CN204793659U - Medium and small generating set combination formula installation formula generator cell equipment - Google Patents

Medium and small generating set combination formula installation formula generator cell equipment Download PDF

Info

Publication number
CN204793659U
CN204793659U CN201520352218.3U CN201520352218U CN204793659U CN 204793659 U CN204793659 U CN 204793659U CN 201520352218 U CN201520352218 U CN 201520352218U CN 204793659 U CN204793659 U CN 204793659U
Authority
CN
China
Prior art keywords
room
equipment box
equipment
excitation
generator cell
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520352218.3U
Other languages
Chinese (zh)
Inventor
刘军文
王广波
范惠
刘万山
秦娜娜
石晓义
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Sinogy Electric Engineering Co Ltd
Original Assignee
China Sinogy Electric Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Sinogy Electric Engineering Co Ltd filed Critical China Sinogy Electric Engineering Co Ltd
Priority to CN201520352218.3U priority Critical patent/CN204793659U/en
Application granted granted Critical
Publication of CN204793659U publication Critical patent/CN204793659U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Patch Boards (AREA)

Abstract

The utility model discloses a medium and small generating set combination formula installation formula generator cell equipment, become the room including high -pressure PT room and excitation, high -pressure PT room and excitation change room aggregate erection component equipment box, arrange three high tension switchgear of welding, high tension switchgear's model KYN28 -12 type in the high pressure PT room in proper order along equipment box width direction, the excitation turns indoor and sets up the excitation transformer. This equipment box is installed at the interplant, delivers to the engineering scene after the debugging finishes. Site work only need carry out the hookup of corresponding basis of equipment box and business turn over line, can accomplish the generator equipment fixing work of being qualified for the next round of competitions very fast, the effectual installation progress of having accelerated not only, and simultaneously because it is the aggregate erection, the effectual occupation of land space of having saved.

