CN204715359U - A kind of novel pile sinking leading truck - Google Patents

A kind of novel pile sinking leading truck Download PDF

Info

Publication number
CN204715359U
CN204715359U CN201520357002.6U CN201520357002U CN204715359U CN 204715359 U CN204715359 U CN 204715359U CN 201520357002 U CN201520357002 U CN 201520357002U CN 204715359 U CN204715359 U CN 204715359U
Authority
CN
China
Prior art keywords
guide ring
leading truck
pile sinking
truss
fixedly connected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520357002.6U
Other languages
Chinese (zh)
Inventor
邢雪梅
李振旺
张得义
张延峰
赵明江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Harbour Co Ltd
Original Assignee
Sinohydro Harbour Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Harbour Co Ltd filed Critical Sinohydro Harbour Co Ltd
Priority to CN201520357002.6U priority Critical patent/CN204715359U/en
Application granted granted Critical
Publication of CN204715359U publication Critical patent/CN204715359U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model relates to a kind of leading truck, specifically a kind of novel pile sinking leading truck, comprise the guide beam of horizontal positioned, equally spacedly on described guide beam be vertically fixedly installed many sub-trusses, the described truss of each pair is all fixedly connected with all horizontally disposed upper guide ring and lower guide ring, described upper guide ring and described lower guide ring are up and down just to setting.Beneficial effect is that structure is simple, and make simple and easy, material consumption amount is little, and cost of production is low, can guarantee verticality and the stability of pile sinking.

Description

A kind of novel pile sinking leading truck
Technical field
The utility model relates to a kind of leading truck, specifically a kind of novel pile sinking leading truck.
Background technology
In the construction of harbour pile driving engineering, commonly use leading truck to lead as pile sinking, guarantee verticality and the stability of pile sinking, traditional leading truck is verticality and the stability of guaranteeing pile sinking stake, usually adopts the leading truck of tape guide groove, and this gathering sill is usually in being with the cylindric of mesopore, although verticality and the stability of pile sinking can be guaranteed preferably, but make complicated, material consumption amount is large, and cost of production is high.
Utility model content
It is simple that technical problem to be solved in the utility model is to provide a kind of structure, and make simple and easy, material consumption amount is little, the novel pile sinking leading truck that cost of production is low, can guarantee verticality and the stability of pile sinking.
The technical scheme that the utility model solves the problems of the technologies described above is as follows: a kind of novel pile sinking leading truck, comprise the guide beam of horizontal positioned, equally spacedly on described guide beam be vertically fixedly installed many sub-trusses, the described truss of each pair is all fixedly connected with all horizontally disposed upper guide ring and lower guide ring, described upper guide ring and described lower guide ring are up and down just to setting.
The beneficial effects of the utility model are: stake can be carried out piling construction through described upper guide ring and lower guide ring, and structure is simple, and make simple and easy, material consumption amount is little, and cost of production is low, can guarantee verticality and the stability of pile sinking; In addition, many sub-trusses are vertically fixedly installed due to equally spaced on described guide beam, the described truss of each pair is all fixedly connected with the upper guide ring vertical with described truss and lower guide ring, makes the utility model can carry out piling construction to many piles simultaneously, improve piling construction efficiency.
On the basis of technique scheme, the utility model can also do following improvement.
Further, described upper guide ring is positioned at the upper end of described truss, and described lower guide ring is positioned at the lower end of described truss, further ensure that verticality and the stability of pile sinking.
Further, described upper guide ring is fixedly connected with described truss by screw with lower guide ring, improves the reliability that described upper guide ring is fixedly connected with described truss with lower guide ring.
Further, described truss is fixedly connected with described guide beam by welding, improves the reliability that described truss is fixedly connected with described guide beam.
Accompanying drawing explanation
Fig. 1 is left view of the present utility model;
Fig. 2 is top view of the present utility model;
In accompanying drawing, the list of parts representated by each label is as follows:
1, guide beam, 2, truss, 3, upper guide ring, 4, lower guide ring.
Detailed description of the invention
Be described principle of the present utility model and feature below in conjunction with accompanying drawing, example, only for explaining the utility model, is not intended to limit scope of the present utility model.
As depicted in figs. 1 and 2, a kind of novel pile sinking leading truck, comprise the guide beam 1 of horizontal positioned, equally spacedly on guide beam 1 be vertically fixedly installed many sub-trusses 2, each sub-truss 2 is all fixedly connected with all horizontally disposed upper guide ring 3 and lower guide ring 4, upper guide ring 3 and lower guide ring about 4 are just to setting.
In the present embodiment, upper guide ring 3 is positioned at the upper end of truss 2, and lower guide ring 4 is positioned at the lower end of truss 2; Upper guide ring 3 is fixedly connected with truss 2 by screw with lower guide ring 4; Truss 2 is fixedly connected with guide beam 1 by welding.
The foregoing is only preferred embodiment of the present utility model, not in order to limit the utility model, all within spirit of the present utility model and principle, any amendment done, equivalent replacement, improvement etc., all should be included within protection domain of the present utility model.

