CN204700348U - A kind of be equipped with electric hammer exempt from climb drilling equipment - Google Patents

A kind of be equipped with electric hammer exempt from climb drilling equipment Download PDF

Info

Publication number
CN204700348U
CN204700348U CN201520392979.1U CN201520392979U CN204700348U CN 204700348 U CN204700348 U CN 204700348U CN 201520392979 U CN201520392979 U CN 201520392979U CN 204700348 U CN204700348 U CN 204700348U
Authority
CN
China
Prior art keywords
electric hammer
column
climb
floor beam
drilling equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520392979.1U
Other languages
Chinese (zh)
Inventor
夏华
张冲
冮润泽
吴善农
杜琳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Third Bureau Intelligent Technology Co Ltd
Original Assignee
China Construction Third Bureau Intelligent Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Third Bureau Intelligent Technology Co Ltd filed Critical China Construction Third Bureau Intelligent Technology Co Ltd
Priority to CN201520392979.1U priority Critical patent/CN204700348U/en
Application granted granted Critical
Publication of CN204700348U publication Critical patent/CN204700348U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Percussive Tools And Related Accessories (AREA)

Abstract

The utility model discloses a kind of be equipped with electric hammer exempt from climb drilling equipment, relate to construction implement field.This device comprises a support, and support is provided with end floor beam and lower end floor beam, and upper end floor beam is provided with pilot hole, and lower end floor beam is provided with lower pilot hole; One column, column is through described upper pilot hole and lower pilot hole, and column lower end is provided with tooth bar; Also comprise an electric hammer, electric hammer is fixed on column upper end; One gear, gear is fixed on support, and wheel and rack is meshed, and drives described column to move up and down during pinion rotation.Adopt the utility model be equipped with electric hammer exempt from climb drilling equipment, can increase work efficiency, avoid the risk of high-rise working, electric hammer can be operated in narrow space, be convenient to during construction observe operating point.

