CN204661518U CN201520300914.XU CN201520300914U CN204661518U CN 204661518 U CN204661518 U CN 204661518U CN 201520300914 U CN201520300914 U CN 201520300914U CN 204661518 U CN204661518 U CN 204661518U
Authority
CN
China
Prior art keywords
mud
pond
sump
medicine device
leacheate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520300914.XU
Other languages
Chinese (zh)
Inventor
康兴生
顾俊杰
刘亚钦
马涛
黄丽珠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ENVIRONMENTAL ENGINEERING Co Ltd SHANDONG ACADEMY OF ENVIRONMENTAL SCIENCE
Original Assignee
ENVIRONMENTAL ENGINEERING Co Ltd SHANDONG ACADEMY OF ENVIRONMENTAL SCIENCE
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ENVIRONMENTAL ENGINEERING Co Ltd SHANDONG ACADEMY OF ENVIRONMENTAL SCIENCE filed Critical ENVIRONMENTAL ENGINEERING Co Ltd SHANDONG ACADEMY OF ENVIRONMENTAL SCIENCE
Priority to CN201520300914.XU priority Critical patent/CN204661518U/en
Application granted granted Critical
Publication of CN204661518U publication Critical patent/CN204661518U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Treatment Of Sludge (AREA)
  • Processing Of Solid Wastes (AREA)

Abstract

A kind of river heavy metal polluted bed mud dystopy governing system, all molten with the leacheate medicine device of roller-type stone washing machine and screw sand washer is connected; Roller-type stone washing machine is connected with collection mud sump, collection mud sump is connected with screw sand washer, screw sand washer, mud mix modified pond, mud settling sump, ring waste reaction tank and leacheate precipitation pond for recovering be connected successively, mud settling sump is by being connected with vibratory screening apparatus, vibratory screening apparatus is connected with hydrocyclone, and hydrocyclone, mud concentration basin, mud conditioner, mechanical dewatering equipment are connected successively with stable curing whipping device; Mud concentration basin, tail water chemical reaction pond are connected successively with tail water chemical precipitation pond; The molten medicine device of stablizer is connected with vibratory screening apparatus; The molten medicine device of flocculation agent is connected with sludge conditioning pond.This system is convenient to implementation and operation, and regulation effect is good, can not produce secondary pollution.