Claims (4)

1. a novel pile sinking leading truck, it is characterized in that: the guide beam (1) comprising horizontal positioned, equally spacedly vertically be fixedly installed many sub-trusses (2) described guide beam (1) is upper, the described truss of each pair (2) is all fixedly connected with all horizontally disposed upper guide ring (3) and lower guide ring (4), described upper guide ring (3) and described lower guide ring (4) are up and down just to setting.
2. the novel pile sinking leading truck of one according to claim 1, it is characterized in that: described upper guide ring (3) is positioned at the upper end of described truss (2), described lower guide ring (4) is positioned at the lower end of described truss (2).
3. the novel pile sinking leading truck of one according to claim 1 and 2, is characterized in that: described upper guide ring (3) is fixedly connected with described truss (2) by screw with lower guide ring (4).
4. the novel pile sinking leading truck of one according to claim 1 and 2, is characterized in that: described truss (2) is fixedly connected with described guide beam (1) by welding.
CN201520357002.6U 2015-05-28 2015-05-28 A kind of novel pile sinking leading truck Expired - Fee Related CN204715359U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520357002.6U CN204715359U (en) 2015-05-28 2015-05-28 A kind of novel pile sinking leading truck

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520357002.6U CN204715359U (en) 2015-05-28 2015-05-28 A kind of novel pile sinking leading truck

Publications (1)

Publication Number Publication Date
CN204715359U true CN204715359U (en) 2015-10-21

Family

ID=54314363

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520357002.6U Expired - Fee Related CN204715359U (en) 2015-05-28 2015-05-28 A kind of novel pile sinking leading truck

Country Status (1)

Country Link
CN (1) CN204715359U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113431042A (en) * 2021-05-18 2021-09-24 中铁大桥局集团第五工程有限公司 Guide structure for constructing straight-driving steel pipe pile and construction method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113431042A (en) * 2021-05-18 2021-09-24 中铁大桥局集团第五工程有限公司 Guide structure for constructing straight-driving steel pipe pile and construction method thereof

Similar Documents

Publication Publication Date Title
BR112012013104A2 (en) crane boom transition structure.
CN204715359U (en) A kind of novel pile sinking leading truck
CN204253048U (en) A kind of shield launching reaction frame for the engineering construction of shield structure
CN204199307U (en) A kind of resistance wave device of hydraulic engineering construction
CN204309082U (en) Hogging moment stretching notch combed template
CN203613541U (en) Driving device for vertical pipe sinking in shallow sea reclamation area
CN204690599U (en) Road and bridge engineering protector
CN204370390U (en) A kind of phreatic high pressure pipeline drainage system structure
CN203793792U (en) Beam frame of paper box packer
CN206827969U (en) Jib crane
CN205046578U (en) Ecological gabion retaining wall
CN205242415U (en) Hydraulic engineering salvagees protection module of usefulness
CN202642845U (en) Piler column structure
CN204530988U (en) A kind of large span lattice crane beam
CN204174547U (en) The highway bridge paravent that can advertise
CN204238129U (en) The multi-functional paravent of highway bridge
CN209179023U (en) A kind of novel groove support
CN203793793U (en) Connecting seat of paper box packer
CN204335199U (en) Door-sliding rack body
CN203654696U (en) Structural steel operating platform for setting lift shaft
CN204001929U (en) A kind of 10 ° of Novel iron towers with interior landform of the gradient that are applicable to
CN203008507U (en) Stator for bearing vertical bar
CN204151743U (en) A kind of hydraulic engineering flashing member
CN205189122U (en) Steel structure component of lightly constructed and simply equipped building
CN206706671U (en) A kind of waterproof Fence structure of hydraulic engineering

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151021