CN204898702U CN201520533116.1U CN201520533116U CN204898702U CN 204898702 U CN204898702 U CN 204898702U CN 201520533116 U CN201520533116 U CN 201520533116U CN 204898702 U CN204898702 U CN 204898702U
Authority
CN
China
Prior art keywords
cement pole
base plate
fixed base
soil layer
administered
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520533116.1U
Other languages
Chinese (zh)
Inventor
杨倩倩
钱文晓
肖冰
党乐
祖向东
王瑞
郭金刚
史昌明
孙鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Eastern Inner Mongolia Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Eastern Inner Mongolia Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Eastern Inner Mongolia Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201520533116.1U priority Critical patent/CN204898702U/en
Application granted granted Critical
Publication of CN204898702U publication Critical patent/CN204898702U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)

Abstract

The utility model discloses a cement pole up -pull structure is administered in sand control earthen backfill, its structure includes cement pole, fixed loop, fixedly acts as go -between, PMKD and the annular clamped piece. The utility model discloses fundamentally has solved china's area in the north, freezes the summer and melts the cement pole up -pull problem that leads to because of the soil winter to simple structure, construction convenience, used material cost is cheap, the time limit for a project is short, greatly reduced annual for solving the required maintenance maintenance cost of cement pole up -pull problem.

Description

A kind of sand control earthen backfill is administered on cement pole and is pulled out structure
Technical field:
The utility model relates to one and prevents from cement pole pulls out structure, particularly relates on a kind of sand control earthen backfill improvement cement pole and pulls out structure.
Background technology:
In northern China most area, there is the winter and freeze the summer and melt in the soil body, thus causes transmission line of electricity part of cement bar generating period pulls out, and on every annual mean is maximum, the amount of pulling out can reach 16cm, also to there is cement pole and tilt and the phenomenon of falling bar in some areas, serious threat line security operation.Body frost heaving is the prerequisite occurring cement pole pulls out, and on pull out generation after, the muddy water sandstone do not freezed around cement pole pole-footing falls into filling hole, and after Second Year is thawed, pole-footing can not fall reposition, is to cause cement pole cumulative bad pulls out and finally causes down the basic reason of bar.
At present, China prevents from cement pole pulls out and mainly contains three class measures, and it is essential that play bracing wire, righting and ridging reinforcing, these class methods need be carried out every year, need at substantial human and material resources, financial resources.Equations of The Second Kind is mainly set about from the process bar base soil body, base oneself upon three Fundamentals eliminating or weaken generation frost heave and (there is the soil of heave susceptibility, certain moisture supply, suitable freezing condition and time), adopt draining water proof, coarse sand changes and fill out and beat the methods such as quicklime pile and process cement pole bar base, such methods engineering amount is great, and frost heave effect is not durable.An other class methods object is the opposing of refinforced cement bar and adapts to freeze thawing deformability, comprise and adopt dark stake formula, spread foundation and isolation method etc., these class methods enhance on cement pole and pull out drag, but shortcoming is that the muddy water sandstone cannot avoiding not freezing around dead man root falls into hole, once generation cement pole pulls out, be difficult to fall after rise to original position, cause in accumulation and pull out, fundamentally do not solve on cement pole and pull out problem.
Utility model content:
Propose one both constructability, save overall expenses, strengthen on shaft and pull out resistance, on the improvement cement pole shaft that can prevent again sand from backfill, draw out method solves an urgent demand of the regional transmission line cement pole of frost heave pulling out problem.
The purpose of this utility model is that providing a kind of sand control earthen backfill to administer on cement pole pulls out structure.
The purpose of this utility model is implemented by following technical scheme, a kind of sand control earthen backfill is administered on cement pole and is pulled out structure, it comprises cement pole, retainer ring, fixing bracing wire, fixed base plate and annular stator, the below of described fixed base plate is provided with described annular stator, the top edge of described annular stator is fixedly connected with the bottom surface of described fixed base plate, the structure design of annular stator and fixed base plate, while resistance is pulled out in increase, effectively prevent sand from backfilling, stop the generation of cement pole shaft pulling out problem.Described cement pole is vertically arranged at above described fixed base plate, and described cement pole bottom is fixed on the end face of described fixed base plate, retainer ring is arranged with above described cement pole, some fixing bracing wires of straining are provided with between described retainer ring and described fixed base plate, one end of described fixing bracing wire and the edge conjunction of described fixed base plate, the other end is connected with described retainer ring, described retainer ring is positioned at more than ground surface, utilize fixing bracing wire, retainer ring is fixedly connected with fixed base plate, cement pole is made to become to be integrated with fixed base plate, increase the total loading of shaft, increase on shaft and pull out resistance.Described cement pole below described retainer ring, described fixed base plate and described annular stator are all embedded in the soil layer on below earth's surface.