Description

River heavy metal polluted bed mud dystopy governing system
Technical field
The utility model relates to a kind of for the governing system of the water bodys such as seasonal stream (containing river, river, rivers, river course) by heavy metal polluted bed mud, belongs to the improvement recovery technique field of polluted bed mud.
Background technology
Bed mud is the superficial deposit material of water bottom, is the mixture of microorganism, soil ulmin, soil and silt etc., is deposited on water bottom is formed through long-time physical chemistry, biological action and water body transmission.Bed mud can reflect the historical process that water body develops, and is the important component part of the natural water ecosystems such as river, lake, mouth of the river beach.
Heavy metal in bed mud comes from atmospheric falling dust, precipitation, soil erosion, rainwash, all kinds of sewage, solid refuse and agricultural chemicals etc., there is the features such as chronicity, cumulative bad, latent and non-reversibility, by food chain thousands of hundred times ground enrichment, be finally detrimental to health.
Current countries in the world to the control and plan of Heavy Metal Pollution in Sediments and Treatment process scheme different, especially in China, the factor impacts such as contaminated and Economy Contrast, still do not possess the condition of comprehensively carrying out Heavy Metal Pollution in Sediments control.Different according to the pollution level of polluted water body, in conjunction with the implementation condition of contaminated site, the recovery technique of heavy metal polluted bed mud conventional at present is mainly divided into in-situ treatment technology and dystopy treatment technology.
In-situ treatment technology mainly comprises original position phytoremediation and in-situ materials soverlay technique, its situ phytoremediation is low, simple to operate with its cost, not easily produce the advantages such as secondary pollution and receive much concern, but still it is low to there is processing efficiency, plant growing is subject to the defect such as local climate, the impact of river course flood situation.In-situ materials soverlay technique is at bed mud surface coverage passivating material, block heavy metal to the delivery pathways in water body, affect larger by the physicochemical property of covering material and the water conservancy hydrological characteristics of natural water, and there is no reliable covering material dispensing device at present, realize all even larger without leak source covering difficulty.Therefore, for heavy contamination water body or in-situ treatment difficulty larger time, normal adopt dystopy treatment technology.
Seasonal stream, also known as broken stream, seasonal river, refers to that river is in the dry season, and river stops, riverbed is exposed; Abundance of water season, form current, even flood Pentium.This kind of river flows through the region of high temperature and drought usually, and mean annual discharge is less, but because of heavy rain, snow melt cause flood peak very large.Now because of the mankind to the excessive diversion in river, damming to make live stream become seasonal stream.The continental river of China mostly is seasonal stream.
Dystopy treatment technology is a kind of " Ex-situ remediation method of heavy metal polluted bed mud " disclosed in CN102372406, primarily of sediment digging and conveying, the antiseepage of reparation district and draining, bed mud modifying agent with microbial strains adds, microorganism and plant combined reparation, wastewater treatment and plant harvesting and incineration disposal unit form; Concrete steps first carry out repairing addressing and the Anti-seeping technology in district, adopt engineering method that heavy metal polluted bed mud is dredged again and be transported to and repair district, then the discharging consolidation process of bed mud is carried out, then bed mud modifying agent is added and microbial strains fully mixes with bed mud and cultivates plant, finally gathering in plant after being burned, being transported to hazardous waste landfill landfill or for reclaiming heavy metal element burning ash.The dredging of bed mud dystopy combines with plant absorbing process method by the method, compared with polluted bed mud chemical treatment method, there is low, the eco-friendly advantage of processing cost, but due to needs dredging, it easily produces and pollutes release in Dredging Process, affects Upper water's quality; In addition, for the bed mud that pollution level is heavier, plant is difficult to grow in bed mud, also limit the application of the method.
Therefore, need badly for seasonal stream, in detailed sediment pollution on-site investigation and hydrological survey basis, dispose requirement according to heavy metal contamination process, exploitation is applicable to dystopy governing system and the administering method thereof of seasonal stream hydrologic condition and heavy metal polluted bed mud.
Summary of the invention
The utility model lacks the problem of system and heavy metal polluted bed mud Treatment process targetedly for current seasonal stream, provides a kind of and is convenient to the river heavy metal polluted bed mud dystopy governing system that enforcement, regulation effect are good, can not produce secondary pollution.
River of the present utility model heavy metal polluted bed mud dystopy governing system, by the following technical solutions:
This system, comprises roller-type stone washing machine, collection mud sump, screw sand washer, the molten medicine device of leacheate, mud mixes modified pond, mud settling sump, ring waste reaction tank, leacheate precipitation pond for recovering, vibratory screening apparatus, hydrocyclone, mud concentration basin, mud conditioner, mechanical dewatering equipment, stable curing whipping device, tail water chemical reaction pond, tail water chemical precipitation pond, the molten medicine device of flocculation agent and the molten medicine device of stablizer; All molten with the leacheate medicine device of roller-type stone washing machine and screw sand washer is connected; Roller-type stone washing machine is connected with collection mud sump, collection mud sump is connected with screw sand washer by the lift pump set within it, screw sand washer, mud mix modified pond, mud settling sump, ring waste reaction tank and leacheate precipitation pond for recovering be connected successively, mud settling sump is connected with vibratory screening apparatus by the lift pump set within it, vibratory screening apparatus is connected with hydrocyclone by lift pump, and hydrocyclone, mud concentration basin, mud conditioner, mechanical dewatering equipment are connected successively with stable curing whipping device; Mud concentration basin, tail water chemical reaction pond are connected successively with tail water chemical precipitation pond; The molten medicine device of stablizer is connected with vibratory screening apparatus; The molten medicine device of flocculation agent is connected with sludge conditioning pond.
When said system is run, the bed mud dug out is delivered to roller-type stone washing machine, adopt river drip washing to carry out eccysis on cobble wherein and rubble, the bed mud after drip washing enters mud and mixes modified pond; Enter mud settling sump after modified, carry out mud-water separation, the supernatant liquor after separation is delivered to leacheate precipitation pond for recovering and is processed, and the mud after separation delivers to vibratory screening apparatus through lift pump, screens out the middle fine sand meeting recycling requirement; Mud under Vibration Screen is delivered to hydrocyclone through lift pump, screens out the thick mud meeting recycling requirement; Mud after hydrocyclone process enters mud concentration basin, carry out mud-water separation, supernatant liquor enters tail water chemical reaction pond and chemical precipitation process is carried out in tail water chemical precipitation pond, the bed mud that concentration is higher enters mud conditioner, add flocculation agent by the molten medicine device of flocculation agent, mud is nursed one's health; The bed mud of mud conditioner is pumped to mechanical dewatering equipment and carries out mechanical dehydration; The stable pharmaceutical solution that bed mud after dehydration is prepared through stable curing whipping device and the molten medicine device of stablizer carries out abundant mix and blend reaction; Bed mud after stable curing process is transported to outside closed bed mud transport trolley specifies ultimate disposal place to do rationally to dispose.
The utility model is convenient to implementation and operation, has stronger specific aim, and regulation effect is good, can not produce secondary pollution.
Accompanying drawing explanation
Fig. 1 is the structured flowchart of the utility model seasonal stream heavy metal polluted bed mud dystopy governing system.
In figure: 1, roller-type stone washing machine, 2, mud sump is collected, 3, screw sand washer, 4, the molten medicine device of leacheate, 5, mud mixes modified pond, 6, mud settling sump, 7, ring waste reaction tank, 8, leacheate precipitation pond for recovering, 9, high frequency linear vibratory screening apparatus, 10, hydrocyclone, 11, mud concentration basin, 12, mud conditioner, 13, mechanical dewatering equipment, 14, stable curing whipping device, 15, tail water chemical reaction pond, 16, tail water chemical precipitation pond, 17, the molten medicine device of flocculation agent, 18, the molten medicine device of stablizer.
Embodiment
As shown in Figure 1, seasonal stream heavy metal polluted bed mud dystopy governing system of the present utility model, comprises roller-type stone washing machine 1, collection mud sump 2, screw sand washer 3, the molten medicine device of leacheate 4, mud mixes modified pond 5, mud settling sump 6, ring waste reaction tank 7, leacheate precipitation pond for recovering 8, vibratory screening apparatus 9, hydrocyclone 10, mud concentration basin 11, sludge conditioning pond 12, mechanical dewatering equipment 13, stable curing whipping device 14, tail water chemical reaction pond 15, tail water chemical precipitation pond 16, the molten medicine device of flocculation agent 17 and the molten medicine device 18 of stablizer.All molten with the leacheate medicine device 4 of roller-type stone washing machine 1 and screw sand washer 2 is connected.Roller-type stone washing machine 1 is connected with collection mud sump 2, and collection mud sump 2 is connected with screw sand washer 3 by the lift pump set within it.Screw sand washer 3, mud mix modified pond 5, mud settling sump 6, ring waste reaction tank 7 and leacheate precipitation pond for recovering 8 be connected successively, mud settling sump 6 is connected with vibratory screening apparatus 9 by the lift pump set within it.Vibratory screening apparatus 9 is connected with hydrocyclone 10 by lift pump, and hydrocyclone 10, mud concentration basin 11, mud conditioner 12, mechanical dewatering equipment 13 are connected successively with stable curing whipping device 14.Mud concentration basin 11, tail water chemical reaction pond 15 are connected successively with tail water chemical precipitation pond 16.The molten medicine device 18 of stablizer is connected with vibratory screening apparatus 9.The molten medicine device 17 of flocculation agent is connected with sludge conditioning pond 12.Vibratory screening apparatus 9 can adopt high frequency linear vibratory screening apparatus.The molten medicine device of leacheate 4, the molten medicine device of stablizer 18 can adopt existing Integral dissolving medicine feeding device with the molten medicine device of flocculation agent 17.Mechanical dewatering equipment 13 can adopt plate-and-frame filter press and centrifuge etc.Stable curing whipping device 14 can adopt various stirrer.
The specific implementation process that said system carries out the improvement of seasonal stream heavy metal polluted bed mud dystopy is as described below.
(1) before process, room is studied and field pilot-scale first by experiment, determine the content situation of heavy metal in the size distribution situation of target section bed mud and different-grain diameter bed mud, the on-site ultimate disposal condition of integration project (comprises Land_use change, building materials utilize, landfill and burning etc.) and Financial cost comparative analysis, comprehensively determine the Sieving and casing requirement for the treatment of processes, determine cobble and rubble (particle diameter > 4.75mm), coarse sand (1.18mm < particle diameter < 4.75mm), the concrete Sieving and casing of middle fine sand (0.075mm < particle diameter < 1.18mm) and mud (0mm < particle diameter < 0.075mm) and corresponding device quantity.
(2) bed mud dug out by the geotechnological machinery such as excavator, dozer is due to cobble, rubble and the coarse sand etc. containing Large stone (being often referred to particle diameter > 1.18mm), first roller-type stone washing machine 1 is transported to through closing bed mud transport trolley, river drip washing is adopted to carry out eccysis on cobble wherein and rubble (particle diameter > 4.75mm), the cobble washed out and rubble after testing analysis heavy metal meet related building material and use standard, directly transport outward recycling; As the cobble that washes out and rubble after testing analysis heavy metal exceed standard, the leacheate that the molten medicine device 4 of leacheate can be adopted to prepare carries out chemical leaching to bed mud, by adjusting the concentration of leacheate, guarantee that the cobble of eccysis and rubble meet relevant criterion requirement.Bed mud after drip washing enters collection mud sump 2 subsequently, and screw sand washer 3 delivered to by the lift pump in collection mud sump 2, adopts river drip washing to carry out eccysis coarse sand (1.18mm < particle diameter < 4.75mm) wherein.Bed mud after screw sand washer 3 drip washing enters mud and mixes modified pond 5.
(3) through high-pressure hydraulic wash away cobble, rubble and coarse sand that the bed mud that obtains contains more time, through the direct load drum stone scrubber 1 of mud lift pump, said process can be repeated, also directly can be promoted to mud and mix modified pond 5.
(4) bed mud that mud mixes in modified pond 5 enters mud settling sump 6, carry out mud-water separation, supernatant liquor containing a large amount of leacheate enters ring waste reaction tank 7 and processes, leacheate after process can meet service requirements, enter the molten medicine device 4 of leacheate to recycle, leacheate after process can not meet service requirements but can to meet discharge water body and requires, direct discharge, leacheate after process can not meet service requirements and can not to meet again discharge water body and require, delivers to leacheate precipitation pond for recovering 8 process through lift pump.
(5) mud after mud settling sump 6 mud-water separation delivers to vibratory screening apparatus 9 through lift pump, by adjusting the aperture of the screen cloth of vibratory screening apparatus 9, screen out the middle fine sand (0.075mm < particle diameter < 1.18mm) meeting recycling requirement, the middle fine sand washed out after testing analysis heavy metal meet related resourceization utilize require, directly transport outward recycling; As fine sand in washing out after testing analysis heavy metal exceed standard, the stable pharmaceutical solution adopting the molten medicine device 18 of stablizer to prepare carries out chemical leaching to bed mud, by the concentration of adjustment stable pharmaceutical solution, guarantee that the middle fine sand of eccysis meets relevant criterion requirement.
(6) mud under vibratory screening apparatus 9 sieve is delivered to hydrocyclone 10 through lift pump, screen out the thick mud (0.020mm < particle diameter < 0.075mm) meeting recycling requirement, the thick mud screened out after testing analysis heavy metal meet related resourceization utilize require, directly transport outward recycling.
(7) mud after hydrocyclone 10 processes enters mud concentration basin 11, carry out mud-water separation, supernatant liquor containing stable pharmaceutical and a small amount of heavy metal enters tail water chemical reaction pond 15 and chemical precipitation process is carried out in tail water chemical precipitation pond 16, qualified discharge after tail water after process satisfied discharge water body standard-required, the bed mud that concentration is higher enters mud conditioner 12, in sludge conditioning pond 12, add flocculation agent by the molten medicine device 17 of flocculation agent, mud is nursed one's health.
(8) bed mud of mud conditioner 12 is delivered to mechanical dewatering equipment 13 through lift pump and is carried out mechanical dehydration, and as the bed mud after dehydration can meet the standard-required in corresponding ultimate disposal place, directly outer running is rationally disposed; As the bed mud after dehydration directly can not meet the standard-required in corresponding ultimate disposal place, then control dehydration equipment operation condition, make bed mud water ratio meet the requirement of follow-up stable curing whipping device.
(9) the stable pharmaceutical solution that the bed mud after dehydration is prepared through stable curing whipping device 14 and the molten medicine device of stablizer 18 carries out abundant mix and blend reaction, by the concentration of adjustment stable pharmaceutical solution, guarantee that the bed mud indices after stable curing process meets the standard-required in corresponding ultimate disposal place.
(10) bed mud after stable curing process is transported to outside closed bed mud transport trolley specifies ultimate disposal place to do rationally to dispose.

