CN204677906U - Integral riser - Google Patents

Integral riser Download PDF

Info

Publication number
CN204677906U
CN204677906U CN201520230327.8U CN201520230327U CN204677906U CN 204677906 U CN204677906 U CN 204677906U CN 201520230327 U CN201520230327 U CN 201520230327U CN 204677906 U CN204677906 U CN 204677906U
Authority
CN
China
Prior art keywords
pipeline
prefabricated pipe
pipe group
prefabricated
integral riser
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520230327.8U
Other languages
Chinese (zh)
Inventor
乔培华
汤毅
陈晓文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Installation Engineering Group Co Ltd
Original Assignee
Shanghai Installation Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Installation Engineering Group Co Ltd filed Critical Shanghai Installation Engineering Group Co Ltd
Priority to CN201520230327.8U priority Critical patent/CN204677906U/en
Application granted granted Critical
Publication of CN204677906U publication Critical patent/CN204677906U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

For in prior art, pipe well internal riser welding difficulty, installation efficiency, the problem that precision is low, the utility model discloses a kind of integral riser, this integral riser comprises at least two sections of prefabricated pipe groups, every section of prefabricated pipe group comprises support, some pipelines, and some bracket fixing plates, described some pipeline enclosures are every being fixedly installed on described support, some bracket fixing plate intervals are fixedly installed on support, and some pipelines are separated into some unit, the detachable connection of corresponding pipeline of contiguous prefabricated pipe group, every section of prefabricated pipe group can be fixed in pipe well by some bracket fixing plates.Integral riser is divided into some prefabricated pipe groups, the batch production of prefabricated pipe group is prefabricated compares traditional single standpipe field fabrication and mounting process, reduce on-the-spot welding, save installation period, reduce installation difficulty, improve installation efficiency and precision, and the cross influence of other construction specialties can be avoided, meet the requirement of green construction.

Description

Integral riser
Technical field
The utility model relates to a kind of integral riser, belongs to dynamo-electric mounting technique field.
Background technique
Along with the development of china's overall national strength and building technology, increasing skyscraper and large-scale synthesis commercial affairs body is had to be in planning and designing and construction period in each city, in these buildings, generally all pipe well can be provided with, for installing the pipeline of different materials, quantity and diameter to realize the functions such as plumbing, fire-fighting spraying or air-conditioning cold and heat supply.
Traditional method of construction carries out successively in-site installation with regard to the single or many pipelines in pipe well, and scene also needs to carry out a large amount of welding job.Construction progress like this is slow, may cause the delay of duration, and often between pipeline Existential Space not enough and cause intermediate conduit to be difficult to welded and installed; During Pipe installing, construct while often there is other electromechanics (as airduct, crane span structure, wire casing, equipment etc.), civil engineering and decoration specialty in scene, therefore cross influence is large.There is the fine finishing (as bending, mantle fiber or perforate etc.) of pipeline in section of tubing erecting bed simultaneously, be subject to processing the restriction of equipment, material and technology, often make the quality of the pipeline of field fabrication undesirable, and considerably increase the consumption of the auxiliary material accessory of pipeline, the various disputes that disturb residents of job site may be increased simultaneously, do not meet the construction trend of green building and green construction.
Model utility content
The purpose of this utility model is to provide a kind of integral riser, integral riser is divided into some prefabricated pipe groups, the batch production of prefabricated pipe group is prefabricated compares traditional single pipe field fabrication and mounting process, reduce on-the-spot welding, greatly saved installation period, reduced installation difficulty, improve installation efficiency and installation precision, and the cross influence of other construction specialties can be avoided, save the overall duration of engineering simultaneously, meet the requirement of green construction.
For solving the problems of the technologies described above, the utility model provides following technological scheme:
A kind of integral riser, comprise at least two sections of prefabricated pipe groups, every section of prefabricated pipe group comprises support, some pipelines and some bracket fixing plates, described some pipeline enclosures are every being fixedly installed on described support, described some bracket fixing plate intervals are fixedly installed on described support, and described some pipelines being separated into some unit, the detachable connection of corresponding pipeline of contiguous prefabricated pipe group, every section of prefabricated pipe group can be fixed in pipe well by described some bracket fixing plates.
Preferably, in above-mentioned integral riser, the corresponding pipeline of contiguous prefabricated pipe group is directly docked or is connected by link.
Preferably, in above-mentioned integral riser, the corresponding pipeline of contiguous prefabricated pipe group adopts spigot and socket type, clamp-press type, hot melting way, flange or groove clamping hoop assembly to connect.
Preferably, in above-mentioned integral riser, described some pipelines are fixedly installed on described support by anchor ear interval, arrange chock or Rubber shockproof pad between described anchor ear and corresponding pipeline.。
Preferably, in above-mentioned integral riser, on described pipeline, the position of through-flooring is provided with the Fire-proof steel plate sleeve pipe that thickness is not less than 1.6mm.
Preferably, in above-mentioned integral riser, every section of prefabricated pipe group at least comprises upper and lower two shared supports, when duct length is greater than 4.5 meters, need arrange many shared supports by the spacing of 1.5m.
Preferably, in above-mentioned integral riser, every section of prefabricated pipe group comprises 2-8 root pipeline, and the height of described every root pipeline is 3.5-8m, and the weight of every section of prefabricated pipe group is no more than 3t, and single pipe weight is no more than 0.75t, and the caliber of single pipe is not more than 500mm.
Preferably, in above-mentioned integral riser, the material of described pipeline is selected from the one in carbon steel, stainless steel, red copper, brass, aluminum alloy and plastics.
Preferably, in above-mentioned integral riser, described bracket fixing plate is bolted on pipe well wall, or full weld is on the pre-embedded steel slab of pipe well wall.
Preferably, in above-mentioned integral riser, the top of described pipeline is provided with expansion joint.
From above disclosed technological scheme, compared with prior art, the beneficial effects of the utility model are as follows:
(1) integral riser described in the utility model is owing to adopting the form of individual layer or the assembling of multiple floor prefabricated pipe group entirety, therefore segmentation batch production can be realized prefabricated, and prefabricated traditional single standpipe field fabrication and the mounting process compared of the batch production of prefabricated pipe group, greatly save installation period.
(2) the utility model is owing to building the installing engineering just starting prefabricated pipe group in civil engineering structure launch, compares above-mentioned conventional mounting technique, can avoid the cross influence of other construction specialties, save the overall duration of engineering simultaneously.