Preferably, described retainer ring is metal ring, and described fixing bracing wire is wire, and described fixed base plate is corrosion resistant plate, and described annular stator is ring stainless steel sheet, and the lower edge of described ring stainless steel sheet is blade-like.
Concrete, described soil layer is divided into frozen soil layer and non-frozen soil layer, and the upper strata of described non-frozen soil layer is described frozen soil layer.
Preferably, described fixed base plate and described annular stator be all embedded in described in non-frozen soil layer.
Preferably, some described fixing bracing wires are uniformly distributed.
Operating principle illustrates: the weight of corrosion resistant plate and ring stainless steel sheet increases the total loading of cement pole shaft, adds the compression frost-heave force that above sun-dried mud brick gravity above corrosion resistant plate and corrosion resistant plate, frozen soil layer is downward simultaneously.
(1) when frozen soil layer thickness is less, when the adhesion (freezing plateau resistance) of frozen soil and cement pole is not enough to overcome the total loading of shaft, sun-dried mud brick gravity and compress frost-heave force, the method effectively prevent the generation of cement pole pulling out phenomenon.
(2) when frozen soil layer thickness is larger, freezing plateau resistance make cement pole shaft occur a certain amount of on when pulling out, ring stainless steel sheet inside is made to form hole, the muddy water sandstone do not freezed can be effectively stoped to fall into hole around, after thawing to Second Year, ring stainless steel sheet reinserts below sun-dried mud brick, and hole disappears, cement pole shaft falls reposition, effectively prevent on cement pole shaft and pulls out.
The utility model has the advantage of: 1, the utility model only need excavate sun-dried mud brick above corrosion resistant plate when constructing, and engineering quantity is little, without the need to extensive construction, greatly reduction of erection time, reducing construction cost; 2, the earthen backfill of the utility model sand control is administered and cement pole is pulled out structure primary raw material used is the stainless steel of constant weight, and this material price is cheap, effectively controls improvement cost; 3, when frozen soil layer thickness is less, prevent from cement pole shaft pulls out Be very effective; 4, when frozen soil layer thickness is larger, by the rising of ring stainless steel sheet, falling and sand control earthen backfill effect, can effectively prevent from cement pole shaft pulls out phenomenon; 5, the utility model fundamentally solves the northern area of China, melt on the cement pole that causes pull out problem because the soil winter freezes the summer, and structure is simple, easy construction, material therefor is with low cost, duration is short, greatly reduces every year for solution cement pole pulling out the maintenance maintenance cost needed for problem.
Accompanying drawing illustrates:
A kind of sand control earthen backfill improvement cement pole pulls out structural representation to Fig. 1.
Cement pole 1, metal ring 2, ground 3 after frost heave, original ground 4, frozen soil layer 5, wire 6, non-frozen soil layer 7, corrosion resistant plate 8, ring stainless steel sheet 9.
Detailed description of the invention:
Embodiment 1: as shown in Figure 1, a kind of sand control earthen backfill is administered on cement pole and is pulled out structure, and it comprises cement pole 1, metal ring 2, wire 6, corrosion resistant plate 8 and ring stainless steel sheet 9, and the lower edge of ring stainless steel sheet 9 is blade-like.The below of corrosion resistant plate 8 is provided with ring stainless steel sheet 9, the top edge of ring stainless steel sheet 9 and the bottom surface of corrosion resistant plate 8 are welded to connect, cement pole 1 is vertically arranged at above corrosion resistant plate 8, and cement pole 1 bottom is fixed on the end face of corrosion resistant plate 8, metal ring 2 is arranged with above cement pole 1, be provided with the some wires strained 6 between metal ring 2 and corrosion resistant plate 8, some wires 6 are uniformly distributed.One end of wire 6 and the edge of corrosion resistant plate 8 are welded to connect, and the other end and metal ring 2 are welded to connect, and metal ring 2 is positioned at more than ground surface, and the cement pole 1 below metal ring 2, corrosion resistant plate 8 and ring stainless steel sheet 9 are all embedded in the soil layer on below earth's surface.Soil layer is divided into frozen soil layer 5 and non-frozen soil layer 7, and the upper strata of non-frozen soil layer 7 is frozen soil layer 5.Corrosion resistant plate 8 and ring stainless steel sheet 9 are all embedded in non-frozen soil layer 7.
After soil body generation frost heave, ground has the rising of certain amplitude, and as shown in Figure 1, after frost heave, ground 3 is higher than original ground 4.
Operating principle illustrates: the weight of corrosion resistant plate 8 and ring stainless steel sheet 9 increases the total loading of cement pole 1 shaft, adds the compression frost-heave force that above sun-dried mud brick gravity above corrosion resistant plate 8 and corrosion resistant plate 8, frozen soil layer is downward simultaneously.
(1) when frozen soil layer 5 thickness is less, when frozen soil layer 5 is not enough to overcome the total loading of shaft, sun-dried mud brick gravity and compress frost-heave force with the adhesion (freezing plateau resistance) of cement pole 1, the method effectively prevent the generation of cement pole 1 pulling out phenomenon.
(2) when frozen soil layer 5 thickness is larger, freezing plateau resistance make cement pole 1 shaft occur a certain amount of on when pulling out, ring stainless steel sheet 9 inside is made to form hole, the muddy water sandstone do not freezed can be effectively stoped to fall into hole around, after thawing to Second Year, ring stainless steel sheet 9 reinserts below sun-dried mud brick, and hole disappears, cement pole 1 shaft falls reposition, effectively prevent on cement pole 1 shaft and pulls out.

Claims (5)

1. a sand control earthen backfill is administered on cement pole and is pulled out structure, it is characterized in that, it comprises cement pole, retainer ring, fixing bracing wire, fixed base plate and annular stator, the below of described fixed base plate is provided with described annular stator, the top edge of described annular stator is fixedly connected with the bottom surface of described fixed base plate, described cement pole is vertically arranged at above described fixed base plate, and described cement pole bottom is fixed on the end face of described fixed base plate, retainer ring is arranged with above described cement pole, some fixing bracing wires of straining are provided with between described retainer ring and described fixed base plate, one end of described fixing bracing wire and the edge conjunction of described fixed base plate, the other end is connected with described retainer ring, described retainer ring is positioned at more than ground surface, described cement pole below described retainer ring, described fixed base plate and described annular stator are all embedded in the soil layer on below earth's surface.
2. a kind of sand control earthen backfill according to claim 1 is administered on cement pole and is pulled out structure, it is characterized in that, described retainer ring is metal ring, described fixing bracing wire is wire, described fixed base plate is corrosion resistant plate, described annular stator is ring stainless steel sheet, and the lower edge of described ring stainless steel sheet is blade-like.
3. a kind of sand control earthen backfill according to claim 1 is administered on cement pole and is pulled out structure, and it is characterized in that, described soil layer is divided into frozen soil layer and non-frozen soil layer, and the upper strata of described non-frozen soil layer is described frozen soil layer.
4. a kind of sand control earthen backfill according to claim 3 is administered on cement pole and is pulled out structure, it is characterized in that, non-frozen soil layer described in described fixed base plate and described annular stator are all embedded in.
5. a kind of sand control earthen backfill according to claim 1 is administered on cement pole and is pulled out structure, and it is characterized in that, some described fixing bracing wires are uniformly distributed.
CN201520533116.1U 2015-07-22 2015-07-22 Cement pole up -pull structure is administered in sand control earthen backfill Active CN204898702U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520533116.1U CN204898702U (en) 2015-07-22 2015-07-22 Cement pole up -pull structure is administered in sand control earthen backfill

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520533116.1U CN204898702U (en) 2015-07-22 2015-07-22 Cement pole up -pull structure is administered in sand control earthen backfill

Publications (1)

Publication Number Publication Date
CN204898702U true CN204898702U (en) 2015-12-23

Family

ID=54920891

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520533116.1U Active CN204898702U (en) 2015-07-22 2015-07-22 Cement pole up -pull structure is administered in sand control earthen backfill

Country Status (1)

Country Link
CN (1) CN204898702U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105040723A (en) * 2015-07-22 2015-11-11 国家电网公司 Structure for preventing sand backfill and treating concrete pole up-pulling and construction method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105040723A (en) * 2015-07-22 2015-11-11 国家电网公司 Structure for preventing sand backfill and treating concrete pole up-pulling and construction method thereof

Similar Documents

Publication Publication Date Title
CN101591904B (en) Method for strengthening composite pile foundation by prepressing drainage and following grouting for drainage body
CN206784453U (en) The concrete foundation anti-freeze expansion structure of Frozen Ground Area
CN206956742U (en) High precipitous rock roadbed side slope repair system
CN105040723B (en) Structure for preventing sand backfill and treating concrete pole up-pulling and construction method thereof
CN203200746U (en) High-pressure jet grouting hollow reinforced tubular pile
CN107964979A (en) A kind of transmission line of electricity combining structure assembled cushion cap anchor rod foundation
CN106703044A (en) Flow-plastic-shaped flushing and filling soil weak stratum sloping combination support method
CN102330436B (en) Composite retaining structure and composite retaining method for half geotechnical layer ultradeep round spiral flow tank
CN103161151B (en) A kind of high-pressure rotary-spray hollow reinforces construction method and the high-pressure rotary-spray hollow reinforcing pile tube of pile tube
CN204151796U (en) A kind of reinforcement eco-concrete bank protection
CN101691760B (en) Composite foundation combining anchor rods with excavation and construction method thereof
CN203498860U (en) Anchor rod foundation structure with concrete blocks for photovoltaic module brackets
CN103015414A (en) Precast concrete post grouting pile and grouting process
CN205152965U (en) Utilize reinforced (rfd) environmental protection of plant roots to squeeze into slip casting type soil nail wall
CN204753621U (en) Power transmission sequence iron tower is with compound basis
CN204898702U (en) Cement pole up -pull structure is administered in sand control earthen backfill
CN206971247U (en) A kind of concrete plinth foundation ruggedized construction being placed on Unloading Rock
CN103938641A (en) Foundation construction technology of large-scale photovoltaic power station in desert
CN201843135U (en) Composite foundation pile in power transmission line
CN201502065U (en) Anchor rod joint excavation compound basis
CN201334664Y (en) Spike-shaped anchor rod
CN105041036A (en) Structure capable of preventing transmission line concrete pole from uplifting and construction method thereof
CN207714358U (en) A kind of transmission line of electricity composite structure assembled cushion cap anchor rod foundation
CN103306290B (en) Permafrost region pole and tower foundation foundation soil returns fast and freezes backfill construction method
CN203361182U (en) Unequal-length bottom-expanded rock anchor pile of power transmission pole tower

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant