CN204551274U - For the location structure that template of pier column of bridge is installed - Google Patents

For the location structure that template of pier column of bridge is installed Download PDF

Info

Publication number
CN204551274U
CN204551274U CN201520176390.8U CN201520176390U CN204551274U CN 204551274 U CN204551274 U CN 204551274U CN 201520176390 U CN201520176390 U CN 201520176390U CN 204551274 U CN204551274 U CN 204551274U
Authority
CN
China
Prior art keywords
cushion cap
template
post mould
banking stop
model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520176390.8U
Other languages
Chinese (zh)
Inventor
郝磊
姜乐
康旭
朱宇
李宝江
任富芝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Sixth Engineering Division Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN201520176390.8U priority Critical patent/CN204551274U/en
Application granted granted Critical
Publication of CN204551274U publication Critical patent/CN204551274U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a kind of location structure installed for template of pier column of bridge, comprise four the post mould limiting components be embedded on cushion cap, each described post mould limiting component comprises the banking stop of a horizontally disposed spacing base and a perpendicular welding, described banking stop is 1/4 ellipse, and cambered surface is outside pier stud, two relative described banking stops are arranged on the same diagonal of post mould, side-to-side anastomosis in four right angles bottom the cambered surface of four described banking stops and the intersecting lens in cushion cap face and post mould; Described spacing base and cushion cap reinforcement welding are also embedded under cushion cap concrete cover.The utility model, when model sheetinstallat, adopts point banking stop being located at cushion cap four bights, independently locates bottom template, greatly simplifie installation procedure, and can prevent template not just, unstable phenomenon, Template Location precision is high, and efficiency of construction is high.

Description

For the location structure that template of pier column of bridge is installed
Technical field
The utility model relates to a kind of location structure, particularly a kind of location structure installed for template of pier column of bridge.
Background technology
When bridge pier column is constructed, the construction sequence of Pier Formwork installed again by general employing first colligation pier stud reinforcing bar, because template own wt is large, its stability when adopting lifting to install, balance, all poor with the accurate polarization of cage of reinforcement, often need repeatedly repeatedly to adjust and can ensure that template is fixed on design attitude, thus meet every technical requirements, this makes, and model sheetinstallat operation is time-consuming, effort, and position inaccuracy, be unfavorable for the high efficiency and the accuracy that realize Current Engineering Construction.
Summary of the invention
The utility model provides a kind of location structure installed for template of pier column of bridge for solving in known technology the technical problem that exists, and this structure can make model sheetinstallat easy construction, accurate positioning, can accelerating construction progress.
The technical scheme that the utility model is taked for the technical problem existed in solution known technology is: a kind of location structure installed for template of pier column of bridge, comprise four the post mould limiting components be embedded on cushion cap, each described post mould limiting component comprises the banking stop of a horizontally disposed spacing base and a perpendicular welding, described banking stop is 1/4 ellipse, and cambered surface is outside pier stud, two relative described banking stops are arranged on the same diagonal of post mould, side-to-side anastomosis in four right angles bottom the cambered surface of four described banking stops and the intersecting lens in cushion cap face and post mould, described spacing base and cushion cap reinforcement welding are also embedded under cushion cap concrete cover.
The advantage that the utility model has and good effect are: when model sheetinstallat, adopt four banking stops be fixed on cushion cap, independently locate bottom template, decrease the time repeatedly adjusting template position, greatly simplifie installation procedure, and can prevent template not just, unstable phenomenon, Template Location precision is high, and efficiency of construction is high.The utility model successfully solves the problems such as Pier Formwork erector duration, complicated operation, template and cage of reinforcement contraposition be inaccurate, especially cushion cap is connected a difficult problem of installing bottom segment template with pier stud, accurately model sheetinstallat position, optimize working procedure, ensure that construction quality, accelerate construction speed.Simultaneously the utility model also have draw materials convenient, low price, easy to process, the advantage of easy construction.
Accompanying drawing explanation
Fig. 1 and Fig. 2 is structural representation of the present utility model;
Fig. 3 is post mould limiting component structural representation of the present utility model.
In figure: 1, post mould limiting component; 1-1, spacing base; 1-2, banking stop; 2, cushion cap; 3, post mould.
Detailed description of the invention
For summary of the invention of the present utility model, Characteristic can be understood further, hereby exemplify following examples, and coordinate accompanying drawing to be described in detail as follows:
Refer to Fig. 1 ~ Fig. 3, a kind of location structure installed for template of pier column of bridge, comprise four the post mould limiting components 1 be embedded on cushion cap 2, each described post mould limiting component 1 comprises the banking stop 1-2 of a horizontally disposed spacing base 1-1 and perpendicular welding, described banking stop 1-2 is 1/4 ellipse, and cambered surface is outside pier stud, two relative described banking stop 1-2 are arranged on the same diagonal of post mould 3, side-to-side anastomosis in four right angles bottom the cambered surface of four described banking stop 1-2 and the intersecting lens in cushion cap face and post mould 3; Described spacing base 1-1 and cushion cap reinforcement welding are also embedded under cushion cap concrete cover.
Banking stop 1-2 is core of the present utility model, and the key of the utility model application designs and processes suitable banking stop.According to parameters such as the materials of modern pier stud construction experience and template, post mould limiting component 1 adopts the structural part of steel plate as Fig. 3 shows, it is made up of spacing base 1-1 and banking stop 1-2 two parts, by being welded together, spacing base 1-1 plays fixing banking stop 1-2, and banking stop 1-2 freely to be glided accurate locating template by template when installing Pier Formwork.
In the present embodiment, spacing base 1-1 is the rectangle adopting 5mm steel plate to be formed, and rectangular length is 200mm, and wide is 100mm.Banking stop 1-2 adopts 5mm steel plate to be formed, and bottom side length 25mm, can adjust according to the thickness of concrete cover of pier stud, bottom side length length can not exceed thickness of concrete cover, edge-on length of side 50mm.
Work progress of the present utility model:
Before pier cap 2 concreting, according to pier stud design scheme, by surveying setting-out determination pier stud shaping position, 4 post mould limiting components 1 are separately fixed at the relevant position of cushion cap 2, and make its cambered surface outside pier stud, and make side-to-side anastomosis in four right angles bottom the cambered surface of four described banking stop 1-2 and the intersecting lens in cushion cap face and post mould 3, ensure that 4 banking stop 1-2 can make post mould fall design attitude on cushion cap along their cambered surface.Then carry out cushion cap concreting and pre-buried column mould limiting component, make spacing base 1-1 be positioned at below cushion cap concrete cover.When Pier Formwork is installed, just determined the position of template by banking stop 1-2, automatically will be slipped to bottom banking stop, thus decrease the activity duration when dropping on banking stop under formwork hoisting, accurate template position, simplifies operation, improves efficiency of construction.
Although be described preferred embodiment of the present utility model by reference to the accompanying drawings above; but the utility model is not limited to above-mentioned detailed description of the invention; above-mentioned detailed description of the invention is only schematic; be not restrictive; those of ordinary skill in the art is under enlightenment of the present utility model; do not departing under the ambit that the utility model aim and claim protect, can also make a lot of form, these all belong within protection domain of the present utility model.

Claims (1)

1. the location structure installed for template of pier column of bridge, it is characterized in that, comprise four the post mould limiting components be embedded on cushion cap, each described post mould limiting component comprises the banking stop of a horizontally disposed spacing base and a perpendicular welding, described banking stop is 1/4 ellipse, and cambered surface is outside pier stud, two relative described banking stops are arranged on the same diagonal of post mould, side-to-side anastomosis in four right angles bottom the cambered surface of four described banking stops and the intersecting lens in cushion cap face and post mould; Described spacing base and cushion cap reinforcement welding are also embedded under cushion cap concrete cover.
CN201520176390.8U 2015-03-26 2015-03-26 For the location structure that template of pier column of bridge is installed Expired - Fee Related CN204551274U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520176390.8U CN204551274U (en) 2015-03-26 2015-03-26 For the location structure that template of pier column of bridge is installed

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520176390.8U CN204551274U (en) 2015-03-26 2015-03-26 For the location structure that template of pier column of bridge is installed

Publications (1)

Publication Number Publication Date
CN204551274U true CN204551274U (en) 2015-08-12

Family

ID=53826407

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520176390.8U Expired - Fee Related CN204551274U (en) 2015-03-26 2015-03-26 For the location structure that template of pier column of bridge is installed

Country Status (1)

Country Link
CN (1) CN204551274U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107030875A (en) * 2017-05-31 2017-08-11 中国建筑土木建设有限公司 Detachable and adjustable positioning system and positioning method for embedded ribs of prefabricated assembly bearing platform of bridge

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107030875A (en) * 2017-05-31 2017-08-11 中国建筑土木建设有限公司 Detachable and adjustable positioning system and positioning method for embedded ribs of prefabricated assembly bearing platform of bridge

Similar Documents

Publication Publication Date Title
CN209636847U (en) Adjustable tower crane basis built-in fitting accurate positioning instrument
CN201459755U (en) Bolt sleeve for construction of equipment foundation
CN204703182U (en) Crab-bolt stock
CN203783165U (en) Multi-directional accurate adjusting device for embedded part
CN103485539A (en) Construction control method for large direct-buried steel anchor fluke embedded part
CN103603506B (en) Inner support, Counter procedure verticality of stand column controller
CN204551274U (en) For the location structure that template of pier column of bridge is installed
CN108678288A (en) A kind of reinforcing bar positioning integrating device
CN103758213A (en) Precise locating mounting connecting structure of assembled wall boards and beam body
CN205907609U (en) Supplementary utensil in pre -buried hole of bridge supporting base stone location
CN202266034U (en) Fixing device for anchor bolts of embedded type diamond combined steel and concrete column feet
CN205259618U (en) Cast -in -place floor gauge control device of concrete
CN203209591U (en) Standard processing device for big-diameter extra-long pile foundation full pre-assembly reinforcement cage
CN102444315A (en) Device and method for installing and positioning pillars for outdoor switchgears of thermal power plant
CN203544344U (en) Ship displacement lateral positioning device
CN105839914A (en) Adjustable steel beam supporting device and adjustable steel beam supporting system
CN203222810U (en) Steel column and base structure system
CN104196150B (en) A kind of steel plate shear force wall and making method thereof
CN211036707U (en) Device for accurately adjusting verticality of prefabricated stand column
CN204199691U (en) A kind of handrail formwork for placing structure of spiral stairs
CN208968545U (en) For circular tube structure cambered surface node and the aided measurement device on cambered surface vertex
CN103061523B (en) Feeding equipment embedded part mounting device and mounting method using same
CN205637632U (en) Special instrument holder is rectified in installation of shaped steel post
CN201827604U (en) Base for high-precision universal mechanical equipment
CN203499012U (en) Anti-thrust support for arch space truss

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150812