CN204876477U - There is not infiltration terrace structure - Google Patents
There is not infiltration terrace structure Download PDFInfo
- Publication number
- CN204876477U CN204876477U CN201520628602.1U CN201520628602U CN204876477U CN 204876477 U CN204876477 U CN 204876477U CN 201520628602 U CN201520628602 U CN 201520628602U CN 204876477 U CN204876477 U CN 204876477U
- Authority
- CN
- China
- Prior art keywords
- layer
- impermeable layer
- floor structure
- thickness
- infiltration
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Floor Finish (AREA)
Abstract
The utility model provides a there is not infiltration terrace structure belongs to the building decoration field. It solved among the prior art can not be better the prevention of seepage of playing pass through the scheduling problem. This there is not infiltration terrace structure, including ground basic unit, fixed first impermeable layer is fixed with the second impermeable layer in the ground basic unit on first impermeable layer, is fixed with the curing agent layer on the second impermeable layer, and the curing agent layer is 6 -10mm with the thickness of second impermeable layer. The utility model has the advantages of can prevent fracture, prevention of seepage passes through.
Description
Technical field
The utility model belongs to building finishing field, relates to a kind of floor structure, particularly a kind of without infiltration floor structure.
Background technology
Floor structure refers to and uses certain material and technique carry out construction processing to original ground and present necessarily ornamental and functional ground.Along with the fast development of building trade, also more and more higher to the requirement of floor structure.
At present, the floor structure used generally adopts material cement, sand and a small amount of additive to combine, be difficult to meet the requirement of floor structure without infiltration, particularly in underground floor or the position of ground floor, experience the years test under common ground easily ftracture, dusting, rise dirt, hardness not, not withstand voltage, wear-resisting, shock-resistant, attractive in appearance not and infiltration, oil impregnate, not easy to clean.
So, for those skilled in the art, need to develop a kind of have can be good play without chemosmotic floor structure.
Utility model content
The purpose of this utility model there are the problems referred to above for existing technology, proposes a kind of without infiltration floor structure, this nothing permeate floor structure have can crack resistence, impermeable effect.
The purpose of this utility model realizes by following technical proposal: a kind of without infiltration floor structure, comprise ground basic unit, it is characterized in that, ground basic unit is fixed the first impermeable layer, first impermeable layer is fixed with the second impermeable layer, second impermeable layer is fixed with solidification oxidant layer, and the thickness of solidification oxidant layer and the second impermeable layer is 6-10mm.
This nothing infiltration floor structure, ground basic unit is fixed with the first impermeable layer, the second impermeable layer from the bottom up successively, adopts fixing like this multilayer impermeable layer, can prevent the infiltration of fresh water or brackish water etc., simultaneously, solidification oxidant layer on the second impermeable layer adopts diamond dust ground special gold casting concrete curing agent, and (diamond dust ground special gold casting concrete curing agent adopted general operation in more than C25 concreting after 28 days in work progress, spray curing compound twice, polish 7 times, last polishing) or adopt existing curing compound in the market, the two component sealing curing compound of the DS601 that such as Wuhan De Ligu Materials Co., Ltd produces, these two kinds of curing compound all have good intermiscibility, and high rigidity, high abrasion, the characteristics such as height is heat-resisting, cracking infiltration can be prevented, and the thickness of solidification oxidant layer and the second impermeable layer is chosen for 8mm.
Above-mentioned without in infiltration floor structure, the first described impermeable layer is layer of concrete or cement mortar screeding layer.Layer of concrete or cement mortar screeding layer ground basic unit of all can tiling is conducive to fixing the second impermeable layer.
Above-mentioned without in infiltration floor structure, the second described impermeable layer is cement layer or water mill rock layers or silicon carbide layer.Cement layer or water mill rock layers or silicon carbide layer all adopt more than C25, have the erosion of anti-fresh water or brackish water, stronger hardness.
Above-mentioned without in infiltration floor structure, the thickness of described ground basic unit and the Thickness Ratio of the first impermeable layer are 1:1.
Above-mentioned without in infiltration floor structure, the thickness of described first impermeable layer is greater than the thickness of the second impermeable layer.The thickness of the first impermeable layer is greater than the second impermeable layer, mainly in order to better play tiling effect, is more conducive to the second impermeable layer and plays its impermeable effect.
Above-mentioned without in infiltration floor structure, the thickness of described first impermeable layer is 15-20cm.
Compared with prior art, the layer of concrete on this nothing infiltration floor structure or cement mortar screeding layer can tile ground basic unit, and are conducive to the fixing of the second impermeable layer; Second impermeable layer is that more than C25 cement layer or water mill rock layers or silicon carbide layer have the erosion of anti-fresh water or brackish water and stronger hardness; Simultaneously, second impermeable layer is fixed with gold casting concrete curing agent or the two component sealing curing compound of DS601, thus makes whole floor structure have higher abrasion resistance, withstand voltage, shock-resistant, impervious, oil resistant, dust-proof, chemical-resistance, environmental protection, anti-skidding, maintenance-free, one-shot forming effect effect at least 20 years.
Accompanying drawing explanation
Fig. 1 is the sectional structure schematic diagram of this nothing infiltration floor structure.
In figure, 1, ground basic unit; 2, the first impermeable layer; 3, the second impermeable layer; 4, oxidant layer is solidified.
Detailed description of the invention
Be below specific embodiment of the utility model and by reference to the accompanying drawings, the technical solution of the utility model is further described, but the utility model be not limited to these embodiments.
As shown in Figure 1, a kind of without infiltration floor structure, comprise ground basic unit 1.Ground basic unit 1 being fixed the first impermeable layer 2, first impermeable layer 2 is layer of concrete or cement mortar screeding layer, and ground basic unit 1 of can tiling is conducive to fixing the second impermeable layer 3.First impermeable layer 2 is fixed with the second impermeable layer 3, second impermeable layer 3 is cement layer or water mill rock layers or silicon carbide layer, and cement layer or water mill rock layers or silicon carbide layer all adopt more than C25, have the erosion of anti-fresh water or brackish water, stronger hardness.Second impermeable layer 3 is fixed with solidification oxidant layer 4, and the thickness of solidification oxidant layer 4 and the second impermeable layer 3 is 6-10mm, and the thickness solidifying oxidant layer and the second impermeable layer in actual production is preferentially chosen for 8mm.
In addition, the thickness of ground basic unit 1 and the Thickness Ratio of the first impermeable layer 2 are 1:1.The thickness of the first impermeable layer 2 is greater than the thickness of the second impermeable layer 3.The thickness of the first impermeable layer 2 is greater than the second impermeable layer 3, mainly in order to better play tiling effect, is more conducive to the second impermeable layer 3 and plays its impermeable effect.The thickness of the first impermeable layer 2 is 18cm, certainly, in actual production process, also can suitably increase according to actual needs or reduce thickness, generally between 15-20cm.
Comprehensively above-mentioned, this nothing infiltration floor structure, ground basic unit 1 is fixed with the first impermeable layer 2, second impermeable layer 3 from the bottom up successively, adopts fixing like this multilayer impermeable layer, can prevent the infiltration of fresh water or brackish water etc., simultaneously, solidification oxidant layer 4 on the second impermeable layer 3 adopts diamond dust ground special gold casting concrete curing agent, and (diamond dust ground special gold casting concrete curing agent adopted general operation in more than C25 concreting after 28 days in work progress, spray curing compound twice, polish 7 times, last polishing) or adopt existing curing compound in the market, the two component sealing curing compound of the DS601 that such as Wuhan De Ligu Materials Co., Ltd produces, these two kinds of curing compound all have good intermiscibility, and high rigidity, high abrasion, the characteristics such as height is heat-resisting, cracking infiltration can be prevented, and the thickness of solidification oxidant layer 4 and the second impermeable layer 3 is chosen for 8mm.Thus make whole floor structure have higher abrasion resistance, withstand voltage, shock-resistant, impervious, oil resistant, dust-proof, chemical-resistance, environmental protection, anti-skidding, maintenance-free, one-shot forming effect effect at least 20 years.
Specific embodiment described herein is only to the explanation for example of the utility model spirit.The utility model person of ordinary skill in the field can make various amendment or supplements or adopt similar mode to substitute to described specific embodiment, but can't depart from spirit of the present utility model or surmount the scope that appended claims defines.
Although more employ 1 herein, ground layer; 2, the first impermeable layer; 3, the second impermeable layer; 4, solidify the terms such as oxidant layer, but do not get rid of the possibility using other term.These terms are used to be only used to describe and explain essence of the present utility model more easily; The restriction that they are construed to any one additional is all contrary with the utility model spirit.
Claims (6)
1., without an infiltration floor structure, comprise ground basic unit, it is characterized in that, ground basic unit is fixed the first impermeable layer, first impermeable layer is fixed with the second impermeable layer, the second impermeable layer is fixed with solidification oxidant layer, the thickness of solidification oxidant layer and the second impermeable layer is 6-10mm.
2. according to claim 1 without infiltration floor structure, it is characterized in that, the first described impermeable layer is layer of concrete or cement mortar screeding layer.
3. according to claim 2ly it is characterized in that without infiltration floor structure, the second described impermeable layer is cement layer or water mill rock layers or silicon carbide layer.
4. according to claim 3 without infiltration floor structure, it is characterized in that, the thickness of described ground basic unit and the Thickness Ratio of the first impermeable layer are 1:1.
5. according to claim 4 without infiltration floor structure, it is characterized in that, the thickness of described first impermeable layer is greater than the thickness of the second impermeable layer.
6. according to claim 5 without infiltration floor structure, it is characterized in that, the thickness of described first impermeable layer is 15-20cm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520628602.1U CN204876477U (en) | 2015-08-19 | 2015-08-19 | There is not infiltration terrace structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520628602.1U CN204876477U (en) | 2015-08-19 | 2015-08-19 | There is not infiltration terrace structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204876477U true CN204876477U (en) | 2015-12-16 |
Family
ID=54820869
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520628602.1U Active CN204876477U (en) | 2015-08-19 | 2015-08-19 | There is not infiltration terrace structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204876477U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106609563A (en) * | 2016-11-03 | 2017-05-03 | 柏利伟(上海)环保科技有限公司 | Crack-resistant, anticorrosive and anti-seepage protection method for concrete structure surfaces |
CN106958358A (en) * | 2017-04-21 | 2017-07-18 | 佛山市万科置业有限公司 | The industrialization commercial residential buildings of energy-conserving and environment-protective |
CN109235832A (en) * | 2018-08-01 | 2019-01-18 | 山东源根化学技术研发有限公司 | A kind of no infiltration type decoration terrace |
-
2015
- 2015-08-19 CN CN201520628602.1U patent/CN204876477U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106609563A (en) * | 2016-11-03 | 2017-05-03 | 柏利伟(上海)环保科技有限公司 | Crack-resistant, anticorrosive and anti-seepage protection method for concrete structure surfaces |
CN106958358A (en) * | 2017-04-21 | 2017-07-18 | 佛山市万科置业有限公司 | The industrialization commercial residential buildings of energy-conserving and environment-protective |
CN109235832A (en) * | 2018-08-01 | 2019-01-18 | 山东源根化学技术研发有限公司 | A kind of no infiltration type decoration terrace |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204876477U (en) | There is not infiltration terrace structure | |
CN104047410B (en) | Stone material paving construction method | |
CN106401144A (en) | Construction technology for addition type wear resisting concrete ground | |
US20090277127A1 (en) | Decorative aggregate concrete surface preparation process | |
CN203373949U (en) | Concrete superflat floor | |
CN104563507A (en) | Novel cast-in-place waterstone ground surface layer construction method | |
CN102061798A (en) | Epoxy self-leveling floor with concrete sealing curing agent and construction method thereof | |
CN107587398A (en) | The construction method of diamond dust ground curing agent | |
CN204040398U (en) | A kind of ground self-leveling system | |
CN109930856A (en) | A kind of the old and new's wall concatenation construction method | |
CN105000850A (en) | Glass artistic floor | |
CN209670270U (en) | A kind of environment protection colour tempering terrace | |
CN208776593U (en) | A kind of polishing concrete decoration terrace | |
CN202466991U (en) | Waterproof ground beam | |
CN202544330U (en) | Crumpled anti-skidding composite floor | |
CN203684596U (en) | Epoxy resin gold millstone ground | |
CN203097218U (en) | Building wear-resisting pouring ground structure | |
CN211666169U (en) | Colorful wear-resisting floor | |
CN206581551U (en) | A kind of magic stone terrace of Self-leveling | |
CN210316374U (en) | Crystal stone terrace | |
CN105544934A (en) | Whole flooring curing construction method | |
CN207892196U (en) | A kind of anticorrosive anti-wear epoxide terrace | |
CN205206247U (en) | Colored solidification terrace of waterborne | |
CN211666170U (en) | Anti-cracking wear-resistant terrace | |
CN109653473A (en) | A kind of extremely frigid zones roofing parking lot cracking resistance colour mirrorlike surface concrete floor way |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
PE01 | Entry into force of the registration of the contract for pledge of patent right |
Denomination of utility model: A non permeable floor structure Effective date of registration: 20201030 Granted publication date: 20151216 Pledgee: Taizhou Branch of Huaxia Bank Co., Ltd Pledgor: TAIZHOU YUANXIN CONSTRUCTION ENGINEERING Co.,Ltd. Registration number: Y2020330000871 |
|
PE01 | Entry into force of the registration of the contract for pledge of patent right |