CN204677892U CN201520311576.XU CN201520311576U CN204677892U CN 204677892 U CN204677892 U CN 204677892U CN 201520311576 U CN201520311576 U CN 201520311576U CN 204677892 U CN204677892 U CN 204677892U
Authority
CN
China
Prior art keywords
pipeline
top layer
support body
cross member
floor cross
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520311576.XU
Other languages
Chinese (zh)
Inventor
步江峰
姜跃君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
EOSLIFT AUTOMATION TECHNOLOGY CORP.
Original Assignee
YIOUSI STORAGE EQUIPMENT Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YIOUSI STORAGE EQUIPMENT Co Ltd filed Critical YIOUSI STORAGE EQUIPMENT Co Ltd
Priority to CN201520311576.XU priority Critical patent/CN204677892U/en
Application granted granted Critical
Publication of CN204677892U publication Critical patent/CN204677892U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model is applicable to the technical field in Pipe installing field, disclose a kind of pipeline to shelve in advance, comprise support body and the pipeline comprising straight tube and bend pipe, the two ends of described pipeline are equipped with mounting flange, described pipeline is fixedly connected with support body by mounting flange, described support body comprises bottom support body, top layer support body and some supporting frames, and described top layer support body is fixedly connected with bottom support body by supporting frame.A kind of pipeline that the utility model provides is shelved in advance, rational in infrastructure, the position of Pipe installing can be determined before pipeline as installed, installation personnel is made only to need according to each mounting plate assembling pipeline on support body, enormously simplify the installation process of under ground piping, thus reduce cost of production, and, also adopt the structure of double-layer rack body, make the comparatively complicated pipeline of underground environment also can shelve installation in advance, meanwhile, shelve the situation of testing property when can also be used in pipe production in advance, to improve installation precision and the quality of product of pipeline.

Description

A kind of pipeline is shelved in advance
[technical field]
The utility model relates to Pipe installing field, and particularly a kind of pipeline is shelved in advance.
[background technique]
Because the angle of pipeline is ever-changing when pipeline makes, keep locating point to be very precisely very difficult after being allowed to condition at welding, the particularly complicated cast of multiple welding pipe joint, the pipeline workman that experience is very abundant deals with and also takes time and effort very much.Therefore, a kind of Pipe installing mode that can be simple and efficient is needed badly.
[model utility content]
The purpose of this utility model is to overcome above-mentioned the deficiencies in the prior art, provides a kind of pipeline to shelve in advance, and it is intended to solve the technical problem that pipeline of the prior art is difficult to locate when mounted.
For achieving the above object, the utility model proposes a kind of pipeline to shelve in advance, comprise support body and the pipeline comprising straight tube and bend pipe, the two ends of described pipeline are equipped with mounting flange, described pipeline is fixedly connected with support body by mounting flange, described support body comprises bottom support body, top layer support body and some supporting frames, and described top layer support body is fixedly connected with bottom support body by supporting frame;
Described bottom support body comprises two floor cross member be parallel to each other, some tie-beams, some to vertical beam and some bottom mounting plates, described tie-beam is located between two floor cross member, described tie-beam and floor cross member are mutually vertical, described vertical beam is all vertical with tie-beam with floor cross member, every a pair vertical beam is located at the end face of two floor cross member respectively, every a pair vertical beam is parallel to each other, the both sides of described bottom mounting plate are fixedly connected with the side of every a pair vertical beam respectively, described bottom mounting plate is also provided with bottom flange, described bottom flange and mounting flange cooperatively interact,
Described top layer support body comprises top layer crossbeam and some top layer mounting plates, described top layer crossbeam and floor cross member are parallel to each other and directly over a floor cross member located therein, described top layer mounting plate is fixed at the two ends of top layer crossbeam, described top layer mounting plate is provided with top layer flange, and described top layer flange also cooperatively interacts with mounting flange;
Described supporting frame comprises support beam and cant beam, and described top layer crossbeam is fixedly connected with floor cross member by support beam, and one end of described cant beam is fixedly connected with support beam, the other end is fixedly connected with the end face of another root crossbeam.
As preferably, described tie-beam is located at the position that every a pair vertical beam is connected with floor cross member.
As preferably, described tie-beam is also located at the position that cant beam is connected with floor cross member with support beam.
As preferably, described floor cross member, top layer crossbeam, vertical beam and tie-beam are I-steel, described support beam and cant beam are C-type steel, and described bottom mounting plate is fixedly connected with the edge of a wing of vertical beam, and the side of described top layer mounting plate is fixedly connected with top layer crossbeam.
As preferably, described top layer mounting plate in the vertical direction and support beam acute angle each other.
The beneficial effects of the utility model: compared with prior art, a kind of pipeline that the utility model provides is shelved in advance, rational in infrastructure, the position of Pipe installing can be determined before pipeline as installed, installation personnel is made only to need according to each mounting plate assembling pipeline on support body, enormously simplify the installation process of under ground piping, thus reduce cost of production, and, also adopt the structure of double-layer rack body, make the comparatively complicated pipeline of underground environment also can shelve installation in advance, simultaneously, shelve the situation of testing property when can also be used in pipe production in advance, to improve installation precision and the quality of product of pipeline.
Feature of the present utility model and advantage will be described in detail by reference to the accompanying drawings by embodiment.
[accompanying drawing explanation]
Fig. 1 is the scheme of installation of the utility model embodiment.
[embodiment]
For making the purpose of this utility model, technological scheme and advantage clearly understand, below by accompanying drawing and embodiment, the utility model is further elaborated.But should be appreciated that, specific embodiment described herein, only in order to explain the utility model, is not limited to scope of the present utility model.In addition, in the following description, the description to known features and technology is eliminated, to avoid unnecessarily obscuring concept of the present utility model.
Consult Fig. 1, the utility model embodiment provides a kind of pipeline to shelve in advance, comprise support body and the pipeline 1 comprising straight tube and bend pipe, the two ends of pipeline 1 are equipped with mounting flange, pipeline 1 is fixedly connected with support body by mounting flange, support body comprises bottom support body 2, top layer support body 3 and some supporting frames, and top layer support body 3 is fixedly connected with bottom support body 2 by supporting frame.
In the utility model embodiment, have employed double-layer rack body, to meet the pre-reload request of baroque pipeline 1, expand the Applicable scope of shelving.
Particularly, bottom support body 2 comprises two floor cross member be parallel to each other 21, some tie-beams 4, some to vertical beam 5 and some bottom mounting plates 22, tie-beam 4 is located between two floor cross member 21, tie-beam 4 is mutually vertical with floor cross member 21, vertical beam 5 is all vertical with tie-beam 4 with floor cross member 21, every a pair vertical beam 5 is located at the end face of two floor cross member 21 respectively, every a pair vertical beam 5 is parallel to each other, the both sides of bottom mounting plate 22 are fixedly connected with the side of every a pair vertical beam 5 respectively, bottom mounting plate 22 is also provided with bottom flange 23, bottom flange 23 and mounting flange cooperatively interact.
In this kind of structure; one piece of corresponding pipeline 1 of bottom mounting plate 22, therefore, user can lay according to the pipeline 1 of reality the quantity needing to increase bottom mounting plate 22; as long as bottom mounting plate 22 keeps vertical by vertical beam 5, namely in protection domain of the present utility model.
Particularly, top layer support body 3 comprises top layer crossbeam 31 and some top layer mounting plates 32, top layer crossbeam 31 and floor cross member 21 are parallel to each other and directly over a floor cross member 21 located therein, top layer mounting plate 32 is fixed at the two ends of top layer crossbeam 31, top layer mounting plate 32 is provided with top layer flange 33, and top layer flange 33 also cooperatively interacts with mounting flange.
Due to the utility model, embodiment only adopts double-layer rack body, therefore, for top layer mounting plate 32 without the need to setting up vertical beam 5 again to ensure the vertical state of top layer mounting plate 32, and, in the installation environment of reality, often the top of pipeline 1 can keep vertical, and its end then needs to offset several angle.
Particularly, supporting frame comprises support beam 61 and cant beam 62, top layer crossbeam 31 is fixedly connected with floor cross member 21 by support beam 61, one end of cant beam 62 is fixedly connected with support beam 61, the other end is fixedly connected with the end face of another root floor cross member 21, thus formation triangular support configurations, improve the steadiness of support body.
In the concrete installation process of the utility model embodiment, each root steel all can in-site installation, facilitates installation personnel to operate.
Further, tie-beam 4 is located at the position that every a pair vertical beam 5 is connected with floor cross member 21.
Wherein, tie-beam 4 is also located at the position that cant beam 62 is connected with floor cross member 21 with support beam 61.
Particularly, floor cross member 21, top layer crossbeam 31, vertical beam 5 and tie-beam 4 are I-steel, and support beam 61 and cant beam 62 are C-type steel, and bottom mounting plate 22 is fixedly connected with the edge of a wing of vertical beam 5, and the side of top layer mounting plate 32 is fixedly connected with top layer crossbeam 31.
Further, top layer mounting plate 32 in the vertical direction and support beam 61 acute angle each other.
The utility model embodiment can determine the position that pipeline 1 is installed before pipeline 1 as installed, installation personnel is made only to need according to each mounting plate assembling pipeline 1 on support body, enormously simplify the installation process of under ground piping 1, thus reduce cost of production, and, also adopt the structure of double-layer rack body, make the comparatively complicated pipeline 1 of underground environment also can shelve installation in advance, simultaneously, shelve the situation that can also be used in testing property when pipeline 1 is produced in advance, to improve installation precision and the quality of product of pipeline 1.
The foregoing is only preferred embodiment of the present utility model; not in order to limit the utility model; all do within spirit of the present utility model and principle any amendment, equivalent to replace or improvement etc., all should be included within protection domain of the present utility model.

Claims (5)

1. a pipeline is shelved in advance, comprise support body and the pipeline (1) comprising straight tube and bend pipe, the two ends of described pipeline (1) are equipped with mounting flange, described pipeline (1) is fixedly connected with support body by mounting flange, it is characterized in that: described support body comprises bottom support body (2), top layer support body (3) and some supporting frames, described top layer support body (3) is fixedly connected with bottom support body (2) by supporting frame;
Described bottom support body (2) comprises two floor cross member be parallel to each other (21), some tie-beams (4), some to vertical beam (5) and some bottom mounting plates (22), described tie-beam (4) is located between two floor cross member (21), described tie-beam (4) is mutually vertical with floor cross member (21), described vertical beam (5) is all vertical with tie-beam (4) with floor cross member (21), every a pair vertical beam (5) is located at the end face of two floor cross member (21) respectively, every a pair vertical beam (5) is parallel to each other, the both sides of described bottom mounting plate (22) are fixedly connected with the side of every a pair vertical beam (5) respectively, described bottom mounting plate (22) is also provided with bottom flange (23), described bottom flange (23) and mounting flange cooperatively interact,
Described top layer support body (3) comprises top layer crossbeam (31) and some top layer mounting plates (32), described top layer crossbeam (31) and floor cross member (21) are parallel to each other and directly over a floor cross member (21) located therein, described top layer mounting plate (32) is fixed at the two ends of top layer crossbeam (31), described top layer mounting plate (32) is provided with top layer flange (33), and described top layer flange (33) also cooperatively interacts with mounting flange;
Described supporting frame comprises support beam (61) and cant beam (62), described top layer crossbeam (31) is fixedly connected with floor cross member (21) by support beam (61), and one end of described cant beam (62) is fixedly connected with support beam (61), the other end is fixedly connected with the end face of another root floor cross member (21).
2. a kind of pipeline as claimed in claim 1 is shelved in advance, it is characterized in that: described tie-beam (4) is located at the position that every a pair vertical beam (5) is connected with floor cross member (21).
3. a kind of pipeline as claimed in claim 2 is shelved in advance, it is characterized in that: described tie-beam (4) is also located at the position that cant beam (62) is connected with floor cross member (21) with support beam (61).
4. a kind of pipeline as claimed in claim 1 is shelved in advance, it is characterized in that: described floor cross member (21), top layer crossbeam (31), vertical beam (5) and tie-beam (4) are I-steel, described support beam (61) and cant beam (62) are C-type steel, described bottom mounting plate (22) is fixedly connected with the edge of a wing of vertical beam (5), and the side of described top layer mounting plate (32) is fixedly connected with top layer crossbeam (31).
5. a kind of pipeline according to any one of Claims 1-4 is shelved in advance, it is characterized in that: described top layer mounting plate (32) in the vertical direction and support beam (61) acute angle each other.
CN201520311576.XU 2015-05-14 2015-05-14 A kind of pipeline is shelved in advance Active CN204677892U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520311576.XU CN204677892U (en) 2015-05-14 2015-05-14 A kind of pipeline is shelved in advance

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520311576.XU CN204677892U (en) 2015-05-14 2015-05-14 A kind of pipeline is shelved in advance

Publications (1)

Publication Number Publication Date
CN204677892U true CN204677892U (en) 2015-09-30

Family

ID=54177584

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520311576.XU Active CN204677892U (en) 2015-05-14 2015-05-14 A kind of pipeline is shelved in advance

Country Status (1)

Country Link
CN (1) CN204677892U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104832708A (en) * 2015-05-14 2015-08-12 意欧斯仓储设备股份有限公司 Pipeline pre-installing frame

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104832708A (en) * 2015-05-14 2015-08-12 意欧斯仓储设备股份有限公司 Pipeline pre-installing frame
CN104832708B (en) * 2015-05-14 2017-01-18 意欧斯智能科技股份有限公司 Pipeline pre-installing frame

Similar Documents

Publication Publication Date Title
CN202866226U (en) Through long groove stone dry-hang system
CN204212291U (en) The ruggedized construction of large span, superelevation light composite wallboard body of wall
CN204677892U (en) A kind of pipeline is shelved in advance
CN104832708A (en) Pipeline pre-installing frame
CN204486153U (en) A kind of glue laminating apparatus of capacitive touch screen
CN204760174U (en) Transformer base structure with adjustable
CN203626854U (en) Tunnel stand column mounting system
CN104075034B (en) A kind of Bidirectional slide pipe support bearing two-way normal load
CN203477608U (en) Fixing pipe clamp used for pipeline
CN203237404U (en) Passenger cabin main pipe positioning and installing device
CN202117170U (en) Support structure capable of sliding freely
CN205509396U (en) An I -steel gallows
CN201865229U (en) Suspended ceiling reverse support
CN204087039U (en) Abacus
CN203589461U (en) U upright bracket of switch cabinet
CN204271562U (en) A kind of simple and easy trailing arm
CN203853727U (en) High-speed rail support assembly structure
CN203334489U (en) Glass curtain wall with strip-shaped locating unit
CN203673116U (en) Adjustable support for cable cross-connecting box
CN203531190U (en) Anti-seismic aluminum alloy stone hanging part
CN205940372U (en) Long -term monitoring devices of bridge three -dimensional displacement
CN204982627U (en) Truss box member port positioner
CN204942174U (en) The cross plate angle controller of a kind of adjustable steel tube tower
CN204346173U (en) A kind of welding stock column cap
CN204295559U (en) A kind of OCTG rack

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: Jiaxing City, Zhejiang province 314300 Haiyan County Yuantong Street salt Scarlett Road No. 99

Patentee after: EOSLIFT AUTOMATION TECHNOLOGY CORP.

Address before: Jiaxing City, Zhejiang province 314300 Haiyan County Yuantong Street salt Scarlett Road No. 99

Patentee before: YIOUSI STORAGE EQUIPMENT CO., LTD.