Claims (1)

1. a river heavy metal polluted bed mud dystopy governing system, it is characterized in that, comprise roller-type stone washing machine, collection mud sump, screw sand washer, the molten medicine device of leacheate, mud mixes modified pond, mud settling sump, ring waste reaction tank, leacheate precipitation pond for recovering, vibratory screening apparatus, hydrocyclone, mud concentration basin, mud conditioner, mechanical dewatering equipment, stable curing whipping device, tail water chemical reaction pond, tail water chemical precipitation pond, the molten medicine device of flocculation agent and the molten medicine device of stablizer; All molten with the leacheate medicine device of roller-type stone washing machine and screw sand washer is connected; Roller-type stone washing machine is connected with collection mud sump, collection mud sump is connected with screw sand washer by the lift pump set within it, screw sand washer, mud mix modified pond, mud settling sump, ring waste reaction tank and leacheate precipitation pond for recovering be connected successively, mud settling sump is connected with vibratory screening apparatus by the lift pump set within it, vibratory screening apparatus is connected with hydrocyclone by lift pump, and hydrocyclone, mud concentration basin, mud conditioner, mechanical dewatering equipment are connected successively with stable curing whipping device; Mud concentration basin, tail water chemical reaction pond are connected successively with tail water chemical precipitation pond; The molten medicine device of stablizer is connected with vibratory screening apparatus; The molten medicine device of flocculation agent is connected with sludge conditioning pond.
CN201520300914.XU 2015-05-12 2015-05-12 River heavy metal polluted bed mud dystopy governing system Expired - Fee Related CN204661518U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520300914.XU CN204661518U (en) 2015-05-12 2015-05-12 River heavy metal polluted bed mud dystopy governing system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520300914.XU CN204661518U (en) 2015-05-12 2015-05-12 River heavy metal polluted bed mud dystopy governing system

Publications (1)

Publication Number Publication Date
CN204661518U true CN204661518U (en) 2015-09-23

Family

ID=54131926

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520300914.XU Expired - Fee Related CN204661518U (en) 2015-05-12 2015-05-12 River heavy metal polluted bed mud dystopy governing system

Country Status (1)

Country Link
CN (1) CN204661518U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109626770A (en) * 2018-12-08 2019-04-16 深圳市升源园林生态有限公司 A kind of pollution of river processing system and processing method
CN110482745A (en) * 2019-09-05 2019-11-22 广东绿富域资源再生科技有限公司 A kind of sewage disposal system and sewage water treatment method of waste incineration slag

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109626770A (en) * 2018-12-08 2019-04-16 深圳市升源园林生态有限公司 A kind of pollution of river processing system and processing method
CN110482745A (en) * 2019-09-05 2019-11-22 广东绿富域资源再生科技有限公司 A kind of sewage disposal system and sewage water treatment method of waste incineration slag

Similar Documents

Publication Publication Date Title
CN104803573A (en) Off-site treatment method and system for bottom mud polluted by heavy metals in river
CN104803572B (en) The dredging of ephemeral stream heavy metal polluted bed mud and dystopy administering method and system
CN103496833B (en) Bottom sediment heavy metal pollution modularized ex situ treatment method
CN102745872B (en) Treatment method and device for riverway and lake heavy metal pollution bottom sludge
CN104226678B (en) A kind of heavy-metal contaminated soil restorative procedure and equipment thereof
CN104874599A (en) Soil ex-situ leaching system and method thereof
CN103588367B (en) Multistage self-control ex-situ treatment system for screening heavy metal-contaminated sediment
WO2018024019A1 (en) Industrial treatment and regeneration system for contaminated bottom mud in rivers and lakes
CN104805799B (en) A kind of ephemeral stream heavy metal polluted bed mud dredging method
CN204396456U (en) A kind of Soil leaching repair system concentrating design concept based on decrement
CN108516658A (en) A kind of cleaning in place, equipment for reclaiming and the method for black-odor riverway bed mud
CN105057340A (en) Chromium-contaminated soil different-position leaching repairing technology and device
CN106277670A (en) A kind of method of fine grained heavily contaminated part bed mud in sharp separation riverbed sludge
CN202785919U (en) Heavy metal polluted sediment processing device for river courses and lakes
CN112588813A (en) Leaching and repairing device for heavy metal and organic matter combined contaminated soil
CN112007936A (en) Muck resourceful treatment system
CN204661518U (en) River heavy metal polluted bed mud dystopy governing system
CN204974702U (en) Chromium -contaminated soil dystopy drip washing prosthetic devices
CN204661517U (en) The dredging of seasonal stream heavy metal polluted bed mud and dystopy governing system
CN203613078U (en) Multi-level auto control screen separation ectopic management system for heavy metal polluted sediment
CN108409073A (en) Ditch mud processing method
CN204620627U (en) A kind of soil heterotopic elution circuit
KR20110029290A (en) Dredged soil processing system and controlling method therefore
JP4123510B2 (en) Contaminated soil treatment system
KR20070019780A (en) Treatment method and apparatus for waste soil which is contained in construction waste

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150923

Termination date: 20170512

CF01 Termination of patent right due to non-payment of annual fee