(3) the overall batch production of the utility model prefabricated pipe group is prefabricated owing to not limiting by material, environment and technology, the making quality of pipeline is all increased, and making material can be saved, avoid the various wasting of resources of job site and the generation of rubbish, in addition, Placement between standpipe group is non-solder mode, such as groove (clip), spigot and socket type or Flange joint, decrease on-the-spot welding job amount, both avoid the narrow and small difficult problem that cannot weld of pipe well, be conducive to green construction again.
(4) traditional pipeline is easy to the impact being subject to adjacent channel installation dimension deviation when making at the scene and assemble, pipeline is caused to install, integral riser described in the utility model makes precision owing to can improve during prefabrication, and pipeline making is unified specification, therefore can avoid the generation of the problems referred to above.
Accompanying drawing explanation
Fig. 1 is the layout schematic diagram of the integral riser of the utility model one embodiment;
Fig. 2 is the lifting schematic diagram of the integral riser of the utility model one embodiment.
In figure: 1-life water pipe, 2-fire-prevention pipe, 3-waste pipe, 4-bracket fixing plate, 5-support, 6-groove link, 7-flange, 8-fixing bolt, 9-pipe well, 10-pipe well guardrail, 11-Fire-proof steel plate sleeve pipe, 12-hanging component, 13-groove, 14-anchor ear, 15-floor, 16-spigot-and-socket joint.
Embodiment
Below in conjunction with the drawings and specific embodiments, the integral riser that the utility model proposes is described in further detail.According to the following describes and claims, advantage of the present utility model and feature will be clearer.It should be noted that, accompanying drawing all adopts the form that simplifies very much and all uses non-ratio accurately, only in order to object that is convenient, aid illustration the utility model embodiment lucidly.
Composition graphs 1 to Fig. 2, present embodiment discloses a kind of integral riser, comprise at least two sections of prefabricated pipe groups and standpipe group, every section of prefabricated pipe group comprises support 5, some pipelines and pipeline, and some bracket fixing plates 4, described some pipeline enclosures are every being fixedly installed on described support 5, pipeline described in the present embodiment comprises life water pipe 1, fire-prevention pipe 2 and waste pipe 3, described some bracket fixing plates 4 interval is fixedly installed on described support 5, and described some pipelines are separated into some unit, the detachable connection of corresponding pipeline of contiguous prefabricated pipe group, the corresponding pipeline of all contiguous prefabricated pipe groups connects the rear each standpipe formed in integral riser, the height of standpipe can be a floor or multiple floor, height determines according to on-the-spot and traffic condition.Every section of prefabricated pipe group can be fixed in pipe well 9 by described some bracket fixing plates 4.The utility model integral riser, owing to adopting multistage prefabricated pipe to assemble the form of joining, therefore can realize segmentation batch production prefabricated, and prefabricated traditional single pipe field fabrication and the mounting process compared of the batch production of prefabricated pipe group, greatly save installation period.On the other hand, the overall batch production of prefabricated pipe group is prefabricated owing to not limiting by material, environment and technology, and the making quality of pipeline is all increased, and can save making material, avoid the various wasting of resources of job site and the generation of rubbish, be conducive to green construction.Again on the one hand, traditional pipeline is easy to the impact being subject to adjacent channel installation dimension deviation when making at the scene and assemble, pipeline is caused to install, integral riser described in the utility model makes precision owing to can improve during prefabrication, and pipeline making is unified specification, therefore can avoid the generation of the problems referred to above.In addition, the utility model, owing to just starting the installing engineering of prefabricated pipe group in civil engineering structure launch, therefore, compares above-mentioned conventional mounting technique, can avoid the cross influence of other construction specialties, save the overall duration of engineering simultaneously.In addition, the Placement of the corresponding pipeline of contiguous prefabricated pipe group is detachable Placement, decreases on-the-spot welding job amount, has both avoided the narrow and small difficult problem that cannot weld of pipe well, and be conducive to green construction again.
Because pipeline is difficult to realize welding by body of wall (i.e. pipe well 9 wall) position, therefore the butt end of the corresponding pipeline of contiguous prefabricated pipe group adopts the Placement of non-solder.The corresponding pipeline of contiguous prefabricated pipe group can directly be docked or be connected by link.In the present embodiment, waste pipe 3 adopts spigot-and-socket joint 16 to connect, for waste pipe 3 and spigot-and-socket joint 16 can split manufacture also can be one-body molded, in the present embodiment, waste pipe 3 is one-body molded with spigot-and-socket joint 16, be called that socket drain pipe life water pipe 1 adopts flange 7 as link, certain flange 7 need fixing bolt 8 with the use of; Fire-prevention pipe 2 adopts groove clamping hoop assembly to connect, that is, in the butt end of the corresponding pipeline of contiguous prefabricated pipe group, one is provided with groove link 6 as link, another is provided with groove 13 as link, and described groove link 6 is connected together with described groove 13.In the present embodiment, the life water pipe 1 that caliber is less adopts flange 7 to connect; The fire-prevention pipe 2 that caliber is larger adopts groove link 6 and described groove 13 to be connected together.Certainly, the Connecting format of pipeline is not only confined to groove (clip) or Flange joint, and the fast Placement such as spigot and socket type, clamp-press type and hot melt, as long as non-solder mode and have required intensity and can be tightly connected.
Preferably, described some pipelines are fixedly installed on described support 5 by anchor ear 14 interval.Described anchor ear 14 is the components embracing or wale another material with a kind of material, belongs to fastening piece.
Preferably, on described pipeline, the position of through-flooring 15 is provided with the Fire-proof steel plate sleeve pipe 11 that thickness is not less than 1.6mm, and described Fire-proof steel plate sleeve pipe 11 is fixed on pipeline by the form of welding in advance.In order to realize vibration isolation when pipeline uses, preferably, chock or Rubber shockproof pad (not shown) are set between described anchor ear 14 and corresponding pipeline.
In order to the specification of specification pipeline, size, material and weight better solve problem in background technique to make the utility model, improve pipeline to make and installation quality, every section of prefabricated pipe group comprises 2-8 root pipeline, the height of described every root pipeline is 3.5-8m, the weight of every section of prefabricated pipe group is no more than 3t, single pipe weight is no more than 0.75t, and the caliber of single pipe is not more than 500mm.
Preferably, according to the above-mentioned specification determined, in conjunction with construction experience, the material of described pipeline is selected from the one in carbon steel, stainless steel, red copper, brass, aluminum alloy and plastics, but not can be lead alloy class material.
In order to make prefabricated pipe group more firmly be fixed on body of wall, preferably, in above-mentioned integral riser, every section of prefabricated pipe group at least comprises upper and lower two shared supports, when duct length is greater than 4.5 meters, need arrange many shared supports by the spacing of 1.5m.That is the maximum perpendicular spacing of shared support 5 should more than 1.5m.Support 5 material is channel-section steel.
Preferably, in above-mentioned integral riser, if only have 3 pipelines on shared support 5,2 pieces of bracket fixing plates 4 are just much of that.If there are 6 pipelines, except head and the tail respectively arrange 1 piece of bracket fixing plate 4, between 3 adjacent pipelines, 1 piece of bracket fixing plate 4 to be set again, altogether want 3 pieces of bracket fixing plates 4.If but the king-sized words of pipe diameter, just need to increase bracket fixing plate 4, just add bracket fixing plate 4 between two pipelines as shown in Figure 1, shared 4 pieces of bracket fixing plates 4.Described bracket fixing plate 4 is bolted on pipe well 9 wall, or full weld is on the pre-embedded steel slab (not shown) of pipe well 9 wall.As form with bolts, every block bracket fixing plate 4 should have 4 M12 EXPANSION ANCHOR BOLTS.
Preferably, in above-mentioned integral riser, the top of described pipeline is provided with expansion joint (not shown).Expansion joint should be arranged on the top of pipeline, after the integral installation of prefabricated pipe group, just can unload hanging component 12, avoids expansion joint can't stand prefabricated pipe group gravity because holding and damaged by pressure.
The installation method of described integral riser, comprises the steps:
Step one: after factory receives order, according to the actual size of described prefabricated pipe group, pipeline in described prefabricated pipe group and support 5 are processed, anchor ear 14 and bracket fixing plate 4 are welded to connect respectively on described support 5, described pipeline is fixed on support 5 by anchor ear 14 respectively, link is set in the butt end of pipeline, then carries out the heat insulation work of pipeline, thus complete the prefabricated of each prefabricated pipe group in factory.Wherein, shared support 5 and bracket fixing plate 4 should according to number of tubes and calibers, bolt hole is rushed in corresponding position by actual conditions, anchor ear 14 and bracket fixing plate 4 are through being welded to connect on channel-section steel or angle steel support 5, then the heat insulation work of pipeline is carried out, as requirement of engineering, can carry out leak test detection before prefabricated pipe group is dispatched from the factory, finally qualified prefabricated pipe group enters through packaging stores district.
Step 2: after each prefabricated pipe group is transported to construction site, comprehensively check, after whether confirmation prefabricated pipe group specification, thermal insulation property meet the demands, then confirms that weather conditions, lifting place, suspension centre hoist cable arrange and whether meet the demands;
Step 3: adopt centre-of gravity shift method or mobile platform haul method by the lifting of prefabricated pipe group in floor, as being installed in high-rise Core Walls Structure pipe well 9, winch pulley system is then adopted to hang in pipe well 9, as being installed on building external region, then utilize tower crane pipe group to be winched to the laggard luggage of pipe well 9 to join, pipeline is when lifting, should tie up firmly, to splice and support 5 can unclamp lifting flexible steel wire after being fixed on pipe well 9 until upper and lower two pipeline butts, in hoisting process each floor carry out hole face limit protection work, the pipe well guardrail 10 being not less than 1.2m should be set up, until prefabricated pipe group is in place.
After lifting, the pipeline of expansion joint is being housed, should according to the overall length of standpipe, free adjusting each prefabricated pipe group length and top expansion joint designed in pipeline, after support 5 installs and is namely fixedly connected with pipe well 9 wall, just can unload hanging component 12, when so can avoid installing, expansion joint is damaged by pressure because bearing excessive pipeline gravity.
After described prefabricated pipe assembling is joined, the Fire-proof steel plate sleeve pipe 11 that thickness is not less than 1.6mm should be had at through-flooring 15 place, its sleeve pipe is fixed on pipeline by the form of welding in advance, and the complete civil engineering unit that coordinates again to be installed carries out closing of pipe well 9 and burying underground of sleeve pipe.
Step 4: after each prefabricated pipe group has connected in pipe well 9, carries out the hydrostatic test to pipe-line system i.e. each standpipe formed respectively according to standard-required, encapsulates, and carry out at pipeline the work of going along with sb. to guard him after pass the test to opening.
Preferably, in step 3, in hoisting process, in order to avoid accident occurs, the rupture pull force for the lifting flexible steel wire installing prefabricated pipe group is not less than 30t, and the lifting speed of prefabricated pipe group in pipe well 9 is not more than 0.5m/s.Preferably, rock and cause pipe well 9 and pipe group to be destroyed, must have the traction of hawser in order to avoid pipe group during lifting may exist, during lifting, the shape of pipe well 9 and size should be fixed simultaneously, can not carry out lifting operation in the pipe well 9 being in dislocation.
Integral riser described in the present embodiment is prefabricated owing to realizing batch production, according to field statistics data feedback, compare above-mentioned traditional standpipe installation method, the installation period of about 80% can be saved, reduce the spillage of material of 15%, increase by the recyclable material of 27%, dimensional accuracy can improve 58%, and the deviation of simultaneously installing can reduce by 35%, onsite application HYDROELECTRIC ENERGY saves about 72%, install fault rate and reduce by 74%, the quantity of refuse of erecting bed can reduce 83%, and erecting bed noise can reduce by 64%.
Integral riser described in the present embodiment, is arranged as adopted fixed plate described in the utility model and bolt is connected in the pipe well 9 of high 400m, and through calculating the collapsing force resisting 9 grades of earthquake intensity earthquakes, calculation method is as follows:
With reference to GB50011-2010 " Code for seismic design of buildings " and YD5059-1998 " communication apparatus installation earthquake resistant design code ", calculate integral riser described in the utility model (8 0.75t pipelines) under least favorable condition, in 9 grades of earthquake intensity earthquakes, threaten the maximum horizontal pulling force suffered by maximum the top pipeline and pipeline to be 9.5 × 104N by earthquake, maximum shear stress is 6.2 × 104N.
With reference to JB-ZQ 4763-2006 " EXPANSION ANCHOR BOLTS specification and performance " table 48, permission pulling force and the permission shearing of M10# EXPANSION ANCHOR BOLTS are respectively 7 × 103N and 5.2 × 103N; With reference to GB/T 3098.1-2000 " fastening piece mechanical property bolt, screw and stud " table 6 ~ table 9, the coarse thread bolt of 3.6 specifications that what M10# EXPANSION ANCHOR BOLTS drag was minimum is, its level is 2.1 × 104N to lowest pull load, ensures that load is 1.1 × 104N.
Design according to the utility model, above-mentioned prefabricated pipe group should the rarest 4 bracket fixing plates 4, each bracket fixing plate 4 bolts calculate, adopting M10# bolt to amount to allows pulling force to be 1.1 × 105N, and permission shearing is 8.3 × 104N, and total pulling force load is 3.4 × 105N, ensure that load is 1.7 × 105N, therefore can resist the earthquake of 9 grades of earthquake intensitys, bolt specification for reduce risk further, therefore is decided to be M12# EXPANSION ANCHOR BOLTS by the utility model.
In sum, the beneficial effects of the utility model are as follows:
(1) integral riser described in the utility model is owing to adopting the form of individual layer or the assembling of multiple floor prefabricated pipe group entirety, therefore segmentation batch production can be realized prefabricated, and prefabricated traditional single standpipe field fabrication and the mounting process compared of the batch production of prefabricated pipe group, greatly save installation period.
(2) the utility model is owing to building the installing engineering just starting prefabricated pipe group in civil engineering structure launch, compares above-mentioned conventional mounting technique, can avoid the cross influence of other construction specialties, save the overall duration of engineering simultaneously.
(3) the overall batch production of the utility model prefabricated pipe group is prefabricated owing to not limiting by material, environment and technology, the making quality of pipeline is all increased, and making material can be saved, avoid the various wasting of resources of job site and the generation of rubbish, in addition, Placement between standpipe group is non-solder mode, such as groove (clip), spigot and socket type or Flange joint, decrease on-the-spot welding job amount, both avoid the narrow and small difficult problem that cannot weld of pipe well, be conducive to green construction again.
(4) traditional pipeline is easy to the impact being subject to adjacent channel installation dimension deviation when making at the scene and assemble, pipeline is caused to install, integral riser described in the utility model makes precision owing to can improve during prefabrication, and pipeline making is unified specification, therefore can avoid the generation of the problems referred to above.
Foregoing description is only the description to the utility model preferred embodiment; any restriction not to the utility model scope; any change that the those of ordinary skill in the utility model field does according to above-mentioned disclosure, modification, all belong to the protection domain of claims.

Claims (10)

1. an integral riser, it is characterized in that, comprise at least two sections of prefabricated pipe groups, every section of prefabricated pipe group comprises support, some pipelines and some bracket fixing plates, described some pipeline enclosures are every being fixedly installed on described support, and described some bracket fixing plate intervals are fixedly installed on described support, and described some pipelines are separated into some unit, the detachable connection of corresponding pipeline of contiguous prefabricated pipe group, every section of prefabricated pipe group can be fixed in pipe well by described some bracket fixing plates.
2. integral riser as claimed in claim 1, it is characterized in that, the corresponding pipeline of contiguous prefabricated pipe group is directly docked or is connected by link.
3. integral riser as claimed in claim 1, is characterized in that, the corresponding pipeline of contiguous prefabricated pipe group adopts spigot and socket type, clamp-press type, hot melting way, flange or groove clamping hoop assembly to connect.
4. integral riser as claimed in claim 1, it is characterized in that, described some pipelines are fixedly installed on described support by anchor ear interval, arrange chock or Rubber shockproof pad between described anchor ear and corresponding pipeline.
5. integral riser as claimed in claim 1, it is characterized in that, on described pipeline, the position of through-flooring is provided with the Fire-proof steel plate sleeve pipe that thickness is not less than 1.6mm.
6. integral riser as claimed in claim 1, it is characterized in that, every section of prefabricated pipe group at least comprises upper and lower two shared supports, when duct length is greater than 4.5 meters, need arrange many shared supports by the spacing of 1.5m.
7. integral riser as claimed in claim 1, it is characterized in that, every section of prefabricated pipe group comprises 2-8 root pipeline, the height of described every root pipeline is 3.5-8m, the weight of every section of prefabricated pipe group is no more than 3t, and single pipe weight is no more than 0.75t, and the caliber of single pipe is not more than 500mm.
8. integral riser as claimed in claim 1, it is characterized in that, the material of described pipeline is selected from the one in carbon steel, stainless steel, red copper, brass, aluminum alloy and plastics.
9. integral riser as claimed in claim 1, it is characterized in that, described bracket fixing plate is bolted on pipe well wall, or full weld is on the pre-embedded steel slab of pipe well wall.
10. integral riser as claimed in claim 1, it is characterized in that, the top of described pipeline is provided with expansion joint.
CN201520230327.8U 2015-04-16 2015-04-16 Integral riser Active CN204677906U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520230327.8U CN204677906U (en) 2015-04-16 2015-04-16 Integral riser

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520230327.8U CN204677906U (en) 2015-04-16 2015-04-16 Integral riser

Publications (1)

Publication Number Publication Date
CN204677906U true CN204677906U (en) 2015-09-30

Family

ID=54177598

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520230327.8U Active CN204677906U (en) 2015-04-16 2015-04-16 Integral riser

Country Status (1)

Country Link
CN (1) CN204677906U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104806822A (en) * 2015-04-16 2015-07-29 上海市安装工程集团有限公司 Combined type stand pipe and modularized installation method thereof
CN107355591A (en) * 2017-07-20 2017-11-17 中建局集团第二建筑有限公司 Jig and its application method for the installation of vertical shaft interior conduit

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104806822A (en) * 2015-04-16 2015-07-29 上海市安装工程集团有限公司 Combined type stand pipe and modularized installation method thereof
CN104806822B (en) * 2015-04-16 2017-03-01 上海市安装工程集团有限公司 The modularity installation method of integral riser
CN107355591A (en) * 2017-07-20 2017-11-17 中建局集团第二建筑有限公司 Jig and its application method for the installation of vertical shaft interior conduit

Similar Documents

Publication Publication Date Title
CN104806822A (en) Combined type stand pipe and modularized installation method thereof
CN204901084U (en) Prefabricated integration assembled sectional shelf -unit based on BIM
CN107662881A (en) Integral riser erecting device and its installation method in a kind of high stove pipe well
CN201475501U (en) Assembling type vertical pipe group support and installation structure with pipe structure
CN205639870U (en) A pipeline gallows is synthesized in heavy construction
CN204677906U (en) Integral riser
CN203820287U (en) Composite steel carrying pole for hoisting roof tiles of steel structure workshops
CN102767644A (en) Assembly type heavy pipeline hanger
CN108086523B (en) Light steel concrete block composite wall and construction method thereof
CN207566725U (en) Integral riser erecting device in a kind of high stove pipe well
CN202082489U (en) Pipe gallery horizontal pipeline mounting device
CN104480959A (en) General tower crane supporting base
CN102777703A (en) Assembly type light pipeline hanger
CN207196844U (en) A kind of integrated air-line system
CN207251110U (en) A kind of large span power cable crane span structure
CN115419205B (en) BIM technology-based building decoration suspended ceiling and installation method thereof
CN218449275U (en) Guide support for large-diameter pipeline in pipe gallery
CN214301845U (en) Support type integrated pipe trench with embedded pipeline
CN204875853U (en) Assembled underground piping lane
CN215596567U (en) Force transmission fixing device for large-diameter pipeline
CN212802104U (en) Novel assembled strength wall
CN211956084U (en) Camera and projecting lamp aggregate erection device
CN215371326U (en) Reusable support suitable for fire fighting combined with water and electricity
CN208272522U (en) Dismountable cable bearer
CN207196845U (en) A kind of integrated airduct module

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant