CN204849721U - Workover rig slide roof beam flexible connection structure between marine fixed platform - Google Patents

Workover rig slide roof beam flexible connection structure between marine fixed platform Download PDF

Info

Publication number
CN204849721U
CN204849721U CN201520595646.9U CN201520595646U CN204849721U CN 204849721 U CN204849721 U CN 204849721U CN 201520595646 U CN201520595646 U CN 201520595646U CN 204849721 U CN204849721 U CN 204849721U
Authority
CN
China
Prior art keywords
platform
workover rig
roof beam
slide roof
web box
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520595646.9U
Other languages
Chinese (zh)
Inventor
谢茂林
杨春生
张紧
高山
李玉鹏
骈嘉成
钟广锋
孟涛
李伟
刘冠荣
赵铭文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Offshore Oil Corp CNOOC
CNOOC China Ltd Tianjin Branch
Original Assignee
China National Offshore Oil Corp CNOOC
CNOOC China Ltd Tianjin Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China National Offshore Oil Corp CNOOC, CNOOC China Ltd Tianjin Branch filed Critical China National Offshore Oil Corp CNOOC
Priority to CN201520595646.9U priority Critical patent/CN204849721U/en
Application granted granted Critical
Publication of CN204849721U publication Critical patent/CN204849721U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model discloses a workover rig slide roof beam flexible connection structure between marine fixed platform, the slide roof beam of two platform butt joints department adopt three web box roof beams be equipped with swing joint section collet bottom the abutting end of three web box roof beams be equipped with slide roof beam swing joint section on the swing joint section collet, slide roof beam swing joint section and two three web box roof beams pass through the bolt and connect respectively. The utility model discloses can make the butt joint of two platform slide roof beams once successful, can avoid marine secondary transformation construction to can effectively solve and transmit each other and cause the problem of destruction with two platform differences projected life to the structure that links to each other because of nonconformity, load appear subsiding in two platforms in the use, reduce the totality investment of engineering project, and help fixed platform's safety in production.

Description

Workover rig slipway beam movable connection structure between fixed offshore platform
Technical field
The utility model relates to the syndeton between fixed offshore platform, particularly relates to two fixed offshore platforms and shares workover rig, the movable connection structure of two platform slipway beam joints.
Background technology
In recent years, rely on the newly-built two leg external platform hangings of built fixed offshore platform and realize drilling and repairing machine share way be widely applied at Bohai Offshore, effectively can reduce the engineering construction investment of oil gas field.The large space platforms such as along with the continuous intensification be familiar with oil reservoir, plug-in two leg platforms often can not meet the needs of production dilatation, newly-built four legs (and above leg) become the active demand of field produces.In order to Control Engineering investment, the drilling and repairing machine of existing platform is effectively utilized, need workover rig slipway beam syndeton between research independent platform.In the past, when newly-built platform is in place and built platform uncontrollable exist left and right, height dislocation, offshore construction need be carried out transform two platform slipway beam dependency structures, connect, two platform workover rig slide rails be adjusted, to meet the needs of workover rig slippage between two platforms simultaneously.In the Long-Time Service process of newly-built offshore platform and built offshore platform, the pile foundation sedimentation of two platforms is different, load transmits impact mutually, the Platform Designing life-span is different, also the workover rig slippage affected between two platforms and platform is kept the safety in production.
Summary of the invention
The utility model provides workover rig slipway beam movable connection structure between a kind of fixed offshore platform for solving in known technology the technical problem that exists, this structure can make two platform slipway beam docking once successes, marine secondary rebuilding construction can be avoided, and can effectively solve because two platforms in use occur that sedimentation is inconsistent, load is transmitted and the two Platform Designing life-span different problems damaged connected structure mutually.
The technical scheme that the utility model is taked for the technical problem existed in solution known technology is: workover rig slipway beam movable connection structure between a kind of fixed offshore platform, the slipway beam of two platform joints adopts three web box beam, be provided with bottom the butt end of described three web box beam and be flexibly connected section collet, described flexible connection section collet is provided with slipway beam and is flexibly connected section, described slipway beam is flexibly connected section and is connected respectively by bolt with two described three web box beam.
Described flexible connection section collet is provided with leveling backing plate.
The advantage that the utility model has and good effect are: adopt three web box beam as fixed platform workover rig slipway beam at two platform joints, for workover rig slide rail reserves adjustable range so that slide rail docking; The slipway beam making suitability is at sea flexibly connected section, for completing the docking of two platform slipway beams, can avoid the secondary rebuilding construction of platform upper chunk, workover rig slide rail, and can guarantee that the workover rig slippage of two platforms is shared.Two independently adopt movable connection structure between offshore platform, can also effectively solve because the sedimentation in Long-Time Service process of two ocean platforms is inconsistent, load is transmitted and the platform different problem damaged connected structure projected life mutually.In sum, the utility model can be installed according to the misalignment of two platform upper chunks and be flexibly connected section collet and slipway beam flexible connection section, make the workover rig slipway beam docking once success of two platforms, reduce the overall investment of object of construction production, and contribute to the safety in production of fixed offshore platform.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model;
Fig. 2 is the structural representation of three web box beam of the present utility model and workover rig slide rail fixed thereon.
In figure: 1, three web box beam; 2, section collet is flexibly connected; 3, slipway beam is flexibly connected section; 4, workover rig slide rail.
Detailed description of the invention
For summary of the invention of the present utility model, Characteristic can be understood further, hereby exemplify following examples, and coordinate accompanying drawing to be described in detail as follows:
Refer to Fig. 1 and Fig. 2, workover rig slipway beam movable connection structure between a kind of fixed offshore platform, the slipway beam of two platform joints adopts three web box beam 1, be provided with bottom the butt end of described three web box beam 1 and be flexibly connected section collet 2, described flexible connection section collet 2 is provided with slipway beam and is flexibly connected section 3, described slipway beam is flexibly connected section 3 and is connected respectively by bolt with two described three web box beam 1.
Adopt three web box beam 1 as fixed platform workover rig slipway beam at two platform joints, can adjust the horizontal level of the workover rig slide rail 4 be located thereon; Be flexibly connected section collet 2 and can carry out Attention problems according to the dislocation of two platform vertical direction, to guarantee that two supporting surfaces being flexibly connected section collet 2 are in same level; Slipway beam is flexibly connected section 3 and at sea makes according to the misalignment of two platforms, with bolts with three web box beam 1 of two platforms.When workover rig does not carry out the slippage operation between two platforms, remove the connection that slipway beam is flexibly connected section 3 and a platform, keep slipway beam to be flexibly connected the connection of section 3 and another platform, can avoid that two platform sedimentations are inconsistent, load is mutually transmitted and damaged connected structure.After the situation that two platform sedimentations are inconsistent occurs, leveling backing plate can be increased on the flexible connection section collet 2 that position is lower, to ensure that two supporting surfaces being flexibly connected section collet 2 are in same level.
Although be described preferred embodiment of the present utility model by reference to the accompanying drawings above; but the utility model is not limited to above-mentioned detailed description of the invention; above-mentioned detailed description of the invention is only schematic; be not restrictive; those of ordinary skill in the art is under enlightenment of the present utility model; do not departing under the ambit that the utility model aim and claim protect, can also make a lot of form, these all belong within protection domain of the present utility model.

Claims (2)

1. workover rig slipway beam movable connection structure between a fixed offshore platform, it is characterized in that, the slipway beam of two platform joints adopts three web box beam, be provided with bottom the butt end of described three web box beam and be flexibly connected section collet, described flexible connection section collet is provided with slipway beam and is flexibly connected section, described slipway beam is flexibly connected section and is connected respectively by bolt with two described three web box beam.
2. workover rig slipway beam movable connection structure between fixed offshore platform according to claim 1, is characterized in that, described flexible connection section collet is provided with leveling backing plate.
CN201520595646.9U 2015-08-07 2015-08-07 Workover rig slide roof beam flexible connection structure between marine fixed platform Active CN204849721U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520595646.9U CN204849721U (en) 2015-08-07 2015-08-07 Workover rig slide roof beam flexible connection structure between marine fixed platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520595646.9U CN204849721U (en) 2015-08-07 2015-08-07 Workover rig slide roof beam flexible connection structure between marine fixed platform

Publications (1)

Publication Number Publication Date
CN204849721U true CN204849721U (en) 2015-12-09

Family

ID=54740289

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520595646.9U Active CN204849721U (en) 2015-08-07 2015-08-07 Workover rig slide roof beam flexible connection structure between marine fixed platform

Country Status (1)

Country Link
CN (1) CN204849721U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115467534A (en) * 2022-10-19 2022-12-13 中国建筑一局(集团)有限公司 Method for constructing steel beams and floor slabs at positions of all-steel ultra-high-rise structure across post-cast strip in advance

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115467534A (en) * 2022-10-19 2022-12-13 中国建筑一局(集团)有限公司 Method for constructing steel beams and floor slabs at positions of all-steel ultra-high-rise structure across post-cast strip in advance
CN115467534B (en) * 2022-10-19 2023-07-28 中国建筑一局(集团)有限公司 Advanced construction method for steel beam and floor slab at span post-pouring zone of all-steel super-high-rise structure

Similar Documents

Publication Publication Date Title
CN102849185B (en) Pile leg installation method for self-elevating drilling platform
CN108487089B (en) A method of railroad bridge is removed and set up on hillside
CN207363606U (en) A kind of drilling machine sliding system
CN106381870B (en) A kind of deep concrete mixture ship pile frame system and pile making method
CN204323659U (en) The bracing or strutting arrangement of the FPSO module of hull
CN102337736A (en) Installation process of upper module on offshore oil platform
CN103967284B (en) The steel column installation method of reserved stigma docking
CN105544396A (en) Steel arc distributive girder structure of rod type bracket for cast-in-place arch bridge and construction method
CN204849721U (en) Workover rig slide roof beam flexible connection structure between marine fixed platform
CN105421228B (en) A kind of bridge expansion joint installation
CN202055764U (en) Sliding base of ocean drilling and repairing machine
CN111395293A (en) Ultra-deep water jacket platform
EP3688232A2 (en) Plug and abandonment of one or more offshore platform wellbores of an offshore platform using a marine jack-up type vessel
CN204703144U (en) A kind of self lift type the Macadam Pile Construction platform
CN204895763U (en) Auxiliary fixtures is corrected to boats and ships upper deck T roof beam
AU2014304378A1 (en) Scaffold
CN203866802U (en) Single-foot column oil production platform
CN201778339U (en) Submarine tunnel pipe joint positioning system
CN105274938A (en) Construction method for integrally hoisting and directly positioning steel suspension box
CN205605220U (en) A adjustable construction platform for work is strutted in tunnel
CN205205680U (en) Cast -in -place arched bridge member formula support steel arc distribution beam construction
CN204940250U (en) A kind of long piled wharf steel pipe pile
CN203682928U (en) Electric hydraulic lifting device
CN106628033A (en) Expandable deck self-elevating platform
CN204984451U (en) Heavy car and heavy governing system of hydraulic support of adjusting

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 100010 Beijing City, Dongcheng District Chaoyangmen No. 25 North Street P.O. Box 4705 Chinese CNOOC building

Co-patentee after: Tianjin Branch of China Sea Prtroleum (China) Co., Ltd.

Patentee after: China Offshore Oil Group Co., Ltd.

Address before: 100010 Beijing City, Dongcheng District Chaoyangmen No. 25 North Street P.O. Box 4705 Chinese CNOOC building

Co-patentee before: Tianjin Branch of China Sea Prtroleum (China) Co., Ltd.

Patentee before: China National Offshore Oil Corporation

CP01 Change in the name or title of a patent holder