the length of described bearing groove 1100 ~ 1200 millimeters, width is 1000 ~ 1100 millimeters, the cystosepiment shape in bearing groove and bearing groove form fit.
As preferred embodiment, described channel-section steel plummer is provided with for anti-skidding steel wire net structure.
As preferred embodiment, be provided with external screw thread in the screw mandrel access groove of described channel-section steel plummer, external screw thread is threaded with the screw-internal thread fit at connection wire rod top.
More than show and describe general principle of the present utility model, principal character and advantage of the present utility model.The technician of the industry should understand; the utility model is not restricted to the described embodiments; the just principle of the present utility model described in above-described embodiment and manual; under the prerequisite not departing from the utility model spirit and scope, the utility model also has various changes and modifications, and these changes and improvements all fall in claimed scope of the present utility model.The protection domain that the utility model requires is defined by appending claims and equivalent thereof.

Claims (6)

1. for the Waterborne movable scaffolding structure of on-water bridge maintenance, it is characterized in that, comprise some flitches, some cystosepiments, some connection wire rods, channel-section steel plummer, the scaffold pedestal of rectangle is connected to form by four flitch head and the tail, the top of scaffold pedestal is provided with channel-section steel plummer, some bearing grooves are separated into by the flitch be laterally longitudinally interspersed in scaffold pedestal, cystosepiment is provided with in bearing groove, position crossing between flitch with flitch is provided with connection wire rod, the overlapping place of flitch and flitch is run through bottom connection wire rod, connection wire rod top is stretched in the screw mandrel access groove of channel-section steel plummer.
2. the Waterborne movable scaffolding structure for on-water bridge maintenance according to claim 1, it is characterized in that, the width of described flitch is 200 millimeters, and length is 4000 millimeters.
3. the Waterborne movable scaffolding structure for on-water bridge maintenance according to claim 1, it is characterized in that, the radius of described connection wire rod is 50 ~ 60 millimeters, and the length of connection wire rod is 400 ~ 500 millimeters, and connection wire rod bottom is equipped with set bolt.
4. the Waterborne movable scaffolding structure for on-water bridge maintenance according to claim 1, it is characterized in that, the length of described bearing groove 1100 ~ 1200 millimeters, width is 1000 ~ 1100 millimeters, the cystosepiment shape in bearing groove and bearing groove form fit.
5. the Waterborne movable scaffolding structure for on-water bridge maintenance according to claim 1, is characterized in that, described channel-section steel plummer is provided with for anti-skidding steel wire net structure.
6. the Waterborne movable scaffolding structure for on-water bridge maintenance according to claim 1, is characterized in that, be provided with external screw thread in the screw mandrel access groove of described channel-section steel plummer, external screw thread is threaded with the screw-internal thread fit at connection wire rod top.
CN201520707190.0U 2015-09-14 2015-09-14 A removal scaffolding structure on water for bridge on water maintenance Active CN204919379U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520707190.0U CN204919379U (en) 2015-09-14 2015-09-14 A removal scaffolding structure on water for bridge on water maintenance

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520707190.0U CN204919379U (en) 2015-09-14 2015-09-14 A removal scaffolding structure on water for bridge on water maintenance

Publications (1)

Publication Number Publication Date
CN204919379U true CN204919379U (en) 2015-12-30

Family

ID=54968523

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520707190.0U Active CN204919379U (en) 2015-09-14 2015-09-14 A removal scaffolding structure on water for bridge on water maintenance

Country Status (1)

Country Link
CN (1) CN204919379U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638297A (en) * 2016-12-05 2017-05-10 广西交通科学研究院 Water detection platform for detecting and maintaining bridge

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638297A (en) * 2016-12-05 2017-05-10 广西交通科学研究院 Water detection platform for detecting and maintaining bridge

Similar Documents

Publication Publication Date Title
CN203923882U (en) One-sided dorsal funciculus steel work cable stayed bridge
CN202164546U (en) High pier bridge construction platform
CN204919379U (en) A removal scaffolding structure on water for bridge on water maintenance
CN203755151U (en) Suspension type bridge inspection vehicle with wind-resistant lifting platform
CN209081290U (en) Bailey truss pylon and distributing earth anchor CABLEWAY ERECTION SYSTEM that can be traversing
CN109339108A (en) A kind of section of track well system based on subway station list branch-cut bridge
CN203625777U (en) Adjustable wheeltrack type beam transporting vehicle on beams
CN205025154U (en) 330kVGIS distribution device place rigid connection sail formula framework
CN209323393U (en) A kind of drag-line bridge king-tower side plane repairing nacelle construction structure
CN207597294U (en) A kind of road and bridge construction safety alarm device
CN206359210U (en) A kind of processing of steel construction is with stablizing lowering or hoisting gear
CN204325944U (en) Intercity track cable stayed bridge Diamond-Shape Form Traveler
CN205265148U (en) Construction equipment is crossed over to high -speed railway of not stopping transport
CN203923912U (en) Crash barrier template stand
CN202707076U (en) Double-line railway tunnel trolley
CN209323394U (en) A kind of drag-line bridge king-tower outer inclined-plane repairing nacelle construction structure
CN204472598U (en) A kind of foot of ladder retractor device for electrification railway contact net tool car ladder
CN209228386U (en) A kind of lining of tunneling Subway Tunnel big cross section stop line two new type formwork trolley
CN203878450U (en) Novel ropeway bridge
CN106451228A (en) Scissor-type self-expansion spanning system for power transmission line live stringing
CN209082432U (en) A kind of efficient wave absorption structure applied in navigable tunnel
CN204530988U (en) A kind of large span lattice crane beam
CN207209263U (en) A kind of truss lifting device of ribbon conveyer
CN206873219U (en) A kind of D types just beam
CN206256393U (en) A kind of ejection hanging-basket walking device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: 200050 15A-1 room, No. 855, Changning Road, Shanghai, Changning District

Patentee after: Shanghai long strengthening Polytron Technologies Inc

Address before: 200050 15A-1 room, No. 855, Changning Road, Shanghai, Changning District

Patentee before: SHANGHAI JIUJIAN REINFORCEMENT TECHNOLOGY CO., LTD.