Description

A kind of be equipped with electric hammer exempt from climb drilling equipment
Technical field
The utility model relates to construction implement field, be specifically related to a kind of be equipped with electric hammer exempt from climb drilling equipment.
Background technology
In Commercial Complex building, the floor height of every layer is very high, and in work progress, light current crane span structure and pipelining need to install screw mandrel on floor, and screw mandrel installation is comparatively large, and 1.8 meter amperes as about every in crane span structure fill 2 rhizoid bars, and about every 1.5 meter amperes of conduit fill a rhizoid bar.Due to the reason of floor height, need to use movable Scaffold platform in the process of screw mandrel installation, and will movable Scaffold every about 2 meters, the work such as the upper and lower scaffold of workmen, safety band consume a large amount of working times, cause operating efficiency not high, and high-rise working also bring risk to workmen.
According to previous experiences, light current specialty is generally all marched into the arena after the specialties such as electromechanics, fire-fighting, and even after dynamo-electric, fire-fighting trunk pipeline construction complete, light current specialty is just marched into the arena sometimes.When the construction operation space leaving light current specialty in furred ceiling after electromechanical speciality trunk crane span structure, airduct, water pipe have been constructed for is very little, this brings very large difficulty to light current construction again.
In addition, scaffold carries out operating personnel's distance operating point when screw mandrel is installed and only has the distance of about 0.3 ~ 0.5 meter, produce a large amount of dust during punching and be unfavorable for that operating personnel observe operating point, and the dust produced enters in operating personnel's body and can cause harmful effect to human body.
Utility model content
For the defect existed in prior art, the purpose of this utility model is to provide a kind of increases work efficiency, improve working environment and can carry out operating in narrow space be equipped with electric hammer exempt from climb drilling equipment.
For reaching above object, the technical scheme that the utility model is taked is: a kind of be equipped with electric hammer exempt from climb drilling equipment, it comprises,
One support, described support is provided with end floor beam and lower end floor beam, and described upper end floor beam is provided with pilot hole, and described lower end floor beam is provided with lower pilot hole;
One column, described column is through described upper pilot hole and lower pilot hole, and described column lower end is provided with tooth bar; It is characterized in that: also comprise,
One electric hammer, described electric hammer is fixed on described column upper end;
One gear, described gear is fixed on support, and described gear is meshed with described tooth bar, and drives described column to move up and down during described pinion rotation.
On the basis of technique scheme, described column end face is fixed with crossbeam, and the handle of described electric hammer is fixed on crossbeam by multiple clip.
On the basis of technique scheme, described tooth bar is between upper end floor beam and lower end floor beam.
On the basis of technique scheme, described rack welding is in described column side.
On the basis of technique scheme, described gear is provided with rocking handle.
On the basis of technique scheme, the switch of described electric hammer is provided with stay cord.
On the basis of technique scheme, described support is provided with at least three feets, and described feet is provided with wheel.
Compared with prior art, the utility model has the advantage of:
Aloft during operation, do not need upper and lower scaffold and safety band repeatedly, improve operating efficiency; Operating personnel stand on the ground and can construct, thus can operate electric hammer in narrow space, it also avoid the risk of high-rise working simultaneously; In addition during construction, people is far from operating point, avoids and adds the infringement that man-hour, dust brought, be also convenient to observe operating point.
Accompanying drawing explanation
Fig. 1 is the front view exempting to climb drilling equipment that electric hammer is housed in the utility model embodiment.
In figure: 1-support, the upper end floor beam of 2-, end floor beam under 3-, the upper pilot hole of 4-, pilot hole under 5-, 6-column, 7-tooth bar, 8-electric hammer, 9-gear, 11-crossbeam, 12-handle, 13-clip, 15-rocking handle, 16-switch, 17-feet, 18-wheel.
Detailed description of the invention
Below in conjunction with accompanying drawing, embodiment of the present utility model is described in further detail.
Fig. 1 shows the structure of exempting to climb drilling equipment that the utility model is equipped with electric hammer.As shown in Figure 1, this device comprises the wheel 18 on support 1, column 6, electric hammer 8, tooth bar 7, gear 9 and support 1 feet 17.Wherein be welded with crossbeam 11 at the end face of column 6, the drill bit of electric hammer 8 is positioned on crossbeam 11 straight up, and the handle 12 of electric hammer 8 is fixed by clip 13 and crossbeam 11.Support 1 is provided with end floor beam 2 and lower end floor beam 3, upper end floor beam 2 is provided with pilot hole 4, lower end floor beam 3 is provided with lower pilot hole 5, column 6 is through upper pilot hole 4 and lower pilot hole 5, and the side of the column 6 between upper end floor beam 2 and lower end floor beam 3 is provided with tooth bar 7, and tooth bar 7 is welded on column 6 side, gear 9 is meshed with tooth bar 7, gear 9 is fixed on support 1, drives described column 6 to move up and down, gear 9 is provided with rocking handle 15 when gear 9 rotates.Be provided with stay cord at the switch 16 of electric hammer 3, support is provided with four feets 17, and each feet 17 is provided with a wheel 18.
Utilize originally be equipped with electric hammer exempt from climbing drilling equipment punching time, support 1 is moved to place to be processed, shake rocking handle 15, gear 9 rotating band carry-over bar 7 moves, thus pillar 6 is moved up and down, after the drill bit of electric hammer 8 is moved to punching place, pull stay cord, opening switch 16, electric hammer 8 is started working, during work, upper pilot hole 4 and lower pilot hole 5 play the effect of vertical columns 6, prevent the impact of generation when punching and rock.
When not using this instrument, floor is installed place's screw mandrel needs 2 workmens to complete for about 15 minutes.Groundwork comprises; The carrying of the instrument such as carrying, electric hammer of movable Scaffold platform, climb up and climb down scaffold operating platform, safety band etc.As the region that equipment in furred ceiling is comparatively concentrated, the operating time may be longer.
One place's leading screw is installed after using this equipment and need be about 7 ~ 8 minutes with the time, operating efficiency can be doubled like this.Operating personnel do not need to carry out work high above the ground more simultaneously, and the probability that high-altitude accident occurs also greatly reduces.
The utility model is not only confined to above-mentioned preferred forms; anyone can draw other various forms of products under enlightenment of the present utility model; no matter but any change is done in its shape or structure; every have identical with the utility model or akin technical scheme, all within its protection domain.

