CN204663008U - A kind of building operations brace type discharging platform - Google Patents

A kind of building operations brace type discharging platform Download PDF

Info

Publication number
CN204663008U
CN204663008U CN201520284483.2U CN201520284483U CN204663008U CN 204663008 U CN204663008 U CN 204663008U CN 201520284483 U CN201520284483 U CN 201520284483U CN 204663008 U CN204663008 U CN 204663008U
Authority
CN
China
Prior art keywords
channel
section steel
tripod
steel pipe
type discharging
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520284483.2U
Other languages
Chinese (zh)
Inventor
关宏生
王庆刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Third Metallurgical Group Co Ltd
Original Assignee
China Third Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Third Metallurgical Group Co Ltd filed Critical China Third Metallurgical Group Co Ltd
Priority to CN201520284483.2U priority Critical patent/CN204663008U/en
Application granted granted Critical
Publication of CN204663008U publication Critical patent/CN204663008U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model relates to technical field of building construction, particularly relate to a kind of building operations brace type discharging platform that the realm of building construction places floor circulation material, comprise material feeding platform, face frontier defense guardrail, tripod, bolt group, it is characterized in that, described material feeding platform is fixedly mounted on tripod, material feeding platform periphery is provided with and faces frontier defense guardrail, and tripod is fixedly mounted on the beam of this layer of building by bolt group, and the channel-section steel one of tripod is close on the beam of substrustion.Compared with prior art, the beneficial effects of the utility model are: structure is simple, easy installation and removal, bearing capacity be twice above, save pre-buried material, with low cost, circulation material efficiency can be improved, improve programming, time saving and energy saving.

Description

A kind of building operations brace type discharging platform
Technical field
The utility model relates to technical field of building construction, particularly relates to a kind of building operations brace type discharging platform that the realm of building construction places floor circulation material.
Background technology
At present, in Building Construction, the discharging platform of construction floor is cable-stayed type entirely, namely reaches about 3m inside floor with two i iron or channel-section steel, fixes, or withstand with many steel pipes with dowel, the four supreme floors of wire rope inclined-pulling in end.There is following defect in the discharging platform of this mode:
1) bearing capacity is little, is generally about 1t;
2) pre-buried a large amount of anchoring piece is needed, waste material;
3) install inconvenience, holding time and resource often, affect programming.
Summary of the invention
For overcoming prior art defect, the technical problem that the utility model solves is to provide a kind of building operations brace type discharging platform, structure is simple, easy installation and removal, bearing capacity are large, save pre-buried material, with low cost, circulation material efficiency can be improved, improve programming.
In order to achieve the above object, the utility model realizes by the following technical solutions:
A kind of building operations brace type discharging platform, comprise material feeding platform, face frontier defense guardrail, tripod, bolt group, it is characterized in that, described material feeding platform is fixedly mounted on tripod, material feeding platform periphery is provided with and faces frontier defense guardrail, tripod is fixedly mounted on the beam of this layer of building by bolt group, and the channel-section steel one of tripod is close on the beam of substrustion.
Wood is stupefied, plank is followed closely system and formed by combining for described material feeding platform.
The described frontier defense guardrail that faces is followed closely system formed by channel-section steel, flitch.
Described tripod is made up of steel pipe one, screw thread, steel pipe two, channel-section steel one, channel-section steel two, steel pipe three, and one end and the channel-section steel two of described steel pipe one are hinged, and the other end is connected with steel pipe two by screw thread, and the other end and the channel-section steel one of steel pipe two are hinged; One end and the channel-section steel one of described steel pipe three are hinged, the other end and channel-section steel two hinged; Described channel-section steel one, channel-section steel two weld together at right angle joint.
Described steel pipe one, steel pipe two-way cross that screw thread is adjustable to be elongated or shortened.
Described channel-section steel one is provided with some bolts hole.
Described bolt group is made up of inner bolt, outer bolt, plastic sleeve, female screws connector, and inner bolt is embedded in the beam of this layer of building in advance, and outer bolt, female screws connector detachably have enough to meet the need to be reused.
Compared with prior art, the beneficial effects of the utility model are: structure is simple, easy installation and removal, bearing capacity be twice above, save pre-buried material, with low cost, circulation material efficiency can be improved, improve programming, time saving and energy saving.
Accompanying drawing explanation
Fig. 1 is side elevation structural representation of the present utility model;
Fig. 2 is plane structure schematic diagram of the present utility model;
Fig. 3 is I portion enlarged diagram in Fig. 2.
In figure: 1-material feeding platform 11-combines wooden stupefied 12-plank 2-and faces frontier defense guardrail 21-channel-section steel 22-flitch 3-tripod 31-steel pipe one 32-screw thread 33-steel pipe two 34-channel-section steel one 35-channel-section steel two 36-bolt hole 37-steel pipe three 4-bolt group 41-inner bolt 42-outer bolt 43-plastic sleeve 44-female screws connector
Detailed description of the invention
Below in conjunction with accompanying drawing, detailed description of the invention of the present utility model is described further:
See Fig. 1-Fig. 3, the utility model relates to a kind of building operations brace type discharging platform, comprise material feeding platform 1, face frontier defense guardrail 2, tripod 3, bolt group 4, described material feeding platform 1 is fixedly mounted on tripod 3, material feeding platform 1 periphery is provided with and faces frontier defense guardrail 2, prevents personnel from falling, and two groups of tripods 3 are fixedly mounted on by bolt group 4 on the beam of this layer of building, one side channel-section steel 1 of tripod 3 is close on the beam of substrustion, and tripod 3 supports material feeding platform 1.
Described material feeding platform 1 is stupefied 11 by combination wood, plank 12 system of following closely forms, to alleviate deadweight.
The described frontier defense guardrail 2 that faces is formed by channel-section steel 21, flitch 22 system of following closely, and not only gains in strength but also alleviate deadweight.
Described tripod 3 is made up of steel pipe 1, screw thread 32, steel pipe 2 33, channel-section steel 1, channel-section steel 2 35, steel pipe 3 37, one end and the channel-section steel 2 35 of described steel pipe 1 are hinged, the other end is connected with steel pipe 2 33 by screw thread 32, and the other end and the channel-section steel 1 of steel pipe 2 33 are hinged; One end and the channel-section steel 1 of described steel pipe 3 37 are hinged, the other end and channel-section steel 2 35 hinged; Described channel-section steel 1, channel-section steel 2 35 weld together at right angle joint.Tripod 3 adopts section steel manufacture, with guaranteed strength, rigidity.
Described steel pipe 1, steel pipe 2 33 elongate or shorten by screw thread 32 is adjustable, according to the Support Position of the difference adjustment brace of building floor height, guarantee tripod 3 reasonable stress, and are passed on the beam column of substrustion by load.
Described channel-section steel 1 is provided with some bolts hole 36, to facilitate the Support Position of adjustment brace.
Described bolt group 4 is made up of inner bolt 41, outer bolt 42, plastic sleeve 43, female screws connector 44, and inner bolt 41 is embedded in the beam of this layer of building in advance, and outer bolt 42, female screws connector 44 detachably turnover are reused, and reduce costs.

Claims (7)

1. a building operations brace type discharging platform, comprise material feeding platform, face frontier defense guardrail, tripod, bolt group, it is characterized in that, described material feeding platform is fixedly mounted on tripod, material feeding platform periphery is provided with and faces frontier defense guardrail, tripod is fixedly mounted on the beam of this layer of building by bolt group, and the channel-section steel one of tripod is close on the beam of substrustion.
2. a kind of building operations brace type discharging platform according to claim 1, is characterized in that, wood is stupefied, plank is followed closely system and formed by combining for described material feeding platform.
3. a kind of building operations brace type discharging platform according to claim 1, is characterized in that, described in face frontier defense guardrail by channel-section steel, flitch follow closely system form.
4. a kind of building operations brace type discharging platform according to claim 1, it is characterized in that, described tripod is made up of steel pipe one, screw thread, steel pipe two, channel-section steel one, channel-section steel two, steel pipe three, one end and the channel-section steel two of described steel pipe one are hinged, the other end is connected with steel pipe two by screw thread, and the other end and the channel-section steel one of steel pipe two are hinged; One end and the channel-section steel one of described steel pipe three are hinged, the other end and channel-section steel two hinged; Described channel-section steel one, channel-section steel two weld together at right angle joint.
5. a kind of building operations brace type discharging platform according to claim 4, is characterized in that, described steel pipe one, steel pipe two-way cross that screw thread is adjustable to be elongated or shortened.
6. a kind of building operations brace type discharging platform according to claim 4, it is characterized in that, described channel-section steel one is provided with some bolts hole.
7. a kind of building operations brace type discharging platform according to claim 1, it is characterized in that, described bolt group is made up of inner bolt, outer bolt, plastic sleeve, female screws connector, inner bolt is embedded in the beam of this layer of building in advance, and outer bolt, female screws connector detachably have enough to meet the need to be reused.
CN201520284483.2U 2015-05-05 2015-05-05 A kind of building operations brace type discharging platform Active CN204663008U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520284483.2U CN204663008U (en) 2015-05-05 2015-05-05 A kind of building operations brace type discharging platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520284483.2U CN204663008U (en) 2015-05-05 2015-05-05 A kind of building operations brace type discharging platform

Publications (1)

Publication Number Publication Date
CN204663008U true CN204663008U (en) 2015-09-23

Family

ID=54133403

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520284483.2U Active CN204663008U (en) 2015-05-05 2015-05-05 A kind of building operations brace type discharging platform

Country Status (1)

Country Link
CN (1) CN204663008U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105484507A (en) * 2015-12-30 2016-04-13 佛山市南海保达建筑机械设备有限公司 Detachable firm and safe building platform
CN111591890A (en) * 2020-04-15 2020-08-28 上海建工四建集团有限公司 Hoisting and sizing traction platform for large-span frame structure prefabricated slab
CN114541723A (en) * 2022-02-18 2022-05-27 北京建工集团有限责任公司 Overhanging type scaffold support structure
CN115303927A (en) * 2021-05-07 2022-11-08 中国核工业二三建设有限公司 Layered hoisting method for large-size variable-section thin-shell type hot chamber shell

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105484507A (en) * 2015-12-30 2016-04-13 佛山市南海保达建筑机械设备有限公司 Detachable firm and safe building platform
CN111591890A (en) * 2020-04-15 2020-08-28 上海建工四建集团有限公司 Hoisting and sizing traction platform for large-span frame structure prefabricated slab
CN115303927A (en) * 2021-05-07 2022-11-08 中国核工业二三建设有限公司 Layered hoisting method for large-size variable-section thin-shell type hot chamber shell
CN115303927B (en) * 2021-05-07 2023-09-08 中国核工业二三建设有限公司 Layered hoisting method for large-size variable-section thin-shell type hot chamber shell
CN114541723A (en) * 2022-02-18 2022-05-27 北京建工集团有限责任公司 Overhanging type scaffold support structure

Similar Documents

Publication Publication Date Title
CN204663008U (en) A kind of building operations brace type discharging platform
CN204728676U (en) A kind of support load-bearing hanger of variable cross-section body of wall
CN204552087U (en) A kind of steel column foot concrete blinding construction equipment
CN204001731U (en) A kind of shuttering supporting vertical rod base fixing device
CN202577347U (en) Waterproof structure of basement steel formwork
CN204199667U (en) Detachable builder's jack corner tripod
CN202706508U (en) Overhanging strength bearing steel beam construction member of scaffold
CN204609295U (en) A kind of square column template anchor ear encloses purlin
CN203188623U (en) Adjustable engineering template supporting fixture
CN204627001U (en) PC structure floor assembled prefabricated post diagonal brace support system
CN204552111U (en) Material distributing machine
CN203939240U (en) A kind of for post or the fixing single-ended mantle fiber split bolt of shear wall formwork
CN204266378U (en) A kind of steel structural embedded parts that can bear larger pulling force
CN201381642Y (en) Crossbeam beam channel joist formwork supporting system
CN205206374U (en) Hold in palm on adjustable top of sagitta self -adaptation for building
CN204456944U (en) A kind of steel back timber for building
CN203334678U (en) Outer wall formwork strengthening system for concrete pouring
CN203412111U (en) Straight threaded sleeve connecting structure at stiffness steel girder node
CN202380740U (en) Opposite-pull bolt for building templates
CN203097262U (en) Scaffold with embedded connecting piece
CN203129566U (en) Simple fixing device of movable scaffold
CN204826636U (en) Ear design support is chosen to plain type roof beam
CN204023885U (en) A kind of Rebar anchor
CN205134941U (en) Stereotype and hang mould in cast -in -place area of superimposed sheet
CN103938885A (en) Method for reinforcing mortise and tenon joint wood frame through bamboo board

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant