CN204876525U - On turn over girder construction with outrigger support of encorbelmenting - Google Patents

On turn over girder construction with outrigger support of encorbelmenting Download PDF

Info

Publication number
CN204876525U
CN204876525U CN201520649789.3U CN201520649789U CN204876525U CN 204876525 U CN204876525 U CN 204876525U CN 201520649789 U CN201520649789 U CN 201520649789U CN 204876525 U CN204876525 U CN 204876525U
Authority
CN
China
Prior art keywords
shaped steel
shaped
floor
sleeve pipe
reinforcing bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520649789.3U
Other languages
Chinese (zh)
Inventor
刘向军
李伍贺
林阳
门贤君
李磊
李小龙
钟龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Highway Engineering Co Ltd
Original Assignee
CCCC First Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Highway Engineering Co Ltd filed Critical CCCC First Highway Engineering Co Ltd
Priority to CN201520649789.3U priority Critical patent/CN204876525U/en
Application granted granted Critical
Publication of CN204876525U publication Critical patent/CN204876525U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model provides an on turn over girder construction with outrigger support of encorbelmenting, it relates to building technical field, and it contains U -shaped reinforcing bar pull ring, shaped steel, pressing plate bolt, shaped steel fix the support frame, PVC sleeve pipe, hard -wood wedge, U -shaped reinforcing bar pull ring pre -buried last the roof beam turns over and on, shaped steel fix the support frame sets up in the floor top, it is the same that shaped steel fix the support frame's height turns over the deck -molding degree on with, the PVC sleeve pipe is pre -buried on the floor, shaped steel passes U -shaped reinforcing bar pull ring level and sets up on shaped steel fix the support frame, the clamp plate spiral alternated shaped steel, the cover is established in the PVC sleeve pipe, fixes shaped steel and floor, the hardwood drift ping is established between pressing plate bolt and shaped steel. Turn over the encorbelment fixed problem of shaped steel of roof beam on it has been solved, installation disassembling operation is convenient, it is firmly stable to support the support body, and pressing plate bolt can reuse, practices thrift the cost.

Description

One is turned over girder construction outrigger bearing of encorbelmenting
Technical field
The utility model relates to technical field of buildings, is specifically related to one be turned over girder construction outrigger bearing of encorbelmenting.
Background technology
Current highrise building often uses the shaped steel suspension scaffolding in work progress, the shaped steel suspension scaffolding utilizes Cantilever Beams to do basis, shaped steel is anchored on building structure beam slab, outward-dipping stretch out fixing after, set up vertical rod at an upper portion thereof, cross bar, paving scaffold floor form construction operation scaffold.
This kind of erection method is applicable to the structural beams end face situation equal with deck flooring, and overhanging type steel adopts U-shaped reinforcing bar draw ring or anchor bolt and beam slab to fix.And some layout design considers that the factors such as floor daylighting, curtain wall decoration turn over girder construction on adopting, in the process of overhanging scaffold erection, structural framing is caused to be damaged for avoiding punching continuously at the upper Liang Chu of turning over, shaped steel Cantilever Beams can not directly be seated on floor, occurring that Cantilever Beams is pressed in turns on beam, the phenomenon that the pre-buried part of floor is unsettled, the strong point that Cantilever Beams is not connected with structure, erection difficulty.
Utility model content
The purpose of this utility model is defect for prior art and deficiency, there is provided a kind of structure simple, girder construction outrigger bearing of encorbelmenting is turned on reasonable in design, easy to use, it solve the fixation problem of turning over beam overhanging type steel, installing/dismounting is easy to operate, supporting frame firm stable, and follower bolt can reuse, cost-saving.
For achieving the above object, the technical solution adopted in the utility model is: it comprises U-shaped reinforcing bar draw ring, shaped steel, follower bolt, shaped steel fixing support rack, PVC sleeve pipe, hard-wood wedge; U-shaped reinforcing bar draw ring is embedded in and turns on beam, shaped steel shaped steel fixing support rack is arranged on above floor, the height of shaped steel fixing support rack with on to turn over depth of beam identical, PVC sleeve pipe pre-embedding is on floor, shaped steel is set up on shaped steel fixing support rack through U-shaped reinforcing bar draw ring level, pressing plate spiral is inserted through shaped steel, is set in PVC sleeve pipe, shaped steel and floor is fixed; Hardwood drift ping is located between follower bolt and shaped steel.
The steel pipe that described shaped steel fixing support rack is 48mm by diameter is formed.
Fixing means of the present utility model is: be embedded with U-shaped reinforcing bar draw ring upper turning on beam, floor is embedded with PVC sleeve pipe, the shaped steel fixing support rack identical with above turning over depth of beam is arranged on floor, shaped steel is arranged on shaped steel fixing support rack through U-shaped reinforcing bar draw ring level, pressing plate spiral is inserted through shaped steel, is set in PVC sleeve pipe, shaped steel and floor is fixed, fill in hard-wood wedge in the gap of follower bolt and shaped steel, then turn over girder construction outrigger bearing of encorbelmenting on and fixedly complete.
After adopting said structure, the utility model beneficial effect is: it with the addition of shaped steel fixing support rack on the basis of original the shaped steel suspension scaffolding, solves the fixation problem of turning over beam overhanging type steel, and installing/dismounting is easy to operate, supporting frame firm stable; The design of floor pre-buried PVC sleeve pipe makes between pressing plate spiral and floor contactless, and follower bolt can reuse, and has saved cost.
Accompanying drawing explanation
Fig. 1 is scheme of installation of the present utility model.
Description of reference numerals:
1, U-shaped reinforcing bar draw ring; 2, shaped steel; 3, follower bolt; 4, shaped steel fixing support rack; 5, PVC sleeve pipe; 6, hard-wood wedge.
Detailed description of the invention
Below in conjunction with accompanying drawing, the utility model is further described.
Referring to as shown in Figure 1, the technical scheme that this detailed description of the invention adopts is: it comprises U-shaped reinforcing bar draw ring 1, shaped steel 2, follower bolt 3, shaped steel fixing support rack 4, PVC sleeve pipe 5, hard-wood wedge 6; U-shaped reinforcing bar draw ring 1 is embedded in and turns on beam, shaped steel fixing support rack 4 is arranged on above floor, the height of shaped steel fixing support rack 4 with on to turn over depth of beam identical, PVC sleeve pipe 5 is embedded on floor, shaped steel 2 is set up on shaped steel fixing support rack 4 through U-shaped reinforcing bar draw ring 1 level, pressing plate spiral 3 is inserted through shaped steel 2, is set in PVC sleeve pipe 5, shaped steel 2 and floor is fixed; Hard-wood wedge 6 plug is located between follower bolt 3 and shaped steel 2.
The steel pipe that described shaped steel fixing support rack 4 is 48mm by diameter is formed.
The fixing means of this detailed description of the invention is: be embedded with U-shaped reinforcing bar draw ring 1 upper turning on beam, floor is embedded with PVC sleeve pipe 5, the shaped steel fixing support rack 4 identical with above turning over depth of beam is arranged on floor, shaped steel 2 is arranged on shaped steel fixing support rack 4 through U-shaped reinforcing bar draw ring 1 level, follower bolt 3 is inserted through shaped steel 2, be set in PVC sleeve pipe 5, shaped steel 2 and floor are fixed, fill in hard-wood wedge 6 in follower bolt 3 and the gap of shaped steel 2, then turn over girder construction outrigger bearing of encorbelmenting on and fixedly complete.
After adopting said structure, the beneficial effect of this detailed description of the invention is: it with the addition of shaped steel fixing support rack on the basis of original the shaped steel suspension scaffolding, solve the fixation problem of turning over beam overhanging type steel, installing/dismounting be easy to operate, supporting frame firm stable; The design of floor pre-buried PVC sleeve pipe makes between pressing plate spiral and floor contactless, and follower bolt can reuse, and has saved cost.
The above, only unrestricted for illustration of the technical solution of the utility model, other amendment that those of ordinary skill in the art make the technical solution of the utility model or equivalently to replace, only otherwise depart from the spirit and scope of technical solutions of the utility model, all should be encompassed in the middle of right of the present utility model.

Claims (2)

1. turn over a girder construction outrigger bearing of encorbelmenting on, it is characterized in that: it comprises U-shaped reinforcing bar draw ring (1), shaped steel (2), follower bolt (3), shaped steel fixing support rack (4), PVC sleeve pipe (5), hard-wood wedge (6); U-shaped reinforcing bar draw ring (1) is embedded in and turns on beam, shaped steel fixing support rack (4) is arranged on above floor, the height of shaped steel shaped steel fixing support rack (4) with on to turn over depth of beam identical, PVC sleeve pipe (5) is embedded on floor, shaped steel (2) is set up on shaped steel fixing support rack (4) through U-shaped reinforcing bar draw ring (1) level, pressing plate spiral (3) is inserted through shaped steel (2), be set in PVC sleeve pipe (5), shaped steel (2) and floor are fixed; Hard-wood wedge (6) plug is located between follower bolt (3) and shaped steel (2).
2. one according to claim 1 is turned over girder construction outrigger bearing of encorbelmenting, it is characterized in that described shaped steel fixing support rack (4) is made up of the steel pipe of diameter 48mm.
CN201520649789.3U 2015-08-27 2015-08-27 On turn over girder construction with outrigger support of encorbelmenting Expired - Fee Related CN204876525U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520649789.3U CN204876525U (en) 2015-08-27 2015-08-27 On turn over girder construction with outrigger support of encorbelmenting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520649789.3U CN204876525U (en) 2015-08-27 2015-08-27 On turn over girder construction with outrigger support of encorbelmenting

Publications (1)

Publication Number Publication Date
CN204876525U true CN204876525U (en) 2015-12-16

Family

ID=54820916

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520649789.3U Expired - Fee Related CN204876525U (en) 2015-08-27 2015-08-27 On turn over girder construction with outrigger support of encorbelmenting

Country Status (1)

Country Link
CN (1) CN204876525U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105926857A (en) * 2016-05-10 2016-09-07 江苏东晟新诚建设集团有限公司 Prefabricated pier and application of prefabricated pier to high-rise reversed beam overhanging scaffold construction
CN106760460A (en) * 2016-12-07 2017-05-31 中国建筑第八工程局有限公司 Suspension scaffold and its installation method for setting up scaffold in prefabricated construction
CN110629996A (en) * 2019-09-30 2019-12-31 杭州昂创科技有限公司 Construction method of profile steel cantilever through-wall-free heightening and anchoring support system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105926857A (en) * 2016-05-10 2016-09-07 江苏东晟新诚建设集团有限公司 Prefabricated pier and application of prefabricated pier to high-rise reversed beam overhanging scaffold construction
CN106760460A (en) * 2016-12-07 2017-05-31 中国建筑第八工程局有限公司 Suspension scaffold and its installation method for setting up scaffold in prefabricated construction
CN110629996A (en) * 2019-09-30 2019-12-31 杭州昂创科技有限公司 Construction method of profile steel cantilever through-wall-free heightening and anchoring support system

Similar Documents

Publication Publication Date Title
CN205348725U (en) Large -span, bearing structure that encorbelments by a wide margin
CN204040446U (en) The shaped steel suspension scaffolding structure
CN103306208A (en) Formwork creeping method for novel 1.6 parabola-shaped four-column type hollow variable section high pier
CN204876525U (en) On turn over girder construction with outrigger support of encorbelmenting
CN105113786A (en) Pad block support system for supporting fixed adjustable cast-in-situ stair formwork
CN203878995U (en) Side wall stair formwork
CN105332506A (en) Formwork support system for parallel multi-section stair and method for constructing same
CN203238948U (en) Hollow ultrahigh formwork profile steel platform
CN203947755U (en) A kind of large Steel Cantilever trussed construction high-altitude construction first floor steel truss erecting device
CN205348761U (en) Basement does not have reinforced structure of no basic lift of installation on back board
CN202055517U (en) Thin-walled cylinder pouring formwork supporting and lifting device
CN106032704A (en) Construction method for using concrete columns to support structures on both sides of post-pouring strip
CN204960309U (en) Fixed adjustable cast -in -place stair template is propped up to establish and is used cushion braced system
CN103147573A (en) Natatorium roof beam slab high formwork construction method
CN204266571U (en) A kind of builder's jack i iron pre-embedded device
CN203977840U (en) A kind of high-altitude long-span strengthening concrete vestibule braced structures
CN204000885U (en) Metro Deep Excavation concrete support hangs mould mould
CN203878991U (en) Staircase steel mold device for multi-storied shaped staircase construction
CN102392534B (en) Aluminum alloy building template assembly
CN102605945B (en) Manufacturing method of big wood formwork
CN203531349U (en) Novel high-bearing easily-dismantled overhanging type scaffold
CN205206315U (en) Run -in runs formwork support system of stair more
CN211597710U (en) A adjustable shore structure of complete set for post-cast strip construction
CN203755682U (en) Secondary pouring form board constructing structure for small opening of concrete structure floor slab
CN103452302B (en) Safety pre-erecting method of cantilever outer frame

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151216

Termination date: 20210827

CF01 Termination of patent right due to non-payment of annual fee