Claims (7)

1. what electric hammer was housed exempts from a climbing drilling equipment, and it comprises,
One support (1), described support (1) is provided with end floor beam (2) and lower end floor beam (3), described upper end floor beam (2) is provided with pilot hole (4), and described lower end floor beam (3) is provided with lower pilot hole (5);
One column (6), described column (6) is through described upper pilot hole (4) and lower pilot hole (5), and described column (6) lower end is provided with tooth bar (7); It is characterized in that: also comprise,
One electric hammer (8), described electric hammer (8) is fixed on described column (6) upper end;
One gear (9), described gear (9) is fixed on support (1), described gear (9) is meshed with described tooth bar (7), and drives described column (6) to move up and down when described gear (9) rotates.
2. as claimed in claim 1 a kind of be equipped with electric hammer exempt from climb drilling equipment, it is characterized in that: described column (6) end face is fixed with crossbeam (11), the handle (12) of described electric hammer (8) is fixed on crossbeam (11) by multiple clip (13).
3. as claimed in claim 1 a kind of be equipped with electric hammer exempt from climb drilling equipment, it is characterized in that: described tooth bar (7) is positioned between end floor beam (2) and lower end floor beam (3).
4. a kind of as described in claim 1 or 3 be equipped with electric hammer exempt from climb drilling equipment, it is characterized in that: described tooth bar (7) is welded on described column (6) side.
5. as claimed in claim 1 a kind of be equipped with electric hammer exempt from climb drilling equipment, it is characterized in that: described gear (9) is provided with rocking handle (15).
6. as claimed in claim 1 a kind of be equipped with electric hammer exempt from climb drilling equipment, it is characterized in that: the switch (16) of described electric hammer (8) is provided with stay cord.
7. as claimed in claim 1 a kind of be equipped with electric hammer exempt from climb drilling equipment, it is characterized in that: described support is provided with at least three feets (17), described feet (17) is provided with wheel (18).
CN201520392979.1U 2015-06-09 2015-06-09 A kind of be equipped with electric hammer exempt from climb drilling equipment Active CN204700348U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520392979.1U CN204700348U (en) 2015-06-09 2015-06-09 A kind of be equipped with electric hammer exempt from climb drilling equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520392979.1U CN204700348U (en) 2015-06-09 2015-06-09 A kind of be equipped with electric hammer exempt from climb drilling equipment

Publications (1)

Publication Number Publication Date
CN204700348U true CN204700348U (en) 2015-10-14

Family

ID=54279984

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520392979.1U Active CN204700348U (en) 2015-06-09 2015-06-09 A kind of be equipped with electric hammer exempt from climb drilling equipment

Country Status (1)

Country Link
CN (1) CN204700348U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106112935A (en) * 2016-07-21 2016-11-16 力帆实业(集团)股份有限公司 A kind of power drill workbench
CN107246239A (en) * 2017-05-15 2017-10-13 合肥市规划设计研究院 A kind of decorative engineering eminence drilling equipment

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106112935A (en) * 2016-07-21 2016-11-16 力帆实业(集团)股份有限公司 A kind of power drill workbench
CN107246239A (en) * 2017-05-15 2017-10-13 合肥市规划设计研究院 A kind of decorative engineering eminence drilling equipment

Similar Documents

Publication Publication Date Title
CN203710562U (en) High building escape device
CN204700348U (en) A kind of be equipped with electric hammer exempt from climb drilling equipment
CN204018794U (en) The indoor fixing construction system of a kind of ceiling
CN204166791U (en) Device is experienced in safety helmet striking
CN104100076A (en) Device for installing hanging bars of indoor suspended ceiling
CN204059910U (en) A kind of liftable high-altitude outdoor working device
CN102969674A (en) Special insulating tool for electrified fastening pin type bottle nut
CN202507205U (en) Novel spanner capable of being applied to high-risk and high-level operation
CN104724644A (en) Mechanical climbing device for electric tower or pole
CN204225458U (en) A kind of novel household building crane
CN108277972A (en) A kind of safety-type hanging basket of construction
CN103701070A (en) Ground guiding wire traveling crane
CN204216485U (en) A kind of transmission line show line device
CN202622700U (en) Hanger rod installation tool
CN204262415U (en) One is used for high-altitude jewel hole can ranging localization spiral electric hammer Electric drill support instrument
CN102974056B (en) Special fire-fighting rescue device
CN205265145U (en) Slide -wire driving safeties
CN204430347U (en) One is used for high-altitude jewel hole can ranging localization lift electric hammer Electric drill support instrument
CN204522061U (en) Serpentine security protection deliverance apparatus
CN204402066U (en) Hand push protective frame
CN201581793U (en) Removable metal hand frame for switch cabinet
CN204782703U (en) Exempt from to hold up safe insulating ladder
CN203987852U (en) A kind of ship anti-collision protection structure that hangs
CN204418634U (en) A kind of safety device of scaffold
CN204045895U (en) A kind of syndeton of concrete bar ground wire

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant