CN204749891U CN201520434651.1U CN201520434651U CN204749891U CN 204749891 U CN204749891 U CN 204749891U CN 201520434651 U CN201520434651 U CN 201520434651U CN 204749891 U CN204749891 U CN 204749891U
Authority
CN
China
Prior art keywords
insulator
load formula
bolt
section steel
channel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520434651.1U
Other languages
Chinese (zh)
Inventor
李增勤
高鸣
蔡昌俊
马金芳
谭冬华
崔莹
邹科务
罗亚敏
庞开阳
高劲
池代臻
江鸣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Electrification Engineering Group Co Ltd
Guangzhou Metro Group Co Ltd
China Railway Electric Industry Co Ltd
Baoji Equipment Co Ltd of China Railway Electrification Engineering Group Co Ltd
Original Assignee
China Railway Electrification Engineering Group Co Ltd
China Railway Electric Industry Co Ltd
Baoji Equipment Co Ltd of China Railway Electrification Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Electrification Engineering Group Co Ltd, China Railway Electric Industry Co Ltd, Baoji Equipment Co Ltd of China Railway Electrification Engineering Group Co Ltd filed Critical China Railway Electrification Engineering Group Co Ltd
Priority to CN201520434651.1U priority Critical patent/CN204749891U/en
Application granted granted Critical
Publication of CN204749891U publication Critical patent/CN204749891U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a smooth load formula rigid insulation hanging device, including suspending the channel -section steel in midair, the insulator, be used for fixed busbar, should suspend in midair is connected with 2 smooth load formula gallowss on the channel -section steel, this cunning load formula gallows is including jack catch that is located upper portion and the die -pin that is located the lower part, the jack catch card of these 2 smooth load formula gallowss is after on this suspends the channel -section steel in midair, have one to be the first bolt of horizontally and to link together these 2 smooth load formula gallowss, this insulator upper portion is that the gold utensil is " one " font metal sheet on the insulator, the upper portion at these 2 die -pins is partially do not inserted on the both sides of this metal sheet, the lower part of this insulator is fixed with one and is vertical second bolt, this second bolt is connected a registration clamp that is " U " font on this insulator, 2 the lower part of this registration clamp is fixed in this busbar at the third bolt of 2 avriss of this registration clamp in individual connection. The utility model has the advantages that: can prevent or reduce the jamming phenomenon to appear, and the busbar can smoothly slide in the anchor section when expend with heat and contract with cold.

