CN204645671U - Precast beam install structure - Google Patents
Precast beam install structure Download PDFInfo
- Publication number
- CN204645671U CN204645671U CN201520115130.XU CN201520115130U CN204645671U CN 204645671 U CN204645671 U CN 204645671U CN 201520115130 U CN201520115130 U CN 201520115130U CN 204645671 U CN204645671 U CN 204645671U
- Authority
- CN
- China
- Prior art keywords
- precast beam
- hoist engine
- steel column
- connecting pin
- base
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model discloses a kind of precast beam install structure, comprise steel column, steel column is positioned on a precast beam, connecting pin is provided with between steel column and precast beam, more than one of connecting pin, and connecting pin is provided with skid resistant course, steel column top extends on precast beam upper surface lateral surface, be connected with a hoist engine through precast beam bottom it, backplate is connected with between hoist engine and precast beam two sides, backplate adopts triangular structure, in hoist engine, adjusting rod is installed, adjusting rod two ends extend on hoist engine two lateral surface, base is connected with bottom hoist engine, be fixedly connected with between base with hoist engine, the built-in pulley structure of base.This precast beam install structure construction speed is fast, bonding strength is high, holistic resistant behavior good, anti-seismic performance is strong, the problem limited by place when efficiently solving precast beam install, installs and dismantles all very convenient.
Description
Technical field
The utility model relates to a kind of mounting structure, particularly a kind of precast beam install structure.
Background technology
Along with the deep development of urbanization process, abundant Appropriate application urban underground space is more and more subject to the attention of relevant all circles, and in urban construction and civilian construction, the underground excavation degree of depth is more and more darker, and Top-Down Construction Method for Deep Foundation Pit is more and more extensive in urban construction application.And prefabricated keeper is as a building operations instrument indispensable in building, receive the concern of constructor equally, utilize prefabricated keeper to be located, certain operating efficiency can be improved, shorten construction period, save construction cost, can position fast when locating precast beam, and adjusting function requires good, assembling and dismounting all require very convenient, but general precast beam install structure is short of its best orientation performance, causes self structure unstable properties.
Utility model content
The technical problems to be solved in the utility model is: overcome the problems referred to above, provides the precast beam install structure that a kind of speed of application is fast, bonding strength is high, holistic resistant behavior is good, anti-seismic performance is strong.
To achieve these goals, the technical solution adopted in the utility model is such: precast beam install structure of the present utility model, comprise steel column, steel column is positioned on a precast beam, connecting pin is provided with between steel column and precast beam, more than one of connecting pin, and connecting pin is provided with skid resistant course, steel column top extends on precast beam upper surface lateral surface, be connected with a hoist engine through precast beam bottom it, backplate is connected with between hoist engine and precast beam two sides, backplate adopts triangular structure, in hoist engine, adjusting rod is installed, adjusting rod two ends extend on hoist engine two lateral surface, base is connected with bottom hoist engine, be fixedly connected with between base with hoist engine, the built-in pulley structure of base.
Further, as a kind of concrete form of structure, between steel column described in the utility model and precast beam, steel floor is also connected with.
Further, as a kind of concrete form of structure, the built-in several steel bar of precast beam described in the utility model.
Further, as a kind of concrete form of structure, connecting pin described in the utility model adopts movable latch structure.
Further, as a kind of concrete form of structure, hoist engine built-in motor described in the utility model.
Further, as a kind of concrete form of structure, adjusting rod described in the utility model adopts telescopic advance lever structure.
Compared with prior art, the utility model has the advantage of: this precast beam install structure construction speed is fast, bonding strength is high, holistic resistant behavior good, anti-seismic performance is strong, the problem limited by place when efficiently solving precast beam install, installs and dismantles all very convenient.
Accompanying drawing explanation
Below in conjunction with drawings and Examples, the utility model is further illustrated.
Fig. 1 is structural representation of the present utility model;
In figure: 1. steel column; 2. precast beam; 3. connecting pin; 4. backplate; 5. hoist engine; 6. adjusting rod; 7. base.
Detailed description of the invention
By reference to the accompanying drawings the utility model is described in further detail now.These accompanying drawings are the schematic diagram of simplification, only basic structure of the present utility model are described in a schematic way, and therefore it only shows the formation relevant with the utility model.
The preferred embodiment of the utility model precast beam install structure as shown in Figure 1, comprise steel column 1, steel column 1 is positioned on a precast beam 2, connecting pin 3 is provided with between steel column 1 and precast beam 2, more than one of connecting pin 3, and connecting pin 3 is provided with skid resistant course, steel column 1 top extends on precast beam 2 upper surface lateral surface, be connected with a hoist engine 5 through precast beam 2 bottom it, backplate 4 is connected with between hoist engine 5 and precast beam 2 two sides, backplate 4 adopts triangular structure, adjusting rod 6 is installed in hoist engine 5, adjusting rod 6 two ends extend on hoist engine 5 liang of lateral surfaces, base 7 is connected with bottom hoist engine 5, be fixedly connected with between base 7 with hoist engine 5, the built-in pulley structure of base 7, steel floor is also connected with between described steel column 1 and precast beam 2, the built-in several steel bar of described precast beam 2, described connecting pin 3 adopts movable latch structure, described hoist engine 5 built-in motor, described adjusting rod 6 adopts telescopic advance lever structure.
Precast beam install structure construction speed of the present utility model is fast, bonding strength is high, holistic resistant behavior good, anti-seismic performance is strong, the problem limited by place when efficiently solving precast beam install, installs and dismantles all very convenient.Also be connected with steel floor between described steel column 1 and precast beam 2, enhance its resistance; Improve its anatomical connectivity performance further; Conveniently regulate; Described hoist engine 5 built-in motor, is convenient to provide power supply; Described adjusting rod 6 adopts telescopic advance lever structure, and telescopicing performance is very good.
With above-mentioned according to desirable embodiment of the present utility model for enlightenment, by above-mentioned description, relevant staff in the scope not departing from this utility model technological thought, can carry out various change and amendment completely.The technical scope of this utility model is not limited to the content on manual, must determine its technical scope according to right.
Claims (6)
1. a precast beam install structure, comprise steel column, it is characterized in that: steel column is positioned on a precast beam, connecting pin is provided with between steel column and precast beam, more than one of connecting pin, and connecting pin is provided with skid resistant course, steel column top extends on precast beam upper surface lateral surface, be connected with a hoist engine through precast beam bottom it, backplate is connected with between hoist engine and precast beam two sides, backplate adopts triangular structure, in hoist engine, adjusting rod is installed, adjusting rod two ends extend on hoist engine two lateral surface, base is connected with bottom hoist engine, be fixedly connected with between base with hoist engine, the built-in pulley structure of base.
2. precast beam install structure according to claim 1, is characterized in that: be also connected with steel floor between described steel column and precast beam.
3. precast beam install structure according to claim 1, is characterized in that: the built-in several steel bar of described precast beam.
4. precast beam install structure according to claim 1, is characterized in that: described connecting pin adopts movable latch structure.
5. precast beam install structure according to claim 1, is characterized in that: described hoist engine built-in motor.
6. precast beam install structure according to claim 1, is characterized in that: described adjusting rod adopts telescopic advance lever structure.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520115130.XU CN204645671U (en) | 2015-02-25 | 2015-02-25 | Precast beam install structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520115130.XU CN204645671U (en) | 2015-02-25 | 2015-02-25 | Precast beam install structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204645671U true CN204645671U (en) | 2015-09-16 |
Family
ID=54098429
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520115130.XU Active CN204645671U (en) | 2015-02-25 | 2015-02-25 | Precast beam install structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204645671U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104806026A (en) * | 2015-02-25 | 2015-07-29 | 成都格瑞思文化传播有限公司 | Precast beam mounting structure |
-
2015
- 2015-02-25 CN CN201520115130.XU patent/CN204645671U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104806026A (en) * | 2015-02-25 | 2015-07-29 | 成都格瑞思文化传播有限公司 | Precast beam mounting structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203834739U (en) | End steel board connection, positioning and assembly type shear wall structure | |
CN105297978A (en) | Prefabricated assembled type steel-concrete combined beam connected through bolt nails | |
CN204645671U (en) | Precast beam install structure | |
CN207776838U (en) | Full-sleeve full-rotation drill counter-force fork device | |
CN203546944U (en) | Assembly type shear wall | |
CN104806026A (en) | Precast beam mounting structure | |
CN204125931U (en) | Foundation pile structure | |
CN204435421U (en) | A kind of assembling manhole | |
CN103669596B (en) | Prefabricated reinforced concrete column beam-to-column joint structure | |
CN203582323U (en) | Radiator fixing device of truck crane | |
CN206309111U (en) | A kind of line bar location and installation component | |
CN202756000U (en) | Airborne temporary support frame | |
CN203452056U (en) | Diversion tunnel gate lifting device | |
CN204899034U (en) | Prefabricated wall post | |
CN105220707A (en) | A kind of continuous casting rise and fall roller hydraulic cylinder be connected and fixed method | |
CN204940688U (en) | Body of wall | |
CN204662477U (en) | Beam foundation structure | |
CN203855952U (en) | Prefabricated locating component | |
CN104295104B (en) | Box-section crane girder high-strength bolt field installation process | |
CN204530684U (en) | Cement-soil stirring pile construction is with lengthening shaft | |
CN103452128A (en) | Method for lifting base plane of power transmission line tower by adopting steel pipe connecting leg | |
CN203834504U (en) | Structure of basement reverse construction method tower crane foundation | |
CN204023797U (en) | A kind of back timber of steel house and the connection fittings of center stand column | |
CN202610973U (en) | Support chord mechanism for steel structure building | |
CN206052971U (en) | A kind of steel column anchor head |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C41 | Transfer of patent application or patent right or utility model | ||
CB03 | Change of inventor or designer information |
Inventor after: Ye Enbing Inventor before: Zeng Yue |
|
COR | Change of bibliographic data | ||
TR01 | Transfer of patent right |
Effective date of registration: 20160122 Address after: 325100 Wenzhou, Yongjia City, South Street, industrial zone, the lower tong Patentee after: Yongjia County Zhongsen Construction Co. Ltd. Address before: Jinjiang District Jinhua Road Chengdu City, Sichuan province 610000 section of No. 8 Building 1 11 unit 23 floor No. 2336 Patentee before: CHENGDU GRACE CULTURE COMMUNICATION CO., LTD. |