Description

Small generation set composite type installing type generator cell equipment in one
Technical field
The utility model relates to a kind of generator cell, specifically small generation set composite type installing type generator cell equipment in one.
Background technology
In present medium and small generator group engineering construction, the generator outlet cell be directly connected with generator voltage power distribution equipment, the equipment of the little indoor of general outlet is fewer, arrange fairly simple, generally be arranged in steam turbine building 0 meter of layer Generator end, line-outgoing equipment can select fixing cabinet XGN type or withdraw-type switch cabinet KYN28 type, and according to equipment size reasonable Arrangement, meet the safety net distance of power distribution equipment regulations stipulate and make an inspection tour maintenance channel requirement, thus determine the size of generator cell, to building, structure discipline entrusts the size of cell, cabinet installation foundation, cable trough, built-in fitting etc., finally carry out design and construction by Civil Specialities, venting practice is considered by heating and ventilating discipline.All the time, generator cell floor space is comparatively large, and its design man-hour, all burdensome and troubles, and also consume a large amount of civil engineerings and equipment set-up time at work progress, added construction and mounting cost in electric and Civil Specialities work.
Utility model content
The purpose of this utility model is to provide small generation set composite type installing type generator cell equipment in one, to solve the problem proposed in above-mentioned background technology.
For achieving the above object, the utility model provides following technical scheme:
Small generation set composite type installing type generator cell equipment in one, comprise high pressure P T room and excitation change room, high pressure P T room and excitation become room combination and install constitution equipment casing, welding three high-tension switch cabinets are arranged in order along equipment box Width, the model KYN28-12 type of high-tension switch cabinet in described high pressure P T room; Excitation becomes indoor and arranges excitation transformer.
As further program of the utility model: the height of described high-tension switch cabinet and the free height of equipment box are consistent, the bus-bar room sidewall of high-tension switch cabinet leaves access hole for convenience detach.
As further program of the utility model: the installation panel of described high-tension switch cabinet is installed generator outlet measuring instrument, the position of the corresponding measuring instrument in equipment box side arranges observation window, and observation window is transparent organic glass window.
As further program of the utility model: the inner high voltage bus of described equipment box adopts insulating barrier and silicon rubber insulating sleeve turnover.
As further program of the utility model: described equipment box is sealed by special steel plate or aluminium alloy plate and is made.
As further program of the utility model: the inside of described equipment box arranges forced ventilation structure, namely high pressure P T indoor location has two one, the air-conditioning processed of 3P, and excitation change is equipped with ventilating fan two in room, and ventilating fan connects attemperating unit.
As further program of the utility model: the pre-buried 10# channel-section steel of base foundation loading end of described equipment box, the end face of 10# channel-section steel is a little more than basic loading end, and the ground lead bottom equipment box should be no less than two, and ground lead connects earth resistance.
Compared with prior art, the beneficial effects of the utility model are: concentrated by all dispersing apparatus in loading movable whole-sealed, anti-condensation equipment box, compound mode is versatile and flexible, single devices technology maturation.This equipment box is installed in factory, delivers to engineering site after debugging.Work on the spot only need carry out the connection of the corresponding basis of equipment box and line, can complete generator outlet fitter's work very soon, not only effectively accelerate installation progress, simultaneously because it is installed for combining, effectively saving and taking up an area space.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
Fig. 2 is the outlet structure schematic diagram of high pressure P T indoor.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, be clearly and completely described the technical scheme in the utility model embodiment, obviously, described embodiment is only the utility model part embodiment, instead of whole embodiments.Based on the embodiment in the utility model, those of ordinary skill in the art are not making the every other embodiment obtained under creative work prerequisite, all belong to the scope of the utility model protection.
Refer to Fig. 1 ~ 2, in the utility model embodiment, small generation set composite type installing type generator cell equipment in one, comprise high pressure P T room 2 and excitation change room 3, high pressure P T room 2 and excitation become room 3 and combine installation constitution equipment casing, welding three high-tension switch cabinets 1 (also can be other fixed high-pressure cabinet) are arranged in order along equipment box Width, the model KYN28-12 type of high-tension switch cabinet 1 in described high pressure P T room 2.
Excitation change arranges excitation transformer 4 in room 3, and be convenient transportation, the Width of excitation transformer 4 does not generally allow to widen, if according to actual needs, when cabinet requires to increase not, can by equipment box extended length, and excitation becomes room 3 can transverse arrangement of turbo.
The described height of high-tension switch cabinet 1 and the free height of equipment box are consistent, and the bus-bar room sidewall of high-tension switch cabinet 1 leaves access hole for convenience detach.
The installation panel 6 of described high-tension switch cabinet 1 installs generator outlet measuring instrument, comprise the measuring instruments such as generator outlet voltage, electric current, power, frequency, power factor, electric energy, and all measuring instruments require to have teletransmission communication interface and 4 ~ 20mA weak electric signal interface.Measuring instrument on high-voltage board front panel should be able to be visible outward at equipment box, therefore require that the corresponding meter location in this side of equipment box arranges observation window, and observation window adopts transparent organic glass window or other transparent material.
The inner high voltage bus of described equipment box adopts insulating barrier+silicon rubber insulating sleeve turnover, and concrete outlet position should cooperatively interact with generator outlet copper bar position and determine.
The structure of described equipment box should have functions of waterproof and dustproof, adopts special steel plate or aluminium alloy plate to make, through preservative treatment, and long service life, simultaneously good looking appearance.
The inside of described equipment box arranges forced ventilation structure, is namely provided with two one, the air-conditioning processed of 3P in high pressure P T room 2, and excitation change is equipped with ventilating fan two in room 3, and make ventilating and cooling good, ventilating fan has attemperating unit, automatically starts and close by design temperature.
The base foundation loading end of described equipment box answers pre-buried 10# channel-section steel, and the end face of 10# channel-section steel is a little more than basic loading end (≯ 3mm), and the ground lead bottom equipment box should be no less than two, and guarantees earth resistance.
To those skilled in the art, obvious the utility model is not limited to the details of above-mentioned one exemplary embodiment, and when not deviating from spirit of the present utility model or essential characteristic, can realize the utility model in other specific forms.Therefore, no matter from which point, all should embodiment be regarded as exemplary, and be nonrestrictive, scope of the present utility model is limited by claims instead of above-mentioned explanation, and all changes be therefore intended in the implication of the equivalency by dropping on claim and scope are included in the utility model.Any Reference numeral in claim should be considered as the claim involved by limiting.
In addition, be to be understood that, although this specification is described according to execution mode, but not each execution mode only comprises an independently technical scheme, this narrating mode of specification is only for clarity sake, those skilled in the art should by specification integrally, and the technical scheme in each embodiment also through appropriately combined, can form other execution modes that it will be appreciated by those skilled in the art that.

Claims (6)

1. small generation set composite type installing type generator cell equipment in one kind, it is characterized in that, comprise high pressure P T room and excitation change room, high pressure P T room and excitation become room combination and install constitution equipment casing, welding three high-tension switch cabinets are arranged in order along equipment box Width, the model KYN28-12 type of high-tension switch cabinet in described high pressure P T room; Excitation becomes indoor and arranges excitation transformer.
2. small generation set composite type installing type generator cell equipment in one according to claim 1, it is characterized in that, the height of described high-tension switch cabinet and the free height of equipment box are consistent, and the bus-bar room sidewall of high-tension switch cabinet leaves access hole for convenience detach.
3. small generation set composite type installing type generator cell equipment in one according to claim 1, it is characterized in that, the installation panel of described high-tension switch cabinet is installed generator outlet measuring instrument, the position of the corresponding measuring instrument in equipment box side arranges observation window, and observation window is transparent organic glass window.
4. small generation set composite type installing type generator cell equipment in one according to claim 1, is characterized in that, the inner high voltage bus of described equipment box adopts insulating barrier and silicon rubber insulating sleeve turnover.
5. small generation set composite type installing type generator cell equipment in one according to claim 1, is characterized in that, described equipment box is sealed by special steel plate or aluminium alloy plate and is made.
6. small generation set composite type installing type generator cell equipment in one according to claim 1, it is characterized in that, the inside of described equipment box arranges forced ventilation structure, namely high pressure P T indoor location has two one, the air-conditioning processed of 3P, excitation change is equipped with ventilating fan two in room, and ventilating fan connects attemperating unit.
Small generation set composite type installing type generator cell equipment in one according to claim 1, it is characterized in that, the pre-buried 10# channel-section steel of base foundation loading end of described equipment box, the end face of 10# channel-section steel is a little more than basic loading end, and the ground lead bottom equipment box should be no less than two, ground lead connects earth resistance.
CN201520352218.3U 2015-08-13 2015-08-13 Medium and small generating set combination formula installation formula generator cell equipment Expired - Fee Related CN204793659U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520352218.3U CN204793659U (en) 2015-08-13 2015-08-13 Medium and small generating set combination formula installation formula generator cell equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520352218.3U CN204793659U (en) 2015-08-13 2015-08-13 Medium and small generating set combination formula installation formula generator cell equipment

Publications (1)

Publication Number Publication Date
CN204793659U true CN204793659U (en) 2015-11-18

Family

ID=54533644

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520352218.3U Expired - Fee Related CN204793659U (en) 2015-08-13 2015-08-13 Medium and small generating set combination formula installation formula generator cell equipment

Country Status (1)

Country Link
CN (1) CN204793659U (en)

Similar Documents

Publication Publication Date Title
CN203774640U (en) Switch cabinet body
CN204885964U (en) Photovoltaic case becomes with contravariant function of stepping up
JP2011210810A (en) Smart grid power generation method and monitoring system therefor
CN209881133U (en) Heat dissipation type high-low voltage power distribution cabinet
CN201975713U (en) Novel box-type substation
CN203562669U (en) Outdoor power equipment pedestal
CN204947387U (en) High-tension electricity gas tank
CN204793659U (en) Medium and small generating set combination formula installation formula generator cell equipment
CN206878361U (en) A kind of outer casing of box type transformer substation with noise reduction and refrigerating function
CN208923686U (en) A kind of intelligent Prefabricated Cubical Substation with operational system
CN204651710U (en) A kind of outdoor distribution low-voltage comprehensive distribution box
CN203895820U (en) Compact totally-enclosed mobile substation
CN204927935U (en) Looped netowrk electrical switching cabinet equipment
CN204156326U (en) The assembly type base of switch cubicle
CN212046927U (en) Box-type charging station
CN203415857U (en) Economical electrical cabinet
CN204030334U (en) A kind of distributed board outdoor
CN212659845U (en) 10kV high tension switchgear with secondary cable chamber on top
CN207052982U (en) A kind of switch cubicle
CN210156749U (en) Miniature centrally installed switchgear
CN208548596U (en) A kind of high-voltage board KYN
CN107069363A (en) A kind of SF6The quick switching device of insulative distributing
CN113071347A (en) Box-type charging station
CN101707327A (en) One-piece integrated cabinet of electric quantity calculation, leakage protection and phase splitting compensation
CN203103798U (en) Suspension type outdoor and low-voltage comprehensive distribution metering box

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Liu Junwen

Inventor after: Wang Guangbo

Inventor after: Yuan Hui

Inventor after: Liu Wanshan

Inventor after: Qin Nana

Inventor after: Shi Xiaoyi

Inventor before: Liu Junwen

Inventor before: Wang Guangbo

Inventor before: Fan Hui

Inventor before: Liu Wanshan

Inventor before: Qin Nana

Inventor before: Shi Xiaoyi

COR Change of bibliographic data
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151118