Description

Sliding load formula rigid insulation suspension apparatus
Technical field
The present invention relates to track traffic component technology field, especially relate to a kind of sliding load formula rigid insulation suspension apparatus.
Background technology
Stream row rigid suspension system is a kind of important power supply system in track traffic, and bus duct is along line arrangement, for locomotive provides electric power, is its important component part.This bus duct not only stably will be suspended on fixed position, and need can bearing temperature change cause expand with heat and contract with cold.The bus duct of prior art is hung by the steady ear installed on the insulator, and insulator is connected on suspention channel-section steel.This connection mode is slided by the gap between bus duct and steady ear, and what compensation bus duct caused because of temperature traverse expands with heat and contract with cold.But, the hitch point of rigid suspension system is more, due to the finite gap between steady ear and bus duct, when running into the section such as minor radius or heavy grade circuit, glade plane space less in this hang very easily causes bus duct clamping stagnation, cause bus duct to be out of shape, then affect current carrying quality, even cause equipment to lose.
Summary of the invention
The object of this invention is to provide a kind of sliding load formula rigid insulation suspension apparatus, it has to prevent or to reduce and occurs catching phenomenon, and bus duct can slide swimmingly when expanding with heat and contract with cold in anchor section, then making locomotive well be flowed, the feature demonstrate,proving traffic safety can be guaranteed.
The technical solution adopted in the present invention is: sliding load formula rigid insulation suspension apparatus, comprise suspention channel-section steel, insulator, for fixing bus duct, described suspention channel-section steel is connected with 2 sliding load formula suspension brackets, this cunning load formula suspension bracket comprises superposed claw and is positioned at the pressure pin of bottom, after the claw of these 2 sliding load formula suspension brackets is stuck on this suspention channel-section steel, one is had to be linked together by these 2 sliding load formula suspension brackets in the first bolt of level, simultaneously, this insulator top and hardware fitting on insulator are " one " font metal sheet, the both sides portion of this metal sheet is inserted in the top of these 2 pressure pins respectively, the bottom of this insulator is fixed with one in the second vertical bolt, this second bolt is connected on this insulator by one in the steady ear of " U " font, and, this bus duct is fixed on the bottom of this steady ear by 2 the 3rd bolts being connected to 2 avris of this steady ear.
The present invention is advantageously: can prevent or reduce and occur catching phenomenon, and in anchor section, bus duct can slide swimmingly when expanding with heat and contract with cold.Sliding load formula rigid insulation suspension apparatus of the present invention, by changing bus duct at the sliding type of hitch point, reliably solves the clamping stagnation of bus duct.Meanwhile, be linear contact lay between sliding load formula suspension bracket and the metal sheet of insulator, friction force is little; and the gap slided between load formula suspension bracket and the metal sheet of insulator is larger; relative motion both convenient, even if thus have larger expanding with heat and contract with cold, also can guarantee the smooth and easy slip of bus duct.
Accompanying drawing explanation
Below in conjunction with drawings and Examples, the present invention is further described:
Fig. 1 is the front view of the sliding load formula rigid insulation suspension apparatus of embodiments of the invention;
Fig. 2 is the schematic perspective view of the sliding load formula rigid insulation suspension apparatus of embodiments of the invention;
Fig. 3 is the schematic perspective view (amplifying relative to Fig. 2) of sliding load formula suspension bracket of the present invention;
Fig. 4 is the schematic perspective view (amplifying relative to Fig. 2) of insulator of the present invention;
Fig. 5 is the schematic perspective view (amplifying relative to Fig. 2) of steady ear of the present invention and link thereof.
In figure:
10, channel-section steel is suspended in midair;
20, load formula suspension bracket is slided, 21, claw, 22, pressure pin, the 23, first bolt, 24, connecting arm;
30, insulator, 31, metal sheet;
41, the second bolt, 42, steady ear, the 43, the 3rd bolt;
50, bus duct.
Detailed description of the invention
Embodiment, is shown in shown in Fig. 1 to Fig. 5: sliding load formula rigid insulation suspension apparatus, comprises suspention channel-section steel 10, insulator 30, for fixing bus duct 50.
Concretely, this suspention channel-section steel 10 is connected with 2 sliding load formula suspension brackets 20.This cunning load formula suspension bracket 20 comprises superposed claw 21 and is positioned at the pressure pin 22 of bottom.The two ends of this pressure pin 22 are fixed on 2 connecting arms 24 extending downwards from the bottom of this cunning load formula suspension bracket 20.After the claw 21 of these 2 sliding load formula suspension brackets 20 is stuck on this suspention channel-section steel 10, first bolt 23 in level is had to be linked together by these 2 sliding load formula suspension brackets 20.Certainly, these 2 sliding 20 points, load formula suspension brackets occupy the both sides of this suspention channel-section steel 10.Meanwhile, this insulator 30 top and hardware fitting on insulator are " one " font metal sheet 31, and the both sides portion of this metal sheet 31 is inserted in the top of these 2 pressure pins 22 respectively.That is, these 2 pressure pins 22 are supported on the both sides of this metal sheet 31.The bottom of this insulator 30 is fixed with one in the second vertical bolt 41, and a steady ear 42 in " U " font is connected on this insulator 30 by this second bolt 41.Obviously, the top of this second bolt 41 is preferably fixed on this insulator 30 bottom, and this steady ear 42 can with this second bolt 41 for axis carries out 360 ° of rotations.And this bus duct 50 is fixed on the bottom of this steady ear 42 by the 3rd bolt 43 having 2 to be connected to 2 avris of this steady ear 42.
Like this, this sliding load formula rigid insulation suspension apparatus, by changing bus duct at the sliding type of hitch point, reliably solves the clamping stagnation of bus duct.Meanwhile, be linear contact lay between sliding load formula suspension bracket and the metal sheet of insulator, friction force is little; and the gap slided between load formula suspension bracket and the metal sheet of insulator is larger; relative motion both convenient, even if thus have larger expanding with heat and contract with cold, also can guarantee the smooth and easy slip of bus duct.
The foregoing is only the preferred embodiments of the present invention; not thereby the scope of the claims of the present invention is limited; every utilize specification sheets of the present invention and accompanying drawing content to do equivalent structure or equivalent flow process conversion; or be directly or indirectly used in other relevant technical fields, be all in like manner included in scope of patent protection of the present invention.

Claims (1)

1. slide load formula rigid insulation suspension apparatus, comprise suspention channel-section steel (10), insulator (30), for fixing bus duct (50), it is characterized in that: described suspention channel-section steel (10) is connected with 2 sliding load formula suspension brackets (20), this cunning load formula suspension bracket (20) comprises superposed claw (21) and is positioned at the pressure pin (22) of bottom, the claw (21) of these 2 sliding load formula suspension brackets (20) be stuck in this suspention channel-section steel (10) upper after, one is had these 2 sliding load formula suspension brackets (20) to be linked together in first bolt (23) of level, simultaneously, this insulator (30) top and hardware fitting on insulator are " one " font metal sheet (31), the both sides portion of this metal sheet (31) is inserted in the top of these 2 pressure pins (22) respectively, the bottom of this insulator (30) is fixed with one in vertical the second bolt (41), this second bolt (41) is connected on this insulator (30) by one in the steady ear (42) of " U " font, and, this bus duct (50) is fixed on the bottom of this steady ear (42) by 2 the 3rd bolts (43) being connected to 2 avris of this steady ear (42).
CN201520434651.1U 2015-06-23 2015-06-23 Smooth load formula rigid insulation hanging device Expired - Fee Related CN204749891U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520434651.1U CN204749891U (en) 2015-06-23 2015-06-23 Smooth load formula rigid insulation hanging device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520434651.1U CN204749891U (en) 2015-06-23 2015-06-23 Smooth load formula rigid insulation hanging device

Publications (1)

Publication Number Publication Date
CN204749891U true CN204749891U (en) 2015-11-11

Family

ID=54464636

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520434651.1U Expired - Fee Related CN204749891U (en) 2015-06-23 2015-06-23 Smooth load formula rigid insulation hanging device

Country Status (1)

Country Link
CN (1) CN204749891U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111806307A (en) * 2020-06-05 2020-10-23 天津中铁电气化设计研究院有限公司 Movable contact net at civil air defense partition door

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111806307A (en) * 2020-06-05 2020-10-23 天津中铁电气化设计研究院有限公司 Movable contact net at civil air defense partition door

Similar Documents

Publication Publication Date Title
CN103296623B (en) Tube busbar suspension fitting for converter station valve hall
CN204779895U (en) A set oxidation treatment hanger generates heat
CN204749891U (en) Smooth load formula rigid insulation hanging device
CN204037376U (en) A kind of anti-clamping stagnation suspension gear for rigid suspension catenary
CN103236659A (en) Near-pole maintenance hanging rack for power transmission line
CN204954276U (en) Frock is fixed a position with main pipe welding to branch's pipeline
CN204300518U (en) Heat distribution pipeline suspention buckle structure
CN102718124A (en) Anti-slipping lifting appliance
CN204917611U (en) Bent axle hoist
CN210798460U (en) Iron tower cross arm rope ladder suspension point extension fixture
CN202575695U (en) I-shaped steel holding clamp
CN203384609U (en) Wall-mounted rack for liquid crystal spliced curtain wall hanging screen
CN203850575U (en) Substation aluminum row grounding wire connection structure
CN205368518U (en) Self -adaptation formula titanium alloy hanger
CN104348115A (en) Wing type automatic conductor clamping device with automatic locking device
CN204274063U (en) A kind of novel clothes hanger
CN104392666A (en) Cable warning board installing frame
CN204580803U (en) A kind of novel clothes hanger
CN202591960U (en) Crankshaft suspension device for diesel engine
CN207122978U (en) A kind of frame for fixing heat sink
CN204749892U (en) Overhead contact line rigid suspension system device
CN211475430U (en) Inverter wall surface mounting structure
CN220732325U (en) Fixing device of wire link
CN216723547U (en) Blower bracket
CN103615301B (en) A kind of automotive muffler erecting by overhang

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20151105

Address after: 100036 Beijing City, Fengtai District Wanshou Road South Golden Village No. 1

Patentee after: Zhongtie Electric Bureau Group Co., Ltd.

Patentee after: In ferroelectric gas Industrial Co., Ltd

Patentee after: China Railway Electrification Bureau Group Baoji Equipment Co., Ltd.

Patentee after: GUANGZHOU METRO GROUP CO., LTD.

Address before: 100036 Beijing City, Fengtai District Wanshou Road South Golden Village No. 1

Patentee before: Zhongtie Electric Bureau Group Co., Ltd.

Patentee before: In ferroelectric gas Industrial Co., Ltd

Patentee before: China Railway Electrification Bureau Group Baoji Equipment Co., Ltd.