CN204827477U - Concrete typical forms is spouted in movable preliminary bracing - Google Patents

Concrete typical forms is spouted in movable preliminary bracing Download PDF

Info

Publication number
CN204827477U
CN204827477U CN201520580678.1U CN201520580678U CN204827477U CN 204827477 U CN204827477 U CN 204827477U CN 201520580678 U CN201520580678 U CN 201520580678U CN 204827477 U CN204827477 U CN 204827477U
Authority
CN
China
Prior art keywords
arc formwork
hydraulic stem
movable support
arc
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520580678.1U
Other languages
Chinese (zh)
Inventor
姜冲
张志远
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Highway Engineering Co Ltd
Original Assignee
CCCC First Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Highway Engineering Co Ltd filed Critical CCCC First Highway Engineering Co Ltd
Priority to CN201520580678.1U priority Critical patent/CN204827477U/en
Application granted granted Critical
Publication of CN204827477U publication Critical patent/CN204827477U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

Concrete typical forms is spouted in movable preliminary bracing, arc formwork's surface is the arc structure, and arc formwork's the radius and the tunnel radius of being under construction equal, arc formwork's inner wall through the hydraulic stem with can move movable support and be connected each hydraulic stem along arc formwork's inner wall evenly distributed, the shotcrete pipe sets up between arc formwork and concrete wet blasting machine, and concrete wet blasting machine is installed on can moving movable support, the vibrator sets up on the arc formwork between each hydraulic stem. Can move movable support and install on laying the track, can move movable support and lay the track and pass through rollers matching. The utility model discloses can effectively reduce the construction degree of difficulty of preliminary bracing, can move movable support, shotcrete pipe, hydraulic stem and can effectively reduce the dust pollution who brings in the work progress through setting up, having reduced the construction and having polluted, the structure that adopts can be fine two lining constructions of assurance in waterproof material's planarization.

Description

Packaged type preliminary bracing spray concrete typified form
Technical field
In this practical constructing tunnel process, strengthen quality control on construction, accelerate work progress, belong to tunnel support technical field.
Background technology
In current constructing tunnel process, preliminary bracing all adopts dampen shotcreting method to construct, and springback capacity is comparatively large, and once whitewash and often can not reach designing requirement, arch and the section of backbreaking repeatedly need be whitewashed and could be met, and spray concrete there are certain requirements operator and machinery.
In dampen shotcreting method work progress:
1, concrete quality is wayward, and particularly water-cement ratio is with randomness; The concrete of wet shot sprays by being transported to wet-spraying machine after production technology production, and its match ratio is in slave mode completely, thus ensure that the quality of pneumatically placed concrete.
2, in operating process, in air, dust content is higher, and construction environment is poor, easily causes actual bodily harm to constructor.
Summary of the invention
It is large that the purpose of this utility model is to overcome rebound of shotcrete modulus in construction of shotcrete, can improve simultaneously and just prop up planeness and reduce construction cost, effectively to ensure that in two lining work progresss, waterproofing materials is smooth.
For achieving the above object, the technical solution adopted in the utility model is packaged type preliminary bracing spray concrete typified form, and this structure comprises movable supporting frame 1, shotcrete pipe 2, hydraulic stem 3, arc formwork 4, vibrator 5; Arc formwork 4 assembles assembling by little arc formwork, and each little arc formwork coordinates gap place to be filled with foam block; The surface of arc formwork 4 is arcuate structure, and the radius of arc formwork 4 is equal with construction tunnel radius; The inwall of arc formwork 4 is connected with movable supporting frame 1 by hydraulic stem 3, and the inwall of each hydraulic stem 3 arcuately template 4 is uniformly distributed; Shotcrete pipe 2 is arranged between arc formwork 4 and concrete spraying machine, and concrete spraying machine is arranged on movable supporting frame 1; Vibrator 5 is arranged on the arc formwork 4 between each hydraulic stem 3.
Described movable supporting frame 1 is arranged on to be laid on track, and movable supporting frame 1 is matched by roller with laying track.
Compared with prior art, the utility model effectively can reduce the difficulty of construction of preliminary bracing, and by arranging movable supporting frame, shotcrete pipe, hydraulic stem can effectively reduce the dust pollution brought in work progress, reduces construction pollution; The structure adopted well can ensure the planarization of waterproofing materials in two lining constructions.
Accompanying drawing explanation
Fig. 1 is the structural representation of packaged type preliminary bracing spray concrete typified form.
In figure: 1, movable supporting frame, 2, shotcrete pipe, 3, hydraulic stem, 4, arc formwork, 5, vibrator.
Detailed description of the invention
This practicality adopts packaged type stand masterplate arc length can determine according to Tunnel Design radius, and the general width of template is 2m, the thick 1cm of template.I iron adopts 20cm, and hydraulic stem adopts 5T, and vibrator vibrates 800W, shotcrete pipe 50mm, and wet-spraying machine adopts JRD-PS800 type concrete spraying machine.
Packaged type preliminary bracing spray concrete typified form adopts long 260 meters of template totally 2 meters × 11 pieces, i iron (20#A200*100), hydraulic stem 12, vibrator 9.
Template is detachable, can according to tunnel interior diameter and Height Adjustment size, and notice during use that template is fixed, whether nozzle blocks.
Concrete implementation step:
1, masterplate size is formulated according to on-site actual situations.
2, adopt hydraulic stem to add Gu Ding, to design elevation, and to fill up the gap between template with foam block.
3, spray match ratio to select.
4, suitable thickness is sprayed.

Claims (1)

1. packaged type preliminary bracing spray concrete typified form, is characterized in that: this structure comprises movable supporting frame (1), shotcrete pipe (2), hydraulic stem (3), arc formwork (4), vibrator (5); Arc formwork (4) assembles assembling by little arc formwork, and each little arc formwork coordinates gap place to be filled with foam block; The surface of arc formwork (4) is arcuate structure, and the radius of arc formwork (4) is equal with construction tunnel radius; The inwall of arc formwork (4) is connected with movable supporting frame (1) by hydraulic stem (3), and the inwall of each hydraulic stem (3) arcuately template (4) is uniformly distributed; Shotcrete pipe (2) is arranged between arc formwork (4) and concrete spraying machine, and concrete spraying machine is arranged on movable supporting frame (1); Vibrator (5) is arranged on the arc formwork (4) between each hydraulic stem (3); Described movable supporting frame (1) is arranged on pre-to be laid on track, and movable supporting frame (1) is laid track matched by roller with pre-.
CN201520580678.1U 2015-08-04 2015-08-04 Concrete typical forms is spouted in movable preliminary bracing Expired - Fee Related CN204827477U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520580678.1U CN204827477U (en) 2015-08-04 2015-08-04 Concrete typical forms is spouted in movable preliminary bracing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520580678.1U CN204827477U (en) 2015-08-04 2015-08-04 Concrete typical forms is spouted in movable preliminary bracing

Publications (1)

Publication Number Publication Date
CN204827477U true CN204827477U (en) 2015-12-02

Family

ID=54685088

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520580678.1U Expired - Fee Related CN204827477U (en) 2015-08-04 2015-08-04 Concrete typical forms is spouted in movable preliminary bracing

Country Status (1)

Country Link
CN (1) CN204827477U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106930777A (en) * 2017-04-14 2017-07-07 中铁六局集团有限公司 The construction method of the lining of Bored Section of Metro main track assembled two
CN108506024A (en) * 2018-04-17 2018-09-07 蓝传雯 A kind of construction method and supporting mold of Tunnel
CN109296386A (en) * 2018-11-26 2019-02-01 蓝传雯 A kind of preceding arm mechanism for mould spray
CN109356619A (en) * 2018-11-26 2019-02-19 蓝传雯 A kind of new concrete mould spraying equipment

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106930777A (en) * 2017-04-14 2017-07-07 中铁六局集团有限公司 The construction method of the lining of Bored Section of Metro main track assembled two
CN106930777B (en) * 2017-04-14 2018-08-24 中铁六局集团有限公司 The construction method that Bored Section of Metro main track assembled two serves as a contrast
CN108506024A (en) * 2018-04-17 2018-09-07 蓝传雯 A kind of construction method and supporting mold of Tunnel
CN109296386A (en) * 2018-11-26 2019-02-01 蓝传雯 A kind of preceding arm mechanism for mould spray
CN109356619A (en) * 2018-11-26 2019-02-19 蓝传雯 A kind of new concrete mould spraying equipment
CN109296386B (en) * 2018-11-26 2024-03-29 四川蓝海智能装备制造有限公司 Forearm mechanism for die spraying
CN109356619B (en) * 2018-11-26 2024-03-29 四川蓝海智能装备制造有限公司 Novel concrete mould spouts equipment

Similar Documents

Publication Publication Date Title
CN204827477U (en) Concrete typical forms is spouted in movable preliminary bracing
CN206737446U (en) A kind of portable masonry panel paving slurry instrument
CN205078283U (en) Tunnel geotechnique's cloth, waterproof board shop cloth machine
CN109208924B (en) Brick joint filling and pointing device and construction method
CN109296184B (en) Method for filling and pointing ceramic tile joints in tunnel
CN103775104A (en) Wet concrete spouting process for use under coal mine
CN208009855U (en) A kind of floor tile construction brick paving machine
CN111305322A (en) Construction structure and construction method for mounting large-diameter steel pipe by adopting shield tunnel
CN102678136B (en) Dual-reduction turnover construction process for sprayed concrete
CN205223976U (en) Irrigation gallery concrete slipform device
CN107100649B (en) Construction process for inclined shaft concrete pouring
CN110671132B (en) Deep loess tunnel deformation control construction structure and method based on sleeve arch
CN204530499U (en) For the automatic travelling device of highway bridge prefabrication beam slab concrete distributing
CN105781584A (en) Concrete wet-spraying self-walking shotcrete support robot
CN217107037U (en) Slip form construction system for TBM tunnel concrete injection
CN106481349B (en) Tunnel lining concrete grouting device and its construction method
CN209942173U (en) Concrete spraying device
CN115897589A (en) Waterproof concrete interval pouring construction method for buried sewage treatment plant
CN109505626B (en) Method for spraying support mold at initial stage of tunnel by using belt template assembly
CN108590208A (en) A kind of building wall is laid with mortar construction equipment and its application method automatically
CN210857547U (en) Be used for outer wall screw rod entrance to a cave plugging device
CN113931350A (en) Construction method of composite light sandwich partition wall
CN113833003A (en) Construction method of raft plate of oversized clean workshop
CN104912209A (en) Plugging device for pipeline reserved hole of cast-in-situ slab and machining and plugging construction method
CN105257317A (en) Loose large-section roadway support technology

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151202

Termination